GET FiT Uganda Annual Report 2020 Message from the Ministry of Finance Planning and Economic Development T he year 2020 has in many ways been a challenging year for the GET FiT Programme The global COVID 19 pandemic has affected project construction timelines and operations and several projects experienced damaging floods at the beginning of the year Despite these challenges GET FiT projects have shown immense resilience rectifying destruction due to the floods and continuing construction and operations As a result the Programme is still alive and impacting the Ugandan electricity supply industry and economy in a positive manner In addition to developers other key stakeholders of the Programme have also continued their efforts in 2020 and this is being recognised on the Continent Uganda was ranked number one in the Electricity Regulatory Index for Africa in 2020 by the African Development Bank for the third time in a row further increasing their scoring from 0 75 in 2019 to 0 80 in 2020 This demonstrates that the robust and conducive regulatory environment created by the Electricity Regulatory Authority ERA and other stakeholders in Uganda is further manifesting itself The Ministry of Finance and Economic Planning is proud to have been part of the conceptualisation and implementation of the GET FiT Programme from the very beginning The Ministry has over the years continued to provide an enabling fiscal policy framework for renewable energy through GET FiT Consequently the Programme has had a central role in improving the country s investment environment for the private sector positioning Uganda as a primary example of successful energy sector development in Africa We thank all stakeholders for their continued support and cooperation in this regard The programme has had a central role in improving the country s investment environment for the private sector positioning Uganda as a primary example of successful energy sector development in Africa Matia Kasaija MP Minister of Finance Planning and Economic Development 2 The year 2021 is anticipated to be an exciting year for GET FiT as the three last projects in the portfolio are expected to be commissioned during the year The commissioning of Nyamagasani 1 SHP Nyamagasani 2 SHP and Kikagati SHP will add 36 MW of installed capacity to the portfolio With this addition the portfolio will have an installed capacity of 158 MW contributing with a planned generation of 760 GWh annually to Uganda s energy mix 3

Page 5

GET FiT Uganda Annual Report 2020 Message from the Ministry of Finance Planning and Economic Development T he year 2020 has in many ways been a challenging year for the GET FiT Programme The global COVID 19 pandemic has affected project construction timelines and operations and several projects experienced damaging floods at the beginning of the year Despite these challenges GET FiT projects have shown immense resilience rectifying destruction due to the floods and continuing construction and operations As a result the Programme is still alive and impacting the Ugandan electricity supply industry and economy in a positive manner In addition to developers other key stakeholders of the Programme have also continued their efforts in 2020 and this is being recognised on the Continent Uganda was ranked number one in the Electricity Regulatory Index for Africa in 2020 by the African Development Bank for the third time in a row further increasing their scoring from 0 75 in 2019 to 0 80 in 2020 This demonstrates that the robust and conducive regulatory environment created by the Electricity Regulatory Authority ERA and other stakeholders in Uganda is further manifesting itself The Ministry of Finance and Economic Planning is proud to have been part of the conceptualisation and implementation of the GET FiT Programme from the very beginning The Ministry has over the years continued to provide an enabling fiscal policy framework for renewable energy through GET FiT Consequently the Programme has had a central role in improving the country s investment environment for the private sector positioning Uganda as a primary example of successful energy sector development in Africa We thank all stakeholders for their continued support and cooperation in this regard The programme has had a central role in improving the country s investment environment for the private sector positioning Uganda as a primary example of successful energy sector development in Africa Matia Kasaija MP Minister of Finance Planning and Economic Development 2 The year 2021 is anticipated to be an exciting year for GET FiT as the three last projects in the portfolio are expected to be commissioned during the year The commissioning of Nyamagasani 1 SHP Nyamagasani 2 SHP and Kikagati SHP will add 36 MW of installed capacity to the portfolio With this addition the portfolio will have an installed capacity of 158 MW contributing with a planned generation of 760 GWh annually to Uganda s energy mix 3

Page 6

GET FiT Uganda Annual Report 2020 Message from UK Amidst a challenging year with COVID 19 disruptions and flooding at various GET FiT sites the programme has continued to make progress GET FiT contributed up to 10 of the national electricity supply and ERA continued to demonstrate improved regulatory capacity Progress has also been made on grid interconnections and 1 370 additional full time employee jobs were created in 2020 alone Developer compliance with environmental and social standards continued to be a priority The registered success was however not immune to the impacts of COVID 19 pandemic that defined 2020 and climate induced disruptions Lockdowns and travel restrictions impacted work progress with developers citing the force majeure clause in the contracts Some projects under construction were delayed due to a supply chain failure and COVID 19 control measures that substantially affected the mobility of workers In addition heavy rains during May 2020 flooded three GET FiT sites and resulted in substantial damage to power generation infrastructure Sustainability of small hydropower plants rests on a better environmental and social impact monitoring and ability to supply this power to the national grid We are keen to complete the grid interconnections in western Uganda in 2021 to ensure that all the power generated by GET FiT is transmitted to the national grid We also welcome the 2020 national energy policies focus on increasing investments in power transmission infrastructure as power generation without adequate distribution does not address the problem of limited access and use Beyond GET FiT we recognise that expanding electricity coverage will require more investment in off grid technologies with a clear focus on power for productive use Investments in off grid technologies is well recognised in the revised Uganda s energy policy The success achieved so far demonstrates best practice for similar programmes across Africa and beyond Lessons from GET FiT have already influenced innovations in the renewable energy sector particularly investments to incentivise the private sector leadership in innovations and scale up I thank the donor partners Government of Uganda the private sector and GET FiT implementing partner KfW for this great partnership over the years The success achieved so far demonstrates best practice for similar programmes across Africa and beyond Lessons from GET FiT have already influenced innovations in the renewable energy sector particularly investments to incentivise the private sector leadership in innovations and scale up Andrew Ockenden Development Director British High Commission Kampala 4 T he GET FiT programme is in its final years and has demonstrated success in assisting Uganda to pursue a low carbon and climate resilient development path consistent with the 2020 national energy policy I wish to thank the GET FiT donors European Union Germany Norway and the UK for providing funding to the programme and Government of Uganda for taking the bold step to lead the way in testing the GET FiT model GET FiT success has demonstrated the viability of private sector investments in renewable energy in developing countries The year 2021 will focus on completion of the remaining three power generation projects as well as the critical grid infrastructure marking the completion of the infrastructure development phase of the programme 5

Page 7

GET FiT Uganda Annual Report 2020 Message from UK Amidst a challenging year with COVID 19 disruptions and flooding at various GET FiT sites the programme has continued to make progress GET FiT contributed up to 10 of the national electricity supply and ERA continued to demonstrate improved regulatory capacity Progress has also been made on grid interconnections and 1 370 additional full time employee jobs were created in 2020 alone Developer compliance with environmental and social standards continued to be a priority The registered success was however not immune to the impacts of COVID 19 pandemic that defined 2020 and climate induced disruptions Lockdowns and travel restrictions impacted work progress with developers citing the force majeure clause in the contracts Some projects under construction were delayed due to a supply chain failure and COVID 19 control measures that substantially affected the mobility of workers In addition heavy rains during May 2020 flooded three GET FiT sites and resulted in substantial damage to power generation infrastructure Sustainability of small hydropower plants rests on a better environmental and social impact monitoring and ability to supply this power to the national grid We are keen to complete the grid interconnections in western Uganda in 2021 to ensure that all the power generated by GET FiT is transmitted to the national grid We also welcome the 2020 national energy policies focus on increasing investments in power transmission infrastructure as power generation without adequate distribution does not address the problem of limited access and use Beyond GET FiT we recognise that expanding electricity coverage will require more investment in off grid technologies with a clear focus on power for productive use Investments in off grid technologies is well recognised in the revised Uganda s energy policy The success achieved so far demonstrates best practice for similar programmes across Africa and beyond Lessons from GET FiT have already influenced innovations in the renewable energy sector particularly investments to incentivise the private sector leadership in innovations and scale up I thank the donor partners Government of Uganda the private sector and GET FiT implementing partner KfW for this great partnership over the years The success achieved so far demonstrates best practice for similar programmes across Africa and beyond Lessons from GET FiT have already influenced innovations in the renewable energy sector particularly investments to incentivise the private sector leadership in innovations and scale up Andrew Ockenden Development Director British High Commission Kampala 4 T he GET FiT programme is in its final years and has demonstrated success in assisting Uganda to pursue a low carbon and climate resilient development path consistent with the 2020 national energy policy I wish to thank the GET FiT donors European Union Germany Norway and the UK for providing funding to the programme and Government of Uganda for taking the bold step to lead the way in testing the GET FiT model GET FiT success has demonstrated the viability of private sector investments in renewable energy in developing countries The year 2021 will focus on completion of the remaining three power generation projects as well as the critical grid infrastructure marking the completion of the infrastructure development phase of the programme 5

Page 8

GET FiT Uganda Annual Report 2020 Executive Summary S purring the local investment climate Since the inception of GET FiT Uganda in 2013 17 small power plants have been developed under the Programme thus setting a track record for successful private investments in the Ugandan power sector Additional private investments in smallscale renewable energy that make use of the standardised PPAs developed under the Programme are further evidence that GET FiT has had a sustainable impact on the sector Best in Africa three times in a row The Programme continues to track the sector development to gain an indication on the regulatory performance of the sector For the second year in a row the Electricity Regulatory Authority ERA has reported that more than 90 of performance and compliance reporting to ERA by the electricity sector licensees was timely and complete This is a substantial increase from 20 in 2017 and is well on the way to the target of 100 timely and complete reporting by 2023 In addition the average time taken by ERA to review generation licences for projects with installed capacity between 1 20 MW in 2020 was less than one month already one month faster than the 2023 target The increasingly robust and conducive regulatory environment created by ERA is being recognised internationally in 2020 Uganda was ranked number one on the Electricity Regulatory Index for Africa by the African Development Bank for the third time in a row ERA is still seeking to improve its services through the Regulatory Information Management System RIMS project that is being implemented The project will enhance ERA s information and data collection processes and create automated and improved webbased solutions for its monitoring and stakeholder engagement The project was commenced in November 2020 and is expected to roll out in mid 2021 Job creation GET FiT Uganda continues to have a positive impact on job creation With three projects still under construction in 2020 about 910 workers have been employed through these projects during the year Moreover the fourteen operational GET FiT power plants have employed approximately 6 470 staff throughout the past year This brings the total amount of direct job creation to approximately 11 730 Full Time Equivalent FTE since inception of the Programme in 2013 Furthermore there is significant indirect job creation due to for example local economic growth Around 90 of the workers are Ugandan employees GET FiT adapting to unforeseen external events 2020 has been an eventful year with unforeseen external incidents impacting the Programme The global COVID 19 pandemic emerged in March 2020 leaving the developers of the three remaining projects with travel restrictions and supply chain disruptions Only two months later in May 2020 major floods occurred in Western Uganda which substantially impacted the construction progress of the Nyamagasani 1 and 2 small hydropower plants SHPs This was a major setback to both projects which had to rebuild key project structures Furthermore the floods affected the operation of the Nyamwamba and Lubilia SHPs leading to downtime whilst remedial works were undertaken The three projects under construction have received support from GET FiT throughout the year even though site visits were not possible ensuring as far as possible that the projects were implemented in accordance with Programme requirements and expectations Portfolio output and performance The total portfolio installed capacity has remained at 122 4 MW since 2019 with no additional GET FiT projects commissioned in 2020 The installed capacity is split between 11 small hydropower projects totalling 82 4 MW installed capacity two solar projects with a total installed capacity of 20 MWp and one bagasse co generation project with 20 MW of installed capacity Despite the challenges experienced in 2020 the GET FiT portfolio delivered 380 GWh to the grid during the year yielding approximately 20 higher production than in 2019 The increase in production is predominantly due to more projects being operational throughout the entire year as compared to 2019 when a few projects were commissioned only late 7

Page 9

GET FiT Uganda Annual Report 2020 Executive Summary S purring the local investment climate Since the inception of GET FiT Uganda in 2013 17 small power plants have been developed under the Programme thus setting a track record for successful private investments in the Ugandan power sector Additional private investments in smallscale renewable energy that make use of the standardised PPAs developed under the Programme are further evidence that GET FiT has had a sustainable impact on the sector Best in Africa three times in a row The Programme continues to track the sector development to gain an indication on the regulatory performance of the sector For the second year in a row the Electricity Regulatory Authority ERA has reported that more than 90 of performance and compliance reporting to ERA by the electricity sector licensees was timely and complete This is a substantial increase from 20 in 2017 and is well on the way to the target of 100 timely and complete reporting by 2023 In addition the average time taken by ERA to review generation licences for projects with installed capacity between 1 20 MW in 2020 was less than one month already one month faster than the 2023 target The increasingly robust and conducive regulatory environment created by ERA is being recognised internationally in 2020 Uganda was ranked number one on the Electricity Regulatory Index for Africa by the African Development Bank for the third time in a row ERA is still seeking to improve its services through the Regulatory Information Management System RIMS project that is being implemented The project will enhance ERA s information and data collection processes and create automated and improved webbased solutions for its monitoring and stakeholder engagement The project was commenced in November 2020 and is expected to roll out in mid 2021 Job creation GET FiT Uganda continues to have a positive impact on job creation With three projects still under construction in 2020 about 910 workers have been employed through these projects during the year Moreover the fourteen operational GET FiT power plants have employed approximately 6 470 staff throughout the past year This brings the total amount of direct job creation to approximately 11 730 Full Time Equivalent FTE since inception of the Programme in 2013 Furthermore there is significant indirect job creation due to for example local economic growth Around 90 of the workers are Ugandan employees GET FiT adapting to unforeseen external events 2020 has been an eventful year with unforeseen external incidents impacting the Programme The global COVID 19 pandemic emerged in March 2020 leaving the developers of the three remaining projects with travel restrictions and supply chain disruptions Only two months later in May 2020 major floods occurred in Western Uganda which substantially impacted the construction progress of the Nyamagasani 1 and 2 small hydropower plants SHPs This was a major setback to both projects which had to rebuild key project structures Furthermore the floods affected the operation of the Nyamwamba and Lubilia SHPs leading to downtime whilst remedial works were undertaken The three projects under construction have received support from GET FiT throughout the year even though site visits were not possible ensuring as far as possible that the projects were implemented in accordance with Programme requirements and expectations Portfolio output and performance The total portfolio installed capacity has remained at 122 4 MW since 2019 with no additional GET FiT projects commissioned in 2020 The installed capacity is split between 11 small hydropower projects totalling 82 4 MW installed capacity two solar projects with a total installed capacity of 20 MWp and one bagasse co generation project with 20 MW of installed capacity Despite the challenges experienced in 2020 the GET FiT portfolio delivered 380 GWh to the grid during the year yielding approximately 20 higher production than in 2019 The increase in production is predominantly due to more projects being operational throughout the entire year as compared to 2019 when a few projects were commissioned only late 7

Page 10

GET FiT Uganda in the year as well as a statistically wetter year experienced at many of the hydropower plants resulting in above average generation The generation of the GET FiT Portfolio covered approximately 10 of the total electricity consumption in Uganda which now includes the full effect of commissioning of the Isimba large hydropower project 183 MW in 2019 Several projects in the portfolio are still facing evacuation problems however as grid reinforcements are still outstanding As a result a deemed energy amount of 130 GWh was reported in 2020 meaning that only 75 of the potential energy that could have been delivered to the grid by GET FiT plants was actually realised The last mile The unexpected pandemic and the flooding events early in 2020 have impacted construction progress for the three projects still under construction namely Kikagati Nyamagasani 1 and Nyamagasani 2 This has led to expected commissioning dates during 2021 delayed from the initially planned commissioning in 2020 for all three projects GET FiT continued to monitor the implementation of these remaining projects during 2020 but as a result of international travel restrictions this was limited to remote supervision only 8 Annual Report 2020 Nyamagasani 1 SHP 15 MW experienced substantial delays in 2019 but made some important changes at the end of the year so that construction progress was substantially improved during the first quarter of 2020 Progress was however adversely impacted by the COVID 19 pandemic in addition to major flooding events in May 2020 Nonetheless construction works continued throughout the year and the project is expected to commission in the middle of 2021 Nyamagasani 2 SHP 5 MW is located downstream of Nyamagasani 1 forming a cascade The project experienced similar challenges in 2019 before the progress at the beginning of 2020 was followed by COVID 19 pandemic and flooding challenges later in 2020 The project also continued construction throughout the year and is now planning to commission during the first quarter of 2021 Kikagati SHP 16 MW also experienced delays in construction during 2020 due to the COVID 19 pandemic such as international travel restrictions and adverse impacts to the supply chain Despite these challenges several important design issues were resolved in 2020 In addition construction work at the powerhouse and other key structures was well underway The Developer is aiming to commission the plant in August 2021 Improving the environmental and social performance GET FiT has had a consistent focus on environmental and social performance during construction and operation of the portfolio Dedicated and joint follow up together with ERA combined with developers strengthened efforts resulted in substantial improvements throughout the implementation period More than 50 environmental and social Conditions Precedent CPs were defined across the Requests for Proposals These continue to be followed up and in 2020 an additional five CPs were cleared These improvements and focus on environmental and social development have led to improved compliance with international standards by developers GET FiT will continue to monitor and follow up these issues closely with a particular focus on environmental flows Grid connection Even though 14 GET FiT projects were operational in 2020 and ready to produce and deliver energy to the grid a significant share of this production has been lost due to significant power evacuation constraints Waki Nkusi Sindila Ndugutu and Siti 2 SHPs are among the projects that face the highest deemed energy claims due to grid constraints Some of the projects under construction are also facing the risk of inadequate grid infrastructure at the expected time of commissioning Efforts are being made to improve the situation In addition to working towards better grid connection infrastructure the country is investing in deeper integration of the projects via transmission line and substation upgrades Outlook 2020 was a challenging yet fruitful year the Programme has proven to handle the challenges well and the developers have continued to construct and operate their plants Now GET FiT is looking forward to the commissioning of the remaining three projects benefitting from the hard work in 2020 The GET FiT Steering Committee resolved in 2020 that GET FiT will increase its focus on environmental flows for hydropower projects going forward by establishing a Working Group on environmental minimum flow compliance This group will address relevant issues across the Ugandan power sector based on lessons learned from the implementation of GET FiT Although 2020 did not turn out the way anyone expected GET FiT Uganda is on track to achieving the overarching Programme targets GET FiT has built a large and diverse renewable energy portfolio at record speed in the given context This is only as a result of the dedicated efforts and loyal commitment to Programme goals by Project Developers Ugandan Government Agencies GET FiT donors and all other valuable members of the GET FiT Uganda community 9

Page 11

GET FiT Uganda in the year as well as a statistically wetter year experienced at many of the hydropower plants resulting in above average generation The generation of the GET FiT Portfolio covered approximately 10 of the total electricity consumption in Uganda which now includes the full effect of commissioning of the Isimba large hydropower project 183 MW in 2019 Several projects in the portfolio are still facing evacuation problems however as grid reinforcements are still outstanding As a result a deemed energy amount of 130 GWh was reported in 2020 meaning that only 75 of the potential energy that could have been delivered to the grid by GET FiT plants was actually realised The last mile The unexpected pandemic and the flooding events early in 2020 have impacted construction progress for the three projects still under construction namely Kikagati Nyamagasani 1 and Nyamagasani 2 This has led to expected commissioning dates during 2021 delayed from the initially planned commissioning in 2020 for all three projects GET FiT continued to monitor the implementation of these remaining projects during 2020 but as a result of international travel restrictions this was limited to remote supervision only 8 Annual Report 2020 Nyamagasani 1 SHP 15 MW experienced substantial delays in 2019 but made some important changes at the end of the year so that construction progress was substantially improved during the first quarter of 2020 Progress was however adversely impacted by the COVID 19 pandemic in addition to major flooding events in May 2020 Nonetheless construction works continued throughout the year and the project is expected to commission in the middle of 2021 Nyamagasani 2 SHP 5 MW is located downstream of Nyamagasani 1 forming a cascade The project experienced similar challenges in 2019 before the progress at the beginning of 2020 was followed by COVID 19 pandemic and flooding challenges later in 2020 The project also continued construction throughout the year and is now planning to commission during the first quarter of 2021 Kikagati SHP 16 MW also experienced delays in construction during 2020 due to the COVID 19 pandemic such as international travel restrictions and adverse impacts to the supply chain Despite these challenges several important design issues were resolved in 2020 In addition construction work at the powerhouse and other key structures was well underway The Developer is aiming to commission the plant in August 2021 Improving the environmental and social performance GET FiT has had a consistent focus on environmental and social performance during construction and operation of the portfolio Dedicated and joint follow up together with ERA combined with developers strengthened efforts resulted in substantial improvements throughout the implementation period More than 50 environmental and social Conditions Precedent CPs were defined across the Requests for Proposals These continue to be followed up and in 2020 an additional five CPs were cleared These improvements and focus on environmental and social development have led to improved compliance with international standards by developers GET FiT will continue to monitor and follow up these issues closely with a particular focus on environmental flows Grid connection Even though 14 GET FiT projects were operational in 2020 and ready to produce and deliver energy to the grid a significant share of this production has been lost due to significant power evacuation constraints Waki Nkusi Sindila Ndugutu and Siti 2 SHPs are among the projects that face the highest deemed energy claims due to grid constraints Some of the projects under construction are also facing the risk of inadequate grid infrastructure at the expected time of commissioning Efforts are being made to improve the situation In addition to working towards better grid connection infrastructure the country is investing in deeper integration of the projects via transmission line and substation upgrades Outlook 2020 was a challenging yet fruitful year the Programme has proven to handle the challenges well and the developers have continued to construct and operate their plants Now GET FiT is looking forward to the commissioning of the remaining three projects benefitting from the hard work in 2020 The GET FiT Steering Committee resolved in 2020 that GET FiT will increase its focus on environmental flows for hydropower projects going forward by establishing a Working Group on environmental minimum flow compliance This group will address relevant issues across the Ugandan power sector based on lessons learned from the implementation of GET FiT Although 2020 did not turn out the way anyone expected GET FiT Uganda is on track to achieving the overarching Programme targets GET FiT has built a large and diverse renewable energy portfolio at record speed in the given context This is only as a result of the dedicated efforts and loyal commitment to Programme goals by Project Developers Ugandan Government Agencies GET FiT donors and all other valuable members of the GET FiT Uganda community 9

Page 12

Annual Report 2020 GET FiT PORTFOLIO GET FiT Uganda 17 Projects 158 MW Hydro 760 GWh y 14 Solar PV 118 4 MW 579 7 GWh y 2 20 MW 33 5 GWh y Bagasse 1 20 MW 147 GWh y Projects Commissioned Uganda Rwimi EP Company Limited REPCL commissioned the 5 5 MW Rwimi SHPP in October 2017 and provides about 27 GWh of energy annually to the National Grid of Uganda Capacity Installed In addition to the power generation REPCL also has other local initiatives related to the power plant such as a gravity flow water supply scheme This scheme was constructed to supply potable water to the surrounding community and was implemented in partnership with our Financiers The Scheme has tremendously reduced the time taken to fetch water a task which is traditionally carried out by the women and children This has enabled the community to engage more in subsistence activities and spend extra time with their families while allowing the children to concentrate more on their education 122 77 Hydropower Bagasse REPCL wishes to record our appreciation to all Stakeholders the GET FiT and the Monitoring Agencies for their valuable advice guidance and funding extended for the successful commissioning and operation of the Rwimi SHPP Firdowsy Ismail Chief Executive Officer Rwimi EP Company Limited Of Portfolio Capacity Installed MW Solar PV Jobs Created 11 732 2016 2017 Ugandan Employment 90 2018 2019 2020 0 1 000 Male 4 6 100 M 455 GET FiT Leverage Ratio 165 M GET FiT Grants 10 36 2015 The Sponsors of REPCL look forward to continuing working with GET FiT in the African Region in developing Renewable Energy projects 14 0 2 000 3 000 Female Million USD in Private Investments Leveraged 290 M Private Financing Public Financing 11

Page 13

Annual Report 2020 GET FiT PORTFOLIO GET FiT Uganda 17 Projects 158 MW Hydro 760 GWh y 14 Solar PV 118 4 MW 579 7 GWh y 2 20 MW 33 5 GWh y Bagasse 1 20 MW 147 GWh y Projects Commissioned Uganda Rwimi EP Company Limited REPCL commissioned the 5 5 MW Rwimi SHPP in October 2017 and provides about 27 GWh of energy annually to the National Grid of Uganda Capacity Installed In addition to the power generation REPCL also has other local initiatives related to the power plant such as a gravity flow water supply scheme This scheme was constructed to supply potable water to the surrounding community and was implemented in partnership with our Financiers The Scheme has tremendously reduced the time taken to fetch water a task which is traditionally carried out by the women and children This has enabled the community to engage more in subsistence activities and spend extra time with their families while allowing the children to concentrate more on their education 122 77 Hydropower Bagasse REPCL wishes to record our appreciation to all Stakeholders the GET FiT and the Monitoring Agencies for their valuable advice guidance and funding extended for the successful commissioning and operation of the Rwimi SHPP Firdowsy Ismail Chief Executive Officer Rwimi EP Company Limited Of Portfolio Capacity Installed MW Solar PV Jobs Created 11 732 2016 2017 Ugandan Employment 90 2018 2019 2020 0 1 000 Male 4 6 100 M 455 GET FiT Leverage Ratio 165 M GET FiT Grants 10 36 2015 The Sponsors of REPCL look forward to continuing working with GET FiT in the African Region in developing Renewable Energy projects 14 0 2 000 3 000 Female Million USD in Private Investments Leveraged 290 M Private Financing Public Financing 11

Page 14

GET FiT Uganda Annual Report 2020 Table of Contents 01 About GET FiT Uganda 17 02 Project Portfolio Status 19 03 Environmental Social Performance 47 04 Grid Connection Technical Assistance 53 05 Financial Status 59 06 Programme Monitoring Risk Management 63 07 Other GET FiT Initiatives 73 08 Outlook for 2021 77 12 13

Page 15

GET FiT Uganda Annual Report 2020 Table of Contents 01 About GET FiT Uganda 17 02 Project Portfolio Status 19 03 Environmental Social Performance 47 04 Grid Connection Technical Assistance 53 05 Financial Status 59 06 Programme Monitoring Risk Management 63 07 Other GET FiT Initiatives 73 08 Outlook for 2021 77 12 13

Page 16

GET FiT Uganda Annual Report 2020 List of Abbreviations 14 CO2 Carbon Dioxide COD Commercial Operation Date CP Condition Precedent BEIS Department for Business Energy Industrial Strategy UK DFA Developer Financing Agreement DFID Department for International Development UK now the Foreign Commonwealth Development Office EPC Engineering Procurement and Construction a form of contract ERA Electricity Regulatory Authority E S Environmental and Social ESIA Environmental and Social Impact Assessments EU ITF European Union Infrastructure Trust Fund FCDO Foreign Commonwealth Development Office UK GHG Greenhouse Gas GoU Government of Uganda GWh Gigawatt Hours IFC PS International Finance Corporation Performance Standards IPP Independent Power Producer MEMD Ministry of Energy and Mineral Development MtCO2e Million Tonnes of Carbon Dioxide Equivalent MVA Mega Volt Ampere MW Megawatts of installed power capacity 1 MW 1000 kilowatts PPA Power Purchase Agreement RE Renewable Energy REA Rural Electrification Agency RFP Request for Proposal SC Steering Committee SHP Small Hydropower Plant SPCC Sector Planning and Coordination Committee SSA Sub Saharan Africa TA Technical Assistance UEDCL Uganda Electricity Distribution Company Limited UETCL Uganda Electricity Transmission Company Limited 15

Page 17

GET FiT Uganda Annual Report 2020 List of Abbreviations 14 CO2 Carbon Dioxide COD Commercial Operation Date CP Condition Precedent BEIS Department for Business Energy Industrial Strategy UK DFA Developer Financing Agreement DFID Department for International Development UK now the Foreign Commonwealth Development Office EPC Engineering Procurement and Construction a form of contract ERA Electricity Regulatory Authority E S Environmental and Social ESIA Environmental and Social Impact Assessments EU ITF European Union Infrastructure Trust Fund FCDO Foreign Commonwealth Development Office UK GHG Greenhouse Gas GoU Government of Uganda GWh Gigawatt Hours IFC PS International Finance Corporation Performance Standards IPP Independent Power Producer MEMD Ministry of Energy and Mineral Development MtCO2e Million Tonnes of Carbon Dioxide Equivalent MVA Mega Volt Ampere MW Megawatts of installed power capacity 1 MW 1000 kilowatts PPA Power Purchase Agreement RE Renewable Energy REA Rural Electrification Agency RFP Request for Proposal SC Steering Committee SHP Small Hydropower Plant SPCC Sector Planning and Coordination Committee SSA Sub Saharan Africa TA Technical Assistance UEDCL Uganda Electricity Distribution Company Limited UETCL Uganda Electricity Transmission Company Limited 15

Page 18

GET FiT Uganda Annual Report 2020 01 About GET FiT Uganda T he GET FiT Uganda Programme was officially launched on May 31st 2013 The Programme which was developed by the Government of Uganda and the Electricity Regulatory Authority ERA in close cooperation with KfW Development Bank is designed to leverage private investments into renewable energy generation projects in Uganda GET FiT is supported by the Governments of Norway the United Kingdom Germany and the EU through the EU Africa Infrastructure Fund The main objective of the GET FiT Programme is to assist Uganda in pursuing a climate resilient low carbon development path resulting in growth poverty reduction and climate change mitigation by facilitating private sector involvement and improving the framework conditions for private investments in renewable energy In Uganda GET FiT is fast tracking a portfolio of 17 small scale renewable energy RE projects promoted by private developers and with a total installed capacity of 158 MW This will yield approximately 760 GWh of clean energy production per year transforming Uganda s energy mix within a period of 3 5 years and resulting in 16 Emission reductions of roughly 10 million tonnes of CO2 in the 20 year lifespan of Power Purchase Agreements PPAs An increase in Uganda s energy production by about 20 and thus a contribution to tackling an anticipated supply shortage Facilitating or significantly improving access to energy for at least 200 000 additional households approximately 1 2 million people also due to strengthening of regional grids Leveraging more than USD 450 million in public and private investments for RE generation projects with a limited amount of results based grant funding A more comprehensive description of the specific tools and approaches applied by GET FiT to address the challenges faced in the Ugandan power sector the governance structure of the Programme and key activities and achievements so far is found in the GET FiT Annual Reports produced since 2013 Following the success of the Programme in Uganda the GET FiT concept has been replicated in other countries with the launch of GET FiT Zambia in 2018 and the anticipated launch of GET FiT Mozambique during 2021 17

Page 19

GET FiT Uganda Annual Report 2020 01 About GET FiT Uganda T he GET FiT Uganda Programme was officially launched on May 31st 2013 The Programme which was developed by the Government of Uganda and the Electricity Regulatory Authority ERA in close cooperation with KfW Development Bank is designed to leverage private investments into renewable energy generation projects in Uganda GET FiT is supported by the Governments of Norway the United Kingdom Germany and the EU through the EU Africa Infrastructure Fund The main objective of the GET FiT Programme is to assist Uganda in pursuing a climate resilient low carbon development path resulting in growth poverty reduction and climate change mitigation by facilitating private sector involvement and improving the framework conditions for private investments in renewable energy In Uganda GET FiT is fast tracking a portfolio of 17 small scale renewable energy RE projects promoted by private developers and with a total installed capacity of 158 MW This will yield approximately 760 GWh of clean energy production per year transforming Uganda s energy mix within a period of 3 5 years and resulting in 16 Emission reductions of roughly 10 million tonnes of CO2 in the 20 year lifespan of Power Purchase Agreements PPAs An increase in Uganda s energy production by about 20 and thus a contribution to tackling an anticipated supply shortage Facilitating or significantly improving access to energy for at least 200 000 additional households approximately 1 2 million people also due to strengthening of regional grids Leveraging more than USD 450 million in public and private investments for RE generation projects with a limited amount of results based grant funding A more comprehensive description of the specific tools and approaches applied by GET FiT to address the challenges faced in the Ugandan power sector the governance structure of the Programme and key activities and achievements so far is found in the GET FiT Annual Reports produced since 2013 Following the success of the Programme in Uganda the GET FiT concept has been replicated in other countries with the launch of GET FiT Zambia in 2018 and the anticipated launch of GET FiT Mozambique during 2021 17

Page 20

GET FiT Uganda Annual Report 2020 02 Project Portfolio Status 2 1 Portfolio Status 2 1 1 Overview A t the start of 2020 14 of the 17 small scale RE projects supported by GET FiT were operational and delivering energy to the Ugandan grid The final three small hydropower projects SHP still under construction were expected to commence commercial operation later in the year finally unlocking the remaining power system contribution from the GET FiT Programme The year 2020 however brought unforeseeable challenges that affected both operational projects and those still under construction alike Firstly the global COVID 19 pandemic which emerged early during 2020 and persisted throughout the year significantly impacted the three projects still under construction Subsequently and in parallel with the ongoing coronavirus pandemic major flooding events in Western Uganda adversely impacted two operational projects as well as two of the projects still under construction These challenges are described in further detail below As a result the three projects still under construction at the start of 2020 were substantially delayed and are now expected to complete construction and commence commercial operation during 2021 The 14 projects operational at the start of 2020 which provide a combined installed capacity of 122 4 MW approximately 77 of the total installed capacity to be implemented under the Programme 158 4 MW nonetheless delivered nearly 380 GWh to the grid corresponding to approximately 10 of the total grid electricity supplied in Uganda Cumulatively the overall power supplied to the Ugandan grid by GET FiT supported projects thus far has totalled more than 1 TWh 2 1 2 Coronavirus The coronavirus pandemic emerged during early 2020 and severely disrupted international travel and shipping as well as the movement of people within Uganda During the second half of March 2020 the developers of the three remaining projects still 18 under construction the Nyamagasani 1 and 2 SHPs and the Kikagati SHP notified the Uganda Electricity Transmission Company Limited UETCL and KfW of a Force Majeure event in accordance with the requirements of their respective Power Purchase Agreements PPA At that stage the Developers notified that travel restrictions imposed worldwide had affected the movement of key project staff as well as significant supply chain disruptions for many of their suppliers Effective from 18 March 2020 the GoU imposed restrictions on certain activities within Uganda to manage the spread of the virus including various nationwide lockdowns and curfews which were partially lifted in May 2020 although it was generally understood that the Ugandan construction industry was allowed to continue with precautions during this period International travel restrictions were relaxed as of 1 October 2020 with the re opening of Entebbe International Airport The Developers reported continuing adverse impacts throughout much of 2020 resulting in construction delays including the supply of equipment travel restrictions national curfews and quarantine procedures Whilst it was not possible for the construction sites to be visited by the GET FiT Implementation Consultant and KfW during 2020 due to the travel restrictions imposed during the ongoing coronavirus pandemic dialogue with the Developers and their construction teams was maintained throughout the year to check on the status of key issues as well as general progress towards achieving Commercial Operation Date COD 2 1 3 Major Flood Events During May 2020 major floods in Western Uganda substantially impacted the construction progress of the Nyamagasani 1 and 2 SHPs as well as operation of the Nyamwamba and Lubilia SHPs All four projects experienced varying degrees of flood damage and required major reconstruction efforts 19

Page 21

GET FiT Uganda Annual Report 2020 02 Project Portfolio Status 2 1 Portfolio Status 2 1 1 Overview A t the start of 2020 14 of the 17 small scale RE projects supported by GET FiT were operational and delivering energy to the Ugandan grid The final three small hydropower projects SHP still under construction were expected to commence commercial operation later in the year finally unlocking the remaining power system contribution from the GET FiT Programme The year 2020 however brought unforeseeable challenges that affected both operational projects and those still under construction alike Firstly the global COVID 19 pandemic which emerged early during 2020 and persisted throughout the year significantly impacted the three projects still under construction Subsequently and in parallel with the ongoing coronavirus pandemic major flooding events in Western Uganda adversely impacted two operational projects as well as two of the projects still under construction These challenges are described in further detail below As a result the three projects still under construction at the start of 2020 were substantially delayed and are now expected to complete construction and commence commercial operation during 2021 The 14 projects operational at the start of 2020 which provide a combined installed capacity of 122 4 MW approximately 77 of the total installed capacity to be implemented under the Programme 158 4 MW nonetheless delivered nearly 380 GWh to the grid corresponding to approximately 10 of the total grid electricity supplied in Uganda Cumulatively the overall power supplied to the Ugandan grid by GET FiT supported projects thus far has totalled more than 1 TWh 2 1 2 Coronavirus The coronavirus pandemic emerged during early 2020 and severely disrupted international travel and shipping as well as the movement of people within Uganda During the second half of March 2020 the developers of the three remaining projects still 18 under construction the Nyamagasani 1 and 2 SHPs and the Kikagati SHP notified the Uganda Electricity Transmission Company Limited UETCL and KfW of a Force Majeure event in accordance with the requirements of their respective Power Purchase Agreements PPA At that stage the Developers notified that travel restrictions imposed worldwide had affected the movement of key project staff as well as significant supply chain disruptions for many of their suppliers Effective from 18 March 2020 the GoU imposed restrictions on certain activities within Uganda to manage the spread of the virus including various nationwide lockdowns and curfews which were partially lifted in May 2020 although it was generally understood that the Ugandan construction industry was allowed to continue with precautions during this period International travel restrictions were relaxed as of 1 October 2020 with the re opening of Entebbe International Airport The Developers reported continuing adverse impacts throughout much of 2020 resulting in construction delays including the supply of equipment travel restrictions national curfews and quarantine procedures Whilst it was not possible for the construction sites to be visited by the GET FiT Implementation Consultant and KfW during 2020 due to the travel restrictions imposed during the ongoing coronavirus pandemic dialogue with the Developers and their construction teams was maintained throughout the year to check on the status of key issues as well as general progress towards achieving Commercial Operation Date COD 2 1 3 Major Flood Events During May 2020 major floods in Western Uganda substantially impacted the construction progress of the Nyamagasani 1 and 2 SHPs as well as operation of the Nyamwamba and Lubilia SHPs All four projects experienced varying degrees of flood damage and required major reconstruction efforts 19

Page 22

GET FiT Uganda At the Nyamagasani 1 and 2 SHPs the Developer again notified UETCL and KfW of a further Force Majeure event relating to flood impacts which were expected to result in substantial construction delays Flood related damage was sustained to key project structures construction equipment and resulted in severely impeded access and construction progress at key project locations Design modifications were incorporated where appropriate and substantial reconstruction efforts were required ultimately resulting in further delays in achieving the COD At the Nyamwamba SHP significant damage was sustained at the intake structure and powerhouse resulting in unplanned outages lasting several months Key structures were subsequently reconstructed or repaired and design modifications incorporated to minimise the risk of future damage The powerhouse was inundated as a result of the flooding and required substantial clean up remedial works and replacement of damaged equipment In the short term the Developer assembled a temporary generating unit from salvaged parts to enable generation to recommence from early October albeit at substantially reduced capacity The full installed capacity of the plant is expected to be restored early during 2021 Flood damage was also sustained at the intake and powerhouse of the Lubilia SHP though the extent was less severe than experienced at the Nyamwamba SHP resulting in a substantially shorter period of operating downtime Design modifications and reconstruction efforts were again required to restore the robustness of key project structures to a standard similar to the pre flood condition 2 1 4 Progress in 2020 and Remaining Challenges Despite the various challenges construction of the three remaining SHPs continued throughout most of 2020 By the end of 2020 remedial and reconstruction works to flood damaged structures of the Nyamagasani 2 SHP were nearing completion with the project anticipated to complete construction and synchronise to the grid during the first quarter of 2021 The long term solution for evacuating power from the Nyamagasani 1 and 2 SHPs was further delayed during 2020 and the Developer subsequently Annual Report 2020 invested in upgrades to the existing nearby grid to enable the plant to be connected commissioning tests completed and evacuation of at least a limited plant output prior to completion of the permanent power evacuation solution Commissioning works and commercial operations during the first quarter of 2021 therefore appeared feasible Table 1 Overview of construction start and commissioning dates for GET FIT supported projects as well as prolonged unplanned internal outages during 2020 Construction Start Commissioning Prolonged unplanned internal outages in 2020 Kakira CHP Q2 2012 Q2 2014 2 months At the Nyamagasani 1 SHP access to the weir site had been reinstated following the May 2020 floods and new construction plant mobilised to enable the works to progress Completion of the weir and upper headrace works remained critical to achieving commercial operation where there was still potential for progress to be affected by further rainfall and high flow events during the statistically wetter period of the year between March and May Commercial operation during the middle of 2021 nonetheless appeared feasible Soroti Solar PV Q1 2016 Q4 2016 Siti 1 SHP Q1 2015 Q2 2017 Muvumbe SHP Q3 2015 Q2 2017 Tororo Solar PV Q1 2017 Q3 2017 Rwimi SHP Q3 2015 Q4 2017 Lubilia SHP Q1 2016 Q2 2018 2 months Nkusi SHP Q2 2015 Q2 2018 1 month Construction works at the final GET FiT support project the Kikagati SHP also progressed throughout 2020 with a predominant focus at the powerhouse the most substantial powerhouse within the portfolio Whilst a number of important design issues had been resolved by the end of 2020 a few key issues were still outstanding and required urgent attention early during 2021 The Developer still planned to progressively commission and bring into operation the three generating units over several months in the second half of 2021 with all three units expected to be operational and COD achieved during the third quarter of 2021 However the completion of major project structures was forecast to occur during the fourth quarter of 2021 and substantial construction works and risks remained Construction completion during early 2022 appeared more realistic although the completion of these works and associated potential construction delays are not anticipated to affect generation Nyamwamba SHP Q4 2015 Q2 2018 7 months Waki SHP Q2 2015 Q4 2018 Sindila SHP Q1 2017 Q2 2019 Siti 2 SHP Q3 2016 Q3 2019 Kyambura SHP Q3 2017 Q3 2019 Ndugutu SHP Q2 2017 Q4 2019 Nyamagasani 2 SHP Q1 2017 Q1 2020 N A Nyamagasani 1 SHP Q1 2017 Q3 2020 N A Kikagati SHP Q4 2017 Q3 20212 N A Table 1 summarises the construction start and commissioning dates for all GET FiT supported projects as well as periods of prolonged unplanned internal outages1 experienced by selected projects during 2020 The expected dates for achieving completion of commissioning tests and commencing commercial operations for the three remaining projects are also shown Project 2 1 5 Consequences of Delayed CODs The Steering Committee concluded in 2019 that all projects still under construction beyond the extended GET FiT Programme deadline of 31 October 20193 would remain eligible for GET FiT support provided that the Developers of those projects agreed to a DFA addendum The addendum stipulated that for each full month of delay beyond 31 October 2019 a penalty of 5 to the COD subsidy payment would be imposed The addendum was agreed to by the Developers of the three projects 2 3 1 For the purpose of this report a prolonged unplanned internal outage is taken to mean any unplanned internal outage lasting two weeks or more 20 still in construction during 2020 the Nyamagasani 1 and 2 SHPs and the Kikagati SHP which will all be subject to these further reductions in the final subsidy amount In September 2020 the Steering Committee further agreed that the DFA COD deadline may be extended where there are genuine and justifiable Force Majeure claims The actual delay arising out of the Force Majeure events and the associated magnitude of Whilst the Developer of the Kikagati SHP expects to commission all three generating units and achieve COD in Q3 2021 the construction of key project structures will continue and are not forecast to be completed until Q4 2021 GET FiT estimates that construction works will not be completed until Q1 2022 The GET FiT Steering Committee resolved in 2018 that at the discretion of the GoU represented by KfW the contractual deadline for all projects still constructing beyond 31 December 2018 would be extended to 31 October 2019 21

Page 23

GET FiT Uganda At the Nyamagasani 1 and 2 SHPs the Developer again notified UETCL and KfW of a further Force Majeure event relating to flood impacts which were expected to result in substantial construction delays Flood related damage was sustained to key project structures construction equipment and resulted in severely impeded access and construction progress at key project locations Design modifications were incorporated where appropriate and substantial reconstruction efforts were required ultimately resulting in further delays in achieving the COD At the Nyamwamba SHP significant damage was sustained at the intake structure and powerhouse resulting in unplanned outages lasting several months Key structures were subsequently reconstructed or repaired and design modifications incorporated to minimise the risk of future damage The powerhouse was inundated as a result of the flooding and required substantial clean up remedial works and replacement of damaged equipment In the short term the Developer assembled a temporary generating unit from salvaged parts to enable generation to recommence from early October albeit at substantially reduced capacity The full installed capacity of the plant is expected to be restored early during 2021 Flood damage was also sustained at the intake and powerhouse of the Lubilia SHP though the extent was less severe than experienced at the Nyamwamba SHP resulting in a substantially shorter period of operating downtime Design modifications and reconstruction efforts were again required to restore the robustness of key project structures to a standard similar to the pre flood condition 2 1 4 Progress in 2020 and Remaining Challenges Despite the various challenges construction of the three remaining SHPs continued throughout most of 2020 By the end of 2020 remedial and reconstruction works to flood damaged structures of the Nyamagasani 2 SHP were nearing completion with the project anticipated to complete construction and synchronise to the grid during the first quarter of 2021 The long term solution for evacuating power from the Nyamagasani 1 and 2 SHPs was further delayed during 2020 and the Developer subsequently Annual Report 2020 invested in upgrades to the existing nearby grid to enable the plant to be connected commissioning tests completed and evacuation of at least a limited plant output prior to completion of the permanent power evacuation solution Commissioning works and commercial operations during the first quarter of 2021 therefore appeared feasible Table 1 Overview of construction start and commissioning dates for GET FIT supported projects as well as prolonged unplanned internal outages during 2020 Construction Start Commissioning Prolonged unplanned internal outages in 2020 Kakira CHP Q2 2012 Q2 2014 2 months At the Nyamagasani 1 SHP access to the weir site had been reinstated following the May 2020 floods and new construction plant mobilised to enable the works to progress Completion of the weir and upper headrace works remained critical to achieving commercial operation where there was still potential for progress to be affected by further rainfall and high flow events during the statistically wetter period of the year between March and May Commercial operation during the middle of 2021 nonetheless appeared feasible Soroti Solar PV Q1 2016 Q4 2016 Siti 1 SHP Q1 2015 Q2 2017 Muvumbe SHP Q3 2015 Q2 2017 Tororo Solar PV Q1 2017 Q3 2017 Rwimi SHP Q3 2015 Q4 2017 Lubilia SHP Q1 2016 Q2 2018 2 months Nkusi SHP Q2 2015 Q2 2018 1 month Construction works at the final GET FiT support project the Kikagati SHP also progressed throughout 2020 with a predominant focus at the powerhouse the most substantial powerhouse within the portfolio Whilst a number of important design issues had been resolved by the end of 2020 a few key issues were still outstanding and required urgent attention early during 2021 The Developer still planned to progressively commission and bring into operation the three generating units over several months in the second half of 2021 with all three units expected to be operational and COD achieved during the third quarter of 2021 However the completion of major project structures was forecast to occur during the fourth quarter of 2021 and substantial construction works and risks remained Construction completion during early 2022 appeared more realistic although the completion of these works and associated potential construction delays are not anticipated to affect generation Nyamwamba SHP Q4 2015 Q2 2018 7 months Waki SHP Q2 2015 Q4 2018 Sindila SHP Q1 2017 Q2 2019 Siti 2 SHP Q3 2016 Q3 2019 Kyambura SHP Q3 2017 Q3 2019 Ndugutu SHP Q2 2017 Q4 2019 Nyamagasani 2 SHP Q1 2017 Q1 2020 N A Nyamagasani 1 SHP Q1 2017 Q3 2020 N A Kikagati SHP Q4 2017 Q3 20212 N A Table 1 summarises the construction start and commissioning dates for all GET FiT supported projects as well as periods of prolonged unplanned internal outages1 experienced by selected projects during 2020 The expected dates for achieving completion of commissioning tests and commencing commercial operations for the three remaining projects are also shown Project 2 1 5 Consequences of Delayed CODs The Steering Committee concluded in 2019 that all projects still under construction beyond the extended GET FiT Programme deadline of 31 October 20193 would remain eligible for GET FiT support provided that the Developers of those projects agreed to a DFA addendum The addendum stipulated that for each full month of delay beyond 31 October 2019 a penalty of 5 to the COD subsidy payment would be imposed The addendum was agreed to by the Developers of the three projects 2 3 1 For the purpose of this report a prolonged unplanned internal outage is taken to mean any unplanned internal outage lasting two weeks or more 20 still in construction during 2020 the Nyamagasani 1 and 2 SHPs and the Kikagati SHP which will all be subject to these further reductions in the final subsidy amount In September 2020 the Steering Committee further agreed that the DFA COD deadline may be extended where there are genuine and justifiable Force Majeure claims The actual delay arising out of the Force Majeure events and the associated magnitude of Whilst the Developer of the Kikagati SHP expects to commission all three generating units and achieve COD in Q3 2021 the construction of key project structures will continue and are not forecast to be completed until Q4 2021 GET FiT estimates that construction works will not be completed until Q1 2022 The GET FiT Steering Committee resolved in 2018 that at the discretion of the GoU represented by KfW the contractual deadline for all projects still constructing beyond 31 December 2018 would be extended to 31 October 2019 21

Page 24

Annual Report 2020 GET FiT Uganda DFA COD deadline extension will be determined by GET FiT subject to legal review assessment of progress on site and decisions by UETCL and ERA with respect to the PPAs The cut off date for final subsidy disbursements made under the GFPPM will nevertheless remain as 2023 24 For operational projects affected by Force Majeure events during 2020 the Steering Committee determined that the DFA term may be extended where justified but no later than the 2023 24 cut off date and provided funding is still available at that stage The lack of a dedicated power evacuation line at the Siti 2 SHP continued to greatly hinder generation resulting in significant deemed energy claims until the temporary evacuation solution was energised at the end of 2020 Unusually high outages also continued to be experienced at the Siti 1 and Waki SHPs see Figure 1 as well as at the Sindila and Ndugutu SHPs where the combined output of the adjacent plants continues to be constrained until the permanent evacuation solution is implemented which is expected in 2021 With these exceptions the grid availability at GET FiT support projects averaged approximately 95 whereas when grid availability at all plants is included the average was substantially lower at approximately 83 2 1 6 Portfolio Operating Performance in 2020 The timely implementation of new power evacuation infrastructure and upgrades to the existing grid continued to be a major issue for several of the SHPs during 2020 Of the 14 operational projects three SHPs had still only partially completed their respective commissioning activities as a result of a combination of grid and water availability related issues In each case improvements to the existing grid and or the completion of new lines were ongoing throughout most of 2020 and were required to enable power generation at full capacity The availability of the plants to generate electricity during 2020 was generally in line with the expected range for a portfolio of new generation projects Only three of the RE projects were substantially below the average plant availability across the portfolio the Kakira cogeneration plant combined heat and power plant CHP and the Lubilia and Nyamwamba SHPs Generation at the Kakira CHP has been constrained since commencing commercial operation as a result of a low availability of fuel this is discussed further in Section 2 2 1 The relatively low availability of the Nyamwamba SHP was predominantly a result of the flood related damage and ongoing construction repairs and replacement of equipment during the second half of 2020 as described above At the Lubilia SHP a landslide alongside the headrace canal in November 2020 resulted in further substantial unplanned outages until the end of the year whilst remedial works were ongoing The energy delivered to the Ugandan grid by the GET FiT supported projects is summarised in Figure 2 below shown as a proportion of the annual energy estimated at application stage The potential energy4 of plants during 2020 is also shown which accounts for deemed energy as a result of grid outages as well as missed generation as a result of internal outages such as experienced at the Lubilia and Nyamwamba SHPs The total energy delivered during 2020 across the portfolio was 380 GWh which represents 81 of the total planned annual generation at application stage For the small hydropower projects in the portfolio Figure 2 indicates that the generation potential of the plants during 2020 was on average 120 5 of the annual generation estimated at application stage indicating that 2020 was statistically a wetter than average year The key exceptions are the adjacent Sindila and Ndugutu SHPs located on the western side of the Rwenzori Mountain range where the energy potential in 2020 is shown to be below the annual energy estimated for each plant at application stage Further generating records in the coming years will improve certainty with respect to the energy potential of the GET FiT RE projects compared with the estimates made at application stage 190 170 150 130 110 100 90 90 70 80 50 70 30 60 Waki SHP 7 Tororo Solar PV Soroti Solar PV Siti 2 SHP Siti 1 SHP Sindila SHP Rwimi SHP Nkusi SHP Ndugutu SHP Energy delivered as proportion of estimated annual energy 10 Energy potential as proportion of estimated annual energy Figure 2 Energy Delivered and Energy Potential During 2020 for all Operational GET FiT Supported Projects Grid Availability Plant Availability Figure 1 Grid and Plant Availability During 2020 for all Operational GET FiT Supported Projects Waki SHP Tororo Solar PV Soroti Solar PV Siti 2 SHP Siti 1 SHP Sindila SHP Rwimi SHP Nyamwamba SHP Nkusi SHP Ndugutu SHP Muvumbe SHP Lubilia SHP Kyambura SHP Kakira CHP 0 22 Nyamwamba SHP 6 20 Muvumbe SHP 30 Lubilia SHP Kakira CHP 40 Kyambura SHP 10 50 The potential energy or generation potential of a Renewable Energy project shall be taken in this report to mean the total energy actually delivered and deemed to have been delivered accounting for grid outages combined with electricity not generated due to internal plant outages The potential energy therefore reflects water availability during the year compared with the planned annual generation at application stage 5 The 120 excludes the energy potential of the Nyamwamba and Waki SHPs Energy potential data for the Nyamwamba SHP are incomplete for 2020 due to the damage sustained to project structures as a result of the May 2020 floods At Waki SHP uncertainties persist with respect to the method of calculating Deemed Energy which contributes to the potential energy see footnote above Nonetheless the generation potential at Waki SHP during 2020 was still estimated to be greater than 100 of that planned at application stage Uncertainties surrounding the method of Deemed Energy calculation are expected to be resolved early during 2021 6 Due to a flooding event the information about energy potential is incomplete and therefore not presented 7 Uncertainties persist with respect to the method of calculating Deemed Energy Therefore the energy potential is not presented for Waki 4 23

Page 25

Annual Report 2020 GET FiT Uganda DFA COD deadline extension will be determined by GET FiT subject to legal review assessment of progress on site and decisions by UETCL and ERA with respect to the PPAs The cut off date for final subsidy disbursements made under the GFPPM will nevertheless remain as 2023 24 For operational projects affected by Force Majeure events during 2020 the Steering Committee determined that the DFA term may be extended where justified but no later than the 2023 24 cut off date and provided funding is still available at that stage The lack of a dedicated power evacuation line at the Siti 2 SHP continued to greatly hinder generation resulting in significant deemed energy claims until the temporary evacuation solution was energised at the end of 2020 Unusually high outages also continued to be experienced at the Siti 1 and Waki SHPs see Figure 1 as well as at the Sindila and Ndugutu SHPs where the combined output of the adjacent plants continues to be constrained until the permanent evacuation solution is implemented which is expected in 2021 With these exceptions the grid availability at GET FiT support projects averaged approximately 95 whereas when grid availability at all plants is included the average was substantially lower at approximately 83 2 1 6 Portfolio Operating Performance in 2020 The timely implementation of new power evacuation infrastructure and upgrades to the existing grid continued to be a major issue for several of the SHPs during 2020 Of the 14 operational projects three SHPs had still only partially completed their respective commissioning activities as a result of a combination of grid and water availability related issues In each case improvements to the existing grid and or the completion of new lines were ongoing throughout most of 2020 and were required to enable power generation at full capacity The availability of the plants to generate electricity during 2020 was generally in line with the expected range for a portfolio of new generation projects Only three of the RE projects were substantially below the average plant availability across the portfolio the Kakira cogeneration plant combined heat and power plant CHP and the Lubilia and Nyamwamba SHPs Generation at the Kakira CHP has been constrained since commencing commercial operation as a result of a low availability of fuel this is discussed further in Section 2 2 1 The relatively low availability of the Nyamwamba SHP was predominantly a result of the flood related damage and ongoing construction repairs and replacement of equipment during the second half of 2020 as described above At the Lubilia SHP a landslide alongside the headrace canal in November 2020 resulted in further substantial unplanned outages until the end of the year whilst remedial works were ongoing The energy delivered to the Ugandan grid by the GET FiT supported projects is summarised in Figure 2 below shown as a proportion of the annual energy estimated at application stage The potential energy4 of plants during 2020 is also shown which accounts for deemed energy as a result of grid outages as well as missed generation as a result of internal outages such as experienced at the Lubilia and Nyamwamba SHPs The total energy delivered during 2020 across the portfolio was 380 GWh which represents 81 of the total planned annual generation at application stage For the small hydropower projects in the portfolio Figure 2 indicates that the generation potential of the plants during 2020 was on average 120 5 of the annual generation estimated at application stage indicating that 2020 was statistically a wetter than average year The key exceptions are the adjacent Sindila and Ndugutu SHPs located on the western side of the Rwenzori Mountain range where the energy potential in 2020 is shown to be below the annual energy estimated for each plant at application stage Further generating records in the coming years will improve certainty with respect to the energy potential of the GET FiT RE projects compared with the estimates made at application stage 190 170 150 130 110 100 90 90 70 80 50 70 30 60 Waki SHP 7 Tororo Solar PV Soroti Solar PV Siti 2 SHP Siti 1 SHP Sindila SHP Rwimi SHP Nkusi SHP Ndugutu SHP Energy delivered as proportion of estimated annual energy 10 Energy potential as proportion of estimated annual energy Figure 2 Energy Delivered and Energy Potential During 2020 for all Operational GET FiT Supported Projects Grid Availability Plant Availability Figure 1 Grid and Plant Availability During 2020 for all Operational GET FiT Supported Projects Waki SHP Tororo Solar PV Soroti Solar PV Siti 2 SHP Siti 1 SHP Sindila SHP Rwimi SHP Nyamwamba SHP Nkusi SHP Ndugutu SHP Muvumbe SHP Lubilia SHP Kyambura SHP Kakira CHP 0 22 Nyamwamba SHP 6 20 Muvumbe SHP 30 Lubilia SHP Kakira CHP 40 Kyambura SHP 10 50 The potential energy or generation potential of a Renewable Energy project shall be taken in this report to mean the total energy actually delivered and deemed to have been delivered accounting for grid outages combined with electricity not generated due to internal plant outages The potential energy therefore reflects water availability during the year compared with the planned annual generation at application stage 5 The 120 excludes the energy potential of the Nyamwamba and Waki SHPs Energy potential data for the Nyamwamba SHP are incomplete for 2020 due to the damage sustained to project structures as a result of the May 2020 floods At Waki SHP uncertainties persist with respect to the method of calculating Deemed Energy which contributes to the potential energy see footnote above Nonetheless the generation potential at Waki SHP during 2020 was still estimated to be greater than 100 of that planned at application stage Uncertainties surrounding the method of Deemed Energy calculation are expected to be resolved early during 2021 6 Due to a flooding event the information about energy potential is incomplete and therefore not presented 7 Uncertainties persist with respect to the method of calculating Deemed Energy Therefore the energy potential is not presented for Waki 4 23

Page 26

GET FiT Uganda Annual Report 2020 2 1 7 Expected Portfolio Output Figure 4 provides a schematic illustration of the merit order effect of the GET FiT portfolio considering the current installed capacity of 122 4 MW The merit order effect refers to the reduction of highly priced peak energy that the utility needs to buy As indicated in the graph the GET FiT portfolio green area is off setting expensive thermal generation grey area that is associated with high GHG emissions Due to GET FiT approximately 14 of total generation capacity has been added thereby reducing generation from the heavy fuel oil plants in the country Only two small power plants have been commissioned in 2020 with a total installed capacity of 16 5 MW This means that the effect of the GET FiT Portfolio on the country s energy supply was largely the same in 2020 as it was in 2019 Notably the I simba HPP commissioned in 2019 increased the installed capacity in the country by 183 MW In addition the commissioning of the 600 MW Karuma Hydropower Project is expected in 2021 Therefore based on ERA reporting it is expected that Uganda will face a significant surplus generation capacity compared to demand in the short to medium term Schematic Representation of Merit Order in 2020 25 Demand Curve 20 Price in USc Marginal Power Price Solar PV Bagasse 15 10 MW 5 Kiira Nalubaale Hydro 0 Solar PV 0 100 Isimba 200 300 Bujagali 400 500 600 Fossil Fuel 700 800 900 1000 Capacity in MW Bagasse 25 GWh year 20 Hydro Figure 3 GET FiT Portfolio Build Up Price in USc An overview of the total planned installed capacity of the portfolio and how it is distributed across the supported technologies is presented in Figure 3 The overall portfolio capacity amounts to a total of 158 4 MW representing approximately 93 of the original Programme target of 170 MW The difference between the planned capacity of the current portfolio and the original target is partly due to a reduction in the overall Programme funding in earlier years combined with a lower share of bagasse biomass than originally anticipated Nevertheless adding an installed capacity of over 150 MW to the Ugandan electricity supply network is a significant achievement and truly reflects the successful impact of the GET FiT Programme Demand Curve Marginal Power Price excl GET FiT Portfolio 15 Merit Order Effect 14 GET FiT Contribution 10 Marginal Power Price 5 Kiira Nalubaale 0 0 100 Isimba 200 300 Bujagali 400 500 600 GET FiT 700 Fossil Fuel 800 900 1000 Capacity in MW Large Hydro Small Hydro Bagasse GET FiT Thermal Figure 4 Schematic Representation of Uganda s Merit Order and the Effect of the GET FiT Portfolio Note The merit order effect is expressed in marginal energy price not average energy price Both thermal power plants have 7 MW generation guaranteed in their PPA Additionally most power plants have take or pay PPAs Therefore the illustration is only a schematic representation of the effects In 2020 a 10 MW solar plant and a 6 5 MW hydropower plant were commissioned 24 25

Page 27

GET FiT Uganda Annual Report 2020 2 1 7 Expected Portfolio Output Figure 4 provides a schematic illustration of the merit order effect of the GET FiT portfolio considering the current installed capacity of 122 4 MW The merit order effect refers to the reduction of highly priced peak energy that the utility needs to buy As indicated in the graph the GET FiT portfolio green area is off setting expensive thermal generation grey area that is associated with high GHG emissions Due to GET FiT approximately 14 of total generation capacity has been added thereby reducing generation from the heavy fuel oil plants in the country Only two small power plants have been commissioned in 2020 with a total installed capacity of 16 5 MW This means that the effect of the GET FiT Portfolio on the country s energy supply was largely the same in 2020 as it was in 2019 Notably the I simba HPP commissioned in 2019 increased the installed capacity in the country by 183 MW In addition the commissioning of the 600 MW Karuma Hydropower Project is expected in 2021 Therefore based on ERA reporting it is expected that Uganda will face a significant surplus generation capacity compared to demand in the short to medium term Schematic Representation of Merit Order in 2020 25 Demand Curve 20 Price in USc Marginal Power Price Solar PV Bagasse 15 10 MW 5 Kiira Nalubaale Hydro 0 Solar PV 0 100 Isimba 200 300 Bujagali 400 500 600 Fossil Fuel 700 800 900 1000 Capacity in MW Bagasse 25 GWh year 20 Hydro Figure 3 GET FiT Portfolio Build Up Price in USc An overview of the total planned installed capacity of the portfolio and how it is distributed across the supported technologies is presented in Figure 3 The overall portfolio capacity amounts to a total of 158 4 MW representing approximately 93 of the original Programme target of 170 MW The difference between the planned capacity of the current portfolio and the original target is partly due to a reduction in the overall Programme funding in earlier years combined with a lower share of bagasse biomass than originally anticipated Nevertheless adding an installed capacity of over 150 MW to the Ugandan electricity supply network is a significant achievement and truly reflects the successful impact of the GET FiT Programme Demand Curve Marginal Power Price excl GET FiT Portfolio 15 Merit Order Effect 14 GET FiT Contribution 10 Marginal Power Price 5 Kiira Nalubaale 0 0 100 Isimba 200 300 Bujagali 400 500 600 GET FiT 700 Fossil Fuel 800 900 1000 Capacity in MW Large Hydro Small Hydro Bagasse GET FiT Thermal Figure 4 Schematic Representation of Uganda s Merit Order and the Effect of the GET FiT Portfolio Note The merit order effect is expressed in marginal energy price not average energy price Both thermal power plants have 7 MW generation guaranteed in their PPA Additionally most power plants have take or pay PPAs Therefore the illustration is only a schematic representation of the effects In 2020 a 10 MW solar plant and a 6 5 MW hydropower plant were commissioned 24 25

Page 28

Annual Report 2020 GET FiT Uganda 2 2 Projects In the following sections projects comprising the GET FiT portfolio are described in more detail highlighting notable developments and power generation8 in 2020 Figure 5 provides an overview of the location of the respective projects of the portfolio Soroti Solar PV Waki SHP Siti II SHP Siti I SHP Nkusi SHP Sindila SHP Ndugutu SHP Rwimi SHP Lubilia SHP Tororo Solar PV Kakira CHP Nyamwamba SHP Nyamagasani I II SHPs Kyambura SHP Kikagati SHP Muvumbe SHP Hydropower Bagasse Solar PV Figure 5 Map of GET FiT Portfolio 8 26 Generation data is presented as provided by the developers The accuracy and appropriateness of the generation levels presented in the following sections will be reviewed by GET FiT only upon submission of annual subsidy payment requests as per contractually agreed procedures 27

Page 29

Annual Report 2020 GET FiT Uganda 2 2 Projects In the following sections projects comprising the GET FiT portfolio are described in more detail highlighting notable developments and power generation8 in 2020 Figure 5 provides an overview of the location of the respective projects of the portfolio Soroti Solar PV Waki SHP Siti II SHP Siti I SHP Nkusi SHP Sindila SHP Ndugutu SHP Rwimi SHP Lubilia SHP Tororo Solar PV Kakira CHP Nyamwamba SHP Nyamagasani I II SHPs Kyambura SHP Kikagati SHP Muvumbe SHP Hydropower Bagasse Solar PV Figure 5 Map of GET FiT Portfolio 8 26 Generation data is presented as provided by the developers The accuracy and appropriateness of the generation levels presented in the following sections will be reviewed by GET FiT only upon submission of annual subsidy payment requests as per contractually agreed procedures 27

Page 30

GET FiT Uganda Annual Report 2020 Soroti Solar PV Kakira CHP Operational Operational T Bagasse Capacity 20 0 in MW Planned Generation 147 0 in GWh year Total Investment 56 8 in million USD GET FiT Commitment 7 1 in million USD he Kakira co generation plant using bagasse from sugar production located in the Jinja District Eastern Uganda was the first operational project supported by GET FiT Power production during the first years of operation was heavily constrained by a low availability of sugar cane caused by increased local competition over sugar cane from multiple new sugar factories The sugar cane supply improved during the past few years basically due to good weather and increased numbers of farmers as well as the expansion of their own satellite cane fields Kakira has expanded its own satellite cane fields to reduce dependency on sugar cane supply by independent farmers to ensure more reliable raw material supply In 2020 even with a higher supply of sugar cane the production from the GET FiT Kakira plant was still only 65 2 GWh due to two main technical problems The need to replace a 11 kV 33 kV transformer which connects Kakira to the grid and problems with the thrust bearing which required a repair of the bearing assembly The grid availability has varied between 87 and 99 over monthly intervals with the average grid availability over the year being 94 Annual Generation in GWh T he Soroti 10 MWp Solar PV was the second project supported by GET FiT Uganda to commission in November 2016 It was the first grid connected solar plant in Uganda and was at commissioning the largest project of its kind in the East and Central African Region The project is located in Soroti District Eastern Uganda The annual production has been very stable across the years Compared to 2019 the number of external outages was reduced in 2020 These outages have mainly been unplanned except for some repair work to the grid The total generation from the plant in 2020 was 16 0 GWh which is the same production which has been obtained yearly since the first full years of operation in 2017 This is slightly less than the planned annual production of 17 5 GWh which was predicted at commissioning The deemed energy due to grid failure and grid maintenance was reduced from 1 24 GWh in 2019 to 0 96 GWh in 2020 The average grid availability in 2020 was 97 4 Without downtime of the grid the total delivered energy could have been 17 0 GWh The project reported some internal outages at the end of January and in February due to two faulty transformers This reduced annual production slightly Solar PV Capacity Planned Generation 35 44 2016 2017 2018 76 2019 65 17 5 in GWh year Total Investment 14 3 in million USD GET FiT Commitment 9 6 in million USD Annual Generation in GWh Estimated Generation 87 10 0 in MW 16 16 16 16 2017 2018 2019 2020 5 2016 2020 2 00 1 80 14 00 1 60 12 00 Energy GWh Uganda 1 40 10 00 1 20 0 80 6 00 0 60 4 00 0 40 2 00 0 00 0 20 0 00 Jan Feb Mar Apr May Planned Energy GWh Jun Jul Aug Sep Oct Nov Actual Energy GWh Figure 6 Kakira Bagasse Planned versus Actual Energy Output 2020 28 Uganda 1 00 8 00 Dec Planned Energy GWh Actual Energy GWh Deemed Energy GWh Figure 7 Soroti Solar PV Planned versus Actual Energy Output 2020 29 Estimated Generation

Page 31

GET FiT Uganda Annual Report 2020 Soroti Solar PV Kakira CHP Operational Operational T Bagasse Capacity 20 0 in MW Planned Generation 147 0 in GWh year Total Investment 56 8 in million USD GET FiT Commitment 7 1 in million USD he Kakira co generation plant using bagasse from sugar production located in the Jinja District Eastern Uganda was the first operational project supported by GET FiT Power production during the first years of operation was heavily constrained by a low availability of sugar cane caused by increased local competition over sugar cane from multiple new sugar factories The sugar cane supply improved during the past few years basically due to good weather and increased numbers of farmers as well as the expansion of their own satellite cane fields Kakira has expanded its own satellite cane fields to reduce dependency on sugar cane supply by independent farmers to ensure more reliable raw material supply In 2020 even with a higher supply of sugar cane the production from the GET FiT Kakira plant was still only 65 2 GWh due to two main technical problems The need to replace a 11 kV 33 kV transformer which connects Kakira to the grid and problems with the thrust bearing which required a repair of the bearing assembly The grid availability has varied between 87 and 99 over monthly intervals with the average grid availability over the year being 94 Annual Generation in GWh T he Soroti 10 MWp Solar PV was the second project supported by GET FiT Uganda to commission in November 2016 It was the first grid connected solar plant in Uganda and was at commissioning the largest project of its kind in the East and Central African Region The project is located in Soroti District Eastern Uganda The annual production has been very stable across the years Compared to 2019 the number of external outages was reduced in 2020 These outages have mainly been unplanned except for some repair work to the grid The total generation from the plant in 2020 was 16 0 GWh which is the same production which has been obtained yearly since the first full years of operation in 2017 This is slightly less than the planned annual production of 17 5 GWh which was predicted at commissioning The deemed energy due to grid failure and grid maintenance was reduced from 1 24 GWh in 2019 to 0 96 GWh in 2020 The average grid availability in 2020 was 97 4 Without downtime of the grid the total delivered energy could have been 17 0 GWh The project reported some internal outages at the end of January and in February due to two faulty transformers This reduced annual production slightly Solar PV Capacity Planned Generation 35 44 2016 2017 2018 76 2019 65 17 5 in GWh year Total Investment 14 3 in million USD GET FiT Commitment 9 6 in million USD Annual Generation in GWh Estimated Generation 87 10 0 in MW 16 16 16 16 2017 2018 2019 2020 5 2016 2020 2 00 1 80 14 00 1 60 12 00 Energy GWh Uganda 1 40 10 00 1 20 0 80 6 00 0 60 4 00 0 40 2 00 0 00 0 20 0 00 Jan Feb Mar Apr May Planned Energy GWh Jun Jul Aug Sep Oct Nov Actual Energy GWh Figure 6 Kakira Bagasse Planned versus Actual Energy Output 2020 28 Uganda 1 00 8 00 Dec Planned Energy GWh Actual Energy GWh Deemed Energy GWh Figure 7 Soroti Solar PV Planned versus Actual Energy Output 2020 29 Estimated Generation

Page 32

GET FiT Uganda Annual Report 2020 Siti 1 SHP Muvumbe SHP Operational Hydropower Capacity 6 1 in MW Planned Generation 25 0 in GWh year Total Investment 15 0 in million USD GET FiT Commitment 3 6 in million USD in GWh 20 20 24 2018 2019 Substantial grid failures and outages continued throughout 2020 with grid availability reportedly as low as 58 on average comparable to 2019 Lost generation due to grid failures and outages accounting for water availability equated to approximately 27 of the potential plant output which is especially high and similar in magnitude to previous years of operation The long term power evacuation solution for the Siti 1 SHP and downstream Siti 2 SHP comprises a new 132 kV transmission line between Mbale and Bulambuli which is expected to substantially improve the availability and reliability of power evacuation from the plants Completion of the permanent evacuation solution is expected during 2024 25 11 2017 T his run of river hydropower plant is located in Bukwo District in Eastern Uganda and has been operational since May 2017 During 2020 the project delivered 24 5 GWh of energy to the grid Adjusting for the partial availability of the power evacuation line the energy output of the plant during 2020 would have reportedly been equivalent to 134 of the average energy estimated at application stage Annual Generation Estimated Generation Operational A persistent and serious non compliance with E S operating phase permit conditions relating to release of the minimum flow requirement at the weir was finally reported as resolved during 2020 T his run of river hydropower project is located in Kabale District in South Western Uganda and has been operational since May 2017 During 2020 the Project generated 35 2 GWh Combined with the energy generated since achieving commercial operation in 2017 the Project has contributed more than 100 GWh of electricity to the Ugandan grid The availability of the grid to evacuate power has been relatively consistent since the plant commenced commercial operations with an average availability in 2020 of more than 94 Nonetheless lost power generation as a result of grid failures and external outages approximately equated to 7 of the potential generation for the year energy delivered plus deemed energy Adjusting for the partial availability of the power evacuation line the cumulative energy output of the plant would instead have been 38 0 GWh approximately equivalent to 121 of the average energy estimated at application stage A post COD site visit undertaken to the site during 2018 and subsequent discussions with the Developer resulted in installation of a new retrofitted arrangement to release and monitor the minimum flow The new arrangement is intended to correct deviations from the minimum release requirements and was completed during 2020 2020 2021e Hydropower Capacity 6 5 in MW Planned Generation 31 0 in GWh year Total Investment 12 5 in million USD GET FiT Commitment 4 5 in million USD Annual Generation in GWh 28 29 2018 2019 35 31 16 2017 2020 2021e 4 50 6 00 4 00 3 50 5 00 3 00 Uganda 4 00 2 50 2 00 Uganda 3 00 1 50 2 00 1 00 1 00 0 50 0 00 0 00 Planned Energy GWh Actual Energy GWh Deemed Energy GWh Figure 8 Siti 1 SHP Planned versus Actual Energy Output 2020 30 Planned Energy GWh Actual Energy GWh Deemed Energy GWh Figure 9 Muvumbe SHP Planned versus Actual Energy Output 2020 31 Estimated Generation

Page 33

GET FiT Uganda Annual Report 2020 Siti 1 SHP Muvumbe SHP Operational Hydropower Capacity 6 1 in MW Planned Generation 25 0 in GWh year Total Investment 15 0 in million USD GET FiT Commitment 3 6 in million USD in GWh 20 20 24 2018 2019 Substantial grid failures and outages continued throughout 2020 with grid availability reportedly as low as 58 on average comparable to 2019 Lost generation due to grid failures and outages accounting for water availability equated to approximately 27 of the potential plant output which is especially high and similar in magnitude to previous years of operation The long term power evacuation solution for the Siti 1 SHP and downstream Siti 2 SHP comprises a new 132 kV transmission line between Mbale and Bulambuli which is expected to substantially improve the availability and reliability of power evacuation from the plants Completion of the permanent evacuation solution is expected during 2024 25 11 2017 T his run of river hydropower plant is located in Bukwo District in Eastern Uganda and has been operational since May 2017 During 2020 the project delivered 24 5 GWh of energy to the grid Adjusting for the partial availability of the power evacuation line the energy output of the plant during 2020 would have reportedly been equivalent to 134 of the average energy estimated at application stage Annual Generation Estimated Generation Operational A persistent and serious non compliance with E S operating phase permit conditions relating to release of the minimum flow requirement at the weir was finally reported as resolved during 2020 T his run of river hydropower project is located in Kabale District in South Western Uganda and has been operational since May 2017 During 2020 the Project generated 35 2 GWh Combined with the energy generated since achieving commercial operation in 2017 the Project has contributed more than 100 GWh of electricity to the Ugandan grid The availability of the grid to evacuate power has been relatively consistent since the plant commenced commercial operations with an average availability in 2020 of more than 94 Nonetheless lost power generation as a result of grid failures and external outages approximately equated to 7 of the potential generation for the year energy delivered plus deemed energy Adjusting for the partial availability of the power evacuation line the cumulative energy output of the plant would instead have been 38 0 GWh approximately equivalent to 121 of the average energy estimated at application stage A post COD site visit undertaken to the site during 2018 and subsequent discussions with the Developer resulted in installation of a new retrofitted arrangement to release and monitor the minimum flow The new arrangement is intended to correct deviations from the minimum release requirements and was completed during 2020 2020 2021e Hydropower Capacity 6 5 in MW Planned Generation 31 0 in GWh year Total Investment 12 5 in million USD GET FiT Commitment 4 5 in million USD Annual Generation in GWh 28 29 2018 2019 35 31 16 2017 2020 2021e 4 50 6 00 4 00 3 50 5 00 3 00 Uganda 4 00 2 50 2 00 Uganda 3 00 1 50 2 00 1 00 1 00 0 50 0 00 0 00 Planned Energy GWh Actual Energy GWh Deemed Energy GWh Figure 8 Siti 1 SHP Planned versus Actual Energy Output 2020 30 Planned Energy GWh Actual Energy GWh Deemed Energy GWh Figure 9 Muvumbe SHP Planned versus Actual Energy Output 2020 31 Estimated Generation

Page 34

GET FiT Uganda Annual Report 2020 Tororo Solar PV Rwimi SHP Operational Operational T Solar PV Capacity 10 0 in MW Planned Generation 16 0 in GWh year Total Investment 19 6 in million USD GET FiT Commitment he Tororo Solar PV project is located in Tororo District Eastern Uganda The 10 MWp power plant commenced commercial operations in September 2017 and so became the second grid connected solar power plant in Uganda The project was developed by Building Energy but during 2020 the majority shareholder changed Further in 2020 the majority shareholder changed from Building Energy S p A to Red Rocket Africa Building Energy South Africa is still a minority shareholder of the plant but has changed its name to Red Rocket South Africa The facility operated to expected and forecasted performance levels and there have been no major issues or concerns during the first three operational years The Soroti project produced exactly at the planned annual production level in 2020 16 0 GWh The grid availability averaged 99 6 during 2020 with only a few hours of outage reported monthly 8 0 in million USD in GWh 16 16 During 2020 the project generated 28 5 GWh Combined with the energy generated since achieving commercial operation in 2017 the project has contributed nearly 90 GWh of electricity to the Uganda grid A series of unplanned maintenance activities were required during 2020 predominantly as a result of debris accumulation at the dam and intake during the May 2020 floods Combined with planned maintenance works this had the effect of reducing the plant availability to 92 Nonetheless the plant still generated 104 of the average energy estimated at application stage Adjusting for the reduced plant availability as a result of unplanned maintenance activities as well as external outages the plant would reportedly have been able to generate a combined 29 5 GWh during 2020 109 of the estimated annual average energy Several of the issues raised during a post COD site visit in November 2019 were resolved by the Developer during 2020 Annual Generation Estimated Generation T his run of river hydropower project is located in Kasese and Bunyangabo Districts in Western Uganda and has been operational since October 2017 16 5 5 in MW Planned Generation 27 0 in GWh year Total Investment 19 0 in million USD GET FiT Commitment 3 9 in million USD Annual Generation in GWh 29 25 28 27 7 2018 2019 2020 2021e 2017 2 00 2019 2020 2021e 3 50 1 60 3 00 1 40 Uganda 2018 4 00 1 80 1 20 2 50 1 00 2 00 0 80 Uganda 1 50 0 60 0 40 1 00 0 20 0 50 0 00 0 00 Planned Energy GWh Actual Energy GWh Deemed Energy GWh Figure 10 Tororo Solar PV Planned versus Actual Energy Output 2020 32 Capacity 16 6 2017 Hydropower Planned Energy GWh Actual Energy GWh Deemed Energy GWh Figure 11 Rwimi SHP Planned versus Actual Energy Output 2019 33 Estimated Generation

Page 35

GET FiT Uganda Annual Report 2020 Tororo Solar PV Rwimi SHP Operational Operational T Solar PV Capacity 10 0 in MW Planned Generation 16 0 in GWh year Total Investment 19 6 in million USD GET FiT Commitment he Tororo Solar PV project is located in Tororo District Eastern Uganda The 10 MWp power plant commenced commercial operations in September 2017 and so became the second grid connected solar power plant in Uganda The project was developed by Building Energy but during 2020 the majority shareholder changed Further in 2020 the majority shareholder changed from Building Energy S p A to Red Rocket Africa Building Energy South Africa is still a minority shareholder of the plant but has changed its name to Red Rocket South Africa The facility operated to expected and forecasted performance levels and there have been no major issues or concerns during the first three operational years The Soroti project produced exactly at the planned annual production level in 2020 16 0 GWh The grid availability averaged 99 6 during 2020 with only a few hours of outage reported monthly 8 0 in million USD in GWh 16 16 During 2020 the project generated 28 5 GWh Combined with the energy generated since achieving commercial operation in 2017 the project has contributed nearly 90 GWh of electricity to the Uganda grid A series of unplanned maintenance activities were required during 2020 predominantly as a result of debris accumulation at the dam and intake during the May 2020 floods Combined with planned maintenance works this had the effect of reducing the plant availability to 92 Nonetheless the plant still generated 104 of the average energy estimated at application stage Adjusting for the reduced plant availability as a result of unplanned maintenance activities as well as external outages the plant would reportedly have been able to generate a combined 29 5 GWh during 2020 109 of the estimated annual average energy Several of the issues raised during a post COD site visit in November 2019 were resolved by the Developer during 2020 Annual Generation Estimated Generation T his run of river hydropower project is located in Kasese and Bunyangabo Districts in Western Uganda and has been operational since October 2017 16 5 5 in MW Planned Generation 27 0 in GWh year Total Investment 19 0 in million USD GET FiT Commitment 3 9 in million USD Annual Generation in GWh 29 25 28 27 7 2018 2019 2020 2021e 2017 2 00 2019 2020 2021e 3 50 1 60 3 00 1 40 Uganda 2018 4 00 1 80 1 20 2 50 1 00 2 00 0 80 Uganda 1 50 0 60 0 40 1 00 0 20 0 50 0 00 0 00 Planned Energy GWh Actual Energy GWh Deemed Energy GWh Figure 10 Tororo Solar PV Planned versus Actual Energy Output 2020 32 Capacity 16 6 2017 Hydropower Planned Energy GWh Actual Energy GWh Deemed Energy GWh Figure 11 Rwimi SHP Planned versus Actual Energy Output 2019 33 Estimated Generation

Page 36

GET FiT Uganda Annual Report 2020 Nkusi SHP Lubilia SHP Operational Operational Hydropower Capacity 5 4 in MW Planned Generation 22 0 in GWh year Total Investment 16 0 in million USD GET FiT Commitment 3 2 in million USD Annual Generation in GWh 20 Estimated Generation 14 2018 22 22 16 2019 T his run of river hydropower plant is located in Kasese District in Western Uganda and delivered a total of 19 9 GWh of electricity to the grid in 2020 having been operational since early April 2018 The plant experienced a major flood event during May 2020 which resulted in damage to key project structures and the need for remedial repairs The downtime in plant operations was limited however as repairs were largely undertaken in parallel with continued generation In November 2020 the project suffered another major setback as a result of a landslide alongside the headrace canal resulting in further substantial unplanned outages until the end of the year Combined with the planned maintenance works during 2020 outages for flooding and remedial repairs resulted in an average plant availability for the year of 86 well below what would be expected from a hydropower plant of similar age Grid failures and external outages during the year resulted in missed generation approximately equivalent to 7 of the potential plant output energy delivered plus deemed energy which were substantially lower than the 14 observed during 2019 Accounting for internal and external outages the plant would have been able to generate a combined 25 2 GWh during 2020 approximately equivalent to 115 of the estimated annual average energy 2020 2021e 2022e Uganda Capacity Grid failures and external outages during 2020 which resulted in an average grid availability of 87 resulted in missed generation approximately equivalent to 13 of the potential plant output energy delivered plus deemed energy substantially improved from the 24 and 28 reported in 2019 and 2018 respectively in million USD Adjusting for internal and external outages the plant would have been able to generate a combined 84 1 GWh during 2020 approximately equivalent to 183 of the average annual energy estimated at application stage indicating that the plant experienced a significantly wetter than average year A post COD visit has not yet been undertaken Meanwhile follow up of outstanding issues at the time of COD is undertaken on a desk study basis 8 00 3 50 7 00 3 00 6 00 2 50 5 00 2 00 4 00 1 50 3 00 1 00 2 00 0 50 1 00 0 00 0 00 Actual Energy GWh Deemed Energy GWh Figure 12 Lubilia SHP Planned versus Actual Energy Output 2020 Hydropower During 2020 the plant was available 92 of the time which is slightly lower than expected for a hydropower project of this age The generation in November was considerably lower than planned due to unplanned internal outages Nonetheless the project still delivered 66 8 GWh to the grid due to a substantially higher flow availability during the year compared with the average annual generation estimated at application stage Combined with the plant output since achieving COD in 2018 the project has generated nearly 140 GWh 4 00 Planned Energy GWh 34 T his run of river hydropower plant is located in the Kibaale and Hoima Districts in Western Uganda and has been operational since June 2018 9 6 in MW Planned Generation 46 0 in GWh year Total Investment 19 6 GET FiT Commitment 2 8 in million USD Annual Generation in GWh 67 44 46 46 2019 2020 2021e 2022e 29 2018 Uganda Planned Energy GWh Actual Energy GWh Deemed Energy GWh Figure 13 Nkusi SHP Planned versus Actual Energy Output 2020 35 Estimated Generation

Page 37

GET FiT Uganda Annual Report 2020 Nkusi SHP Lubilia SHP Operational Operational Hydropower Capacity 5 4 in MW Planned Generation 22 0 in GWh year Total Investment 16 0 in million USD GET FiT Commitment 3 2 in million USD Annual Generation in GWh 20 Estimated Generation 14 2018 22 22 16 2019 T his run of river hydropower plant is located in Kasese District in Western Uganda and delivered a total of 19 9 GWh of electricity to the grid in 2020 having been operational since early April 2018 The plant experienced a major flood event during May 2020 which resulted in damage to key project structures and the need for remedial repairs The downtime in plant operations was limited however as repairs were largely undertaken in parallel with continued generation In November 2020 the project suffered another major setback as a result of a landslide alongside the headrace canal resulting in further substantial unplanned outages until the end of the year Combined with the planned maintenance works during 2020 outages for flooding and remedial repairs resulted in an average plant availability for the year of 86 well below what would be expected from a hydropower plant of similar age Grid failures and external outages during the year resulted in missed generation approximately equivalent to 7 of the potential plant output energy delivered plus deemed energy which were substantially lower than the 14 observed during 2019 Accounting for internal and external outages the plant would have been able to generate a combined 25 2 GWh during 2020 approximately equivalent to 115 of the estimated annual average energy 2020 2021e 2022e Uganda Capacity Grid failures and external outages during 2020 which resulted in an average grid availability of 87 resulted in missed generation approximately equivalent to 13 of the potential plant output energy delivered plus deemed energy substantially improved from the 24 and 28 reported in 2019 and 2018 respectively in million USD Adjusting for internal and external outages the plant would have been able to generate a combined 84 1 GWh during 2020 approximately equivalent to 183 of the average annual energy estimated at application stage indicating that the plant experienced a significantly wetter than average year A post COD visit has not yet been undertaken Meanwhile follow up of outstanding issues at the time of COD is undertaken on a desk study basis 8 00 3 50 7 00 3 00 6 00 2 50 5 00 2 00 4 00 1 50 3 00 1 00 2 00 0 50 1 00 0 00 0 00 Actual Energy GWh Deemed Energy GWh Figure 12 Lubilia SHP Planned versus Actual Energy Output 2020 Hydropower During 2020 the plant was available 92 of the time which is slightly lower than expected for a hydropower project of this age The generation in November was considerably lower than planned due to unplanned internal outages Nonetheless the project still delivered 66 8 GWh to the grid due to a substantially higher flow availability during the year compared with the average annual generation estimated at application stage Combined with the plant output since achieving COD in 2018 the project has generated nearly 140 GWh 4 00 Planned Energy GWh 34 T his run of river hydropower plant is located in the Kibaale and Hoima Districts in Western Uganda and has been operational since June 2018 9 6 in MW Planned Generation 46 0 in GWh year Total Investment 19 6 GET FiT Commitment 2 8 in million USD Annual Generation in GWh 67 44 46 46 2019 2020 2021e 2022e 29 2018 Uganda Planned Energy GWh Actual Energy GWh Deemed Energy GWh Figure 13 Nkusi SHP Planned versus Actual Energy Output 2020 35 Estimated Generation

Page 38

GET FiT Uganda Annual Report 2020 Nyamwamba SHP Waki SHP Operational Hydropower Capacity 9 2 in MW Planned Generation 39 0 in GWh year Total Investment 28 7 in million USD GET FiT Commitment 5 8 in million USD Annual Generation in GWh Estimated Generation 39 30 39 30 16 Operational T T During May 2020 the plant experienced a major flood resulting in substantial damage to key project structures and unplanned outages lasting several months Key structures were subsequently reconstructed or repaired and equipment replaced in the powerhouse GET FiT undertook desk based reviews of reconstruction plans designs and environmental and social compliance issues Procurement lead in times and shipping delays meant that not all replacement equipment had reached site by the end of 2020 including equipment for measuring deemed energy During 2020 the project delivered 17 6 GWh of electricity to the grid Grid availability during 2020 was again very poor averaging approximately 77 similar to the value reported in 2019 see Chapter 4 for further details It was not possible to assess the energy potential of the plant during 2020 however due to uncertainties with respect to the method of calculating Deemed Energy Nonetheless based on available data the plant was estimated to have had a generation potential during 2020 greater than 100 of that planned at application stage Uncertainties surrounding the method of Deemed Energy calculation are expected to be resolved early during 2021 his run of river hydropower plant is located in Kasese District in Western Uganda and has been operational since April 2018 In the short term the Developer salvaged parts from all three generation units and assembled a single unit Following reconstruction of the intake and assembly of the temporary generating unit the plant recommenced operations in early October 2020 albeit at substantially reduced capacity Despite the major setbacks the plant still generated 16 4 GWh during 2020 including approximately 6 GWh from the temporary generating unit during the last three months of the year as a result of higher than expected flow availability Due to the damage to project structures in May it was not possible to estimate the generation potential in 2020 his run of river hydropower plant is located in Hoima and Buliisa Districts in Western Uganda and has been operational since December 2018 A post COD visit has not yet been undertaken Meanwhile follow up of outstanding issues at the time of COD is undertaken on a desk study basis This has included following up on technical engineering and environmental and social issues such as the release and monitoring of the environmental minimum flow Hydropower Capacity 4 8 in MW Planned Generation 25 0 in GWh year Total Investment 17 3 in million USD GET FiT Commitment 3 6 in million USD Annual Generation in GWh 25 25 18 13 1 2018 2019 2018 2020 2021e 2022e 2019 2020 2021e 2022e 4 00 3 50 5 00 3 00 4 00 Uganda 2 50 3 00 Uganda 2 00 1 50 2 00 1 00 1 00 0 50 0 00 0 00 Planned Energy GWh Actual Energy GWh Deemed Energy GWh Figure 14 Nyamwamba SHP Planned versus Actual Energy Output 2020 36 Planned Energy GWh Actual Energy GWh Deemed Energy GWh Figure 15 Waki SHP Planned versus Actual Energy Output 2020 37 Estimated Generation

Page 39

GET FiT Uganda Annual Report 2020 Nyamwamba SHP Waki SHP Operational Hydropower Capacity 9 2 in MW Planned Generation 39 0 in GWh year Total Investment 28 7 in million USD GET FiT Commitment 5 8 in million USD Annual Generation in GWh Estimated Generation 39 30 39 30 16 Operational T T During May 2020 the plant experienced a major flood resulting in substantial damage to key project structures and unplanned outages lasting several months Key structures were subsequently reconstructed or repaired and equipment replaced in the powerhouse GET FiT undertook desk based reviews of reconstruction plans designs and environmental and social compliance issues Procurement lead in times and shipping delays meant that not all replacement equipment had reached site by the end of 2020 including equipment for measuring deemed energy During 2020 the project delivered 17 6 GWh of electricity to the grid Grid availability during 2020 was again very poor averaging approximately 77 similar to the value reported in 2019 see Chapter 4 for further details It was not possible to assess the energy potential of the plant during 2020 however due to uncertainties with respect to the method of calculating Deemed Energy Nonetheless based on available data the plant was estimated to have had a generation potential during 2020 greater than 100 of that planned at application stage Uncertainties surrounding the method of Deemed Energy calculation are expected to be resolved early during 2021 his run of river hydropower plant is located in Kasese District in Western Uganda and has been operational since April 2018 In the short term the Developer salvaged parts from all three generation units and assembled a single unit Following reconstruction of the intake and assembly of the temporary generating unit the plant recommenced operations in early October 2020 albeit at substantially reduced capacity Despite the major setbacks the plant still generated 16 4 GWh during 2020 including approximately 6 GWh from the temporary generating unit during the last three months of the year as a result of higher than expected flow availability Due to the damage to project structures in May it was not possible to estimate the generation potential in 2020 his run of river hydropower plant is located in Hoima and Buliisa Districts in Western Uganda and has been operational since December 2018 A post COD visit has not yet been undertaken Meanwhile follow up of outstanding issues at the time of COD is undertaken on a desk study basis This has included following up on technical engineering and environmental and social issues such as the release and monitoring of the environmental minimum flow Hydropower Capacity 4 8 in MW Planned Generation 25 0 in GWh year Total Investment 17 3 in million USD GET FiT Commitment 3 6 in million USD Annual Generation in GWh 25 25 18 13 1 2018 2019 2018 2020 2021e 2022e 2019 2020 2021e 2022e 4 00 3 50 5 00 3 00 4 00 Uganda 2 50 3 00 Uganda 2 00 1 50 2 00 1 00 1 00 0 50 0 00 0 00 Planned Energy GWh Actual Energy GWh Deemed Energy GWh Figure 14 Nyamwamba SHP Planned versus Actual Energy Output 2020 36 Planned Energy GWh Actual Energy GWh Deemed Energy GWh Figure 15 Waki SHP Planned versus Actual Energy Output 2020 37 Estimated Generation

Page 40

GET FiT Uganda Annual Report 2020 Sindila SHP Siti 2 SHP Operational Hydropower Capacity 5 3 in MW Planned Generation 27 0 in GWh year Total Investment 19 4 in million USD GET FiT Commitment 3 9 in million USD Annual Generation in GWh 27 Estimated Generation 27 27 15 9 2019 Operational T his run of river hydropower plant is located in Bundibugyo District in Western Uganda and was developed in parallel with the Ndugutu SHP located on an adjacent river basin also supported by GET FiT The project commenced construction in February 2017 and synchronised to the grid during April 2019 Despite having been operational since 2019 the plant has still not been able to complete the full suite of commissioning tests due to a combination of limited available water and grid constraints Grid constraints continue to effectively limit the combined output from the Sindila and adjacent Ndugutu SHPs to approximately 8 MW which when combined with outages resulted in generation losses approximately equivalent to 21 of the potential plant output for the year energy delivered plus deemed energy The availability of the grid during 2020 was on average 83 whereas the plant availability was 98 which is in the expected range for a new SHP Despite grid constraints the plant was still able to deliver 14 7 GWh to the grid during 2020 Whilst 2020 was generally observed to have been a statistically wetter than average year for most of the GET FiT SHPs see Section 2 1 6 the water available for generation at both the Sindila and adjacent Ndugutu SHPs was less than that estimated at application stage Adjusting for the partial grid availability the potential energy output of the plant was equivalent to approximately 69 of the annual energy estimated at application stage T his run of river hydropower plant is located in Bukwo District in Eastern Uganda The Project commenced construction in August 2016 and completed partial commissioning tests and synchronised to the grid in July 2019 The permanent power evacuation solution comprising a new 132 kV transmission line see Siti 1 SHP description is expected to be completed during 2024 In the interim the plant was connected to a new 130 km long 33 kV line at the end of 2020 see Section 4 which enabled further commissioning tests to be undertaken and power evacuation to be increased As a result the plant was only able to deliver 6 5 GWh to the grid during compared with an annual energy of 70 0 GWh9 estimated at application stage Deemed energy claims accounted for 93 of the potential plant output during the year and are expected to be significantly reduced during 2021 Adjusting for internal and external outages the plant would have been able to generate a combined 97 5 GWh during 2020 approximately equivalent to 139 of the estimated average annual energy indicating a significantly wetter than average year As a result of substantial and persistent environmental and social non compliances throughout the construction period as well as during the early period of plant operations the Developer and the GoU represented by KfW subsequently agreed during 2020 to a substantial reduction in the overall subsidy amount for which the project was eligible 2020 2021e 2022e 2023e Capacity 16 5 in MW Planned Generation 70 0 in GWh year Total Investment 33 0 in million USD GET FiT Commitment 10 2 in million USD Annual Generation in GWh 70 2 2019 14 00 70 70 6 2020 2021e 2022e 2023e 12 00 4 00 3 50 10 00 3 00 Uganda Hydropower 8 00 2 50 Uganda 6 00 2 00 1 50 4 00 1 00 2 00 0 50 0 00 0 00 Planned Energy GWh Actual Energy GWh Planned Energy GWh Deemed Energy GWh Figure 16 Sindila SHP Planned versus Actual Energy Output 2020 Deemed Energy GWh Figure 17 Siti 2 SHP Planned versus Actual Energy Output 2020 9 38 Actual Energy GWh The planned average annual generation of the Siti 2 SHP has been adjusted from the 72 GWh reported in previous GET FiT Uganda reporting in order to reflect the expected plant output more accurately 39 Estimated Generation

Page 41

GET FiT Uganda Annual Report 2020 Sindila SHP Siti 2 SHP Operational Hydropower Capacity 5 3 in MW Planned Generation 27 0 in GWh year Total Investment 19 4 in million USD GET FiT Commitment 3 9 in million USD Annual Generation in GWh 27 Estimated Generation 27 27 15 9 2019 Operational T his run of river hydropower plant is located in Bundibugyo District in Western Uganda and was developed in parallel with the Ndugutu SHP located on an adjacent river basin also supported by GET FiT The project commenced construction in February 2017 and synchronised to the grid during April 2019 Despite having been operational since 2019 the plant has still not been able to complete the full suite of commissioning tests due to a combination of limited available water and grid constraints Grid constraints continue to effectively limit the combined output from the Sindila and adjacent Ndugutu SHPs to approximately 8 MW which when combined with outages resulted in generation losses approximately equivalent to 21 of the potential plant output for the year energy delivered plus deemed energy The availability of the grid during 2020 was on average 83 whereas the plant availability was 98 which is in the expected range for a new SHP Despite grid constraints the plant was still able to deliver 14 7 GWh to the grid during 2020 Whilst 2020 was generally observed to have been a statistically wetter than average year for most of the GET FiT SHPs see Section 2 1 6 the water available for generation at both the Sindila and adjacent Ndugutu SHPs was less than that estimated at application stage Adjusting for the partial grid availability the potential energy output of the plant was equivalent to approximately 69 of the annual energy estimated at application stage T his run of river hydropower plant is located in Bukwo District in Eastern Uganda The Project commenced construction in August 2016 and completed partial commissioning tests and synchronised to the grid in July 2019 The permanent power evacuation solution comprising a new 132 kV transmission line see Siti 1 SHP description is expected to be completed during 2024 In the interim the plant was connected to a new 130 km long 33 kV line at the end of 2020 see Section 4 which enabled further commissioning tests to be undertaken and power evacuation to be increased As a result the plant was only able to deliver 6 5 GWh to the grid during compared with an annual energy of 70 0 GWh9 estimated at application stage Deemed energy claims accounted for 93 of the potential plant output during the year and are expected to be significantly reduced during 2021 Adjusting for internal and external outages the plant would have been able to generate a combined 97 5 GWh during 2020 approximately equivalent to 139 of the estimated average annual energy indicating a significantly wetter than average year As a result of substantial and persistent environmental and social non compliances throughout the construction period as well as during the early period of plant operations the Developer and the GoU represented by KfW subsequently agreed during 2020 to a substantial reduction in the overall subsidy amount for which the project was eligible 2020 2021e 2022e 2023e Capacity 16 5 in MW Planned Generation 70 0 in GWh year Total Investment 33 0 in million USD GET FiT Commitment 10 2 in million USD Annual Generation in GWh 70 2 2019 14 00 70 70 6 2020 2021e 2022e 2023e 12 00 4 00 3 50 10 00 3 00 Uganda Hydropower 8 00 2 50 Uganda 6 00 2 00 1 50 4 00 1 00 2 00 0 50 0 00 0 00 Planned Energy GWh Actual Energy GWh Planned Energy GWh Deemed Energy GWh Figure 16 Sindila SHP Planned versus Actual Energy Output 2020 Deemed Energy GWh Figure 17 Siti 2 SHP Planned versus Actual Energy Output 2020 9 38 Actual Energy GWh The planned average annual generation of the Siti 2 SHP has been adjusted from the 72 GWh reported in previous GET FiT Uganda reporting in order to reflect the expected plant output more accurately 39 Estimated Generation

Page 42

GET FiT Uganda Annual Report 2020 Ndugutu SHP Kyambura SHP Operational Operational Hydropower Capacity 7 6 in MW Planned Generation 36 7 in GWh year Total Investment 24 0 in million USD GET FiT Commitment 5 4 in million USD T his run of river hydropower plant is located in the Rubirizi District in Western Uganda The Developer initially mobilised to site in February 2017 but only commenced with key construction activities from September 2017 During 2020 the Project delivered 33 7 GWh of electricity to the grid Grid failures and external outages resulted in generation losses approximately equivalent to 12 of the potential plant output for the year energy delivered plus deemed energy which is similar to the level of outages experienced in the first five full months of operation in 2019 The plant availability during 2020 was again above 98 which is in line with the upper end of the expected range for a new SHP whilst grid availability was slightly lower than during the second half of 2019 with an annual average availability in 2020 of 91 Adjusting for the partial availability of the power evacuation line the cumulative energy output of the plant during 2020 would have been 38 4 GWh approximately equivalent to 105 of the annual average energy estimated at application stage Annual Generation in GWh 34 Estimated Generation 37 37 37 2020 2021e 2022e 2023e Hydropower Capacity 5 9 in MW Despite having been operational since 2019 the plant was still unable to complete the full suite of commissioning tests due to a combination of limited available water and grid constraints Nonetheless plant availability during 2020 was 98 which is in line with the upper end of the expected range for a new SHP and 19 0 GWh of electricity was delivered to the grid Reinforcements to the existing grid and construction of a new power evacuation line to the Fort Portal substation were ongoing during 2020 These efforts are expected to substantially reduce outages and allow both Ndugutu and the neighbouring Sindila SHPs to generate at full capacity In the meantime the grid was only capable of evacuating power up to a maximum of 8 MW from both plants during 2020 which is less than their combined total capacity As a result an average grid availability of 83 resulted in missed generation at the Ndugutu SHP approximately equivalent to 21 of the potential plant output for the year energy delivered plus deemed energy Adjusting for the partial availability of the power evacuation line the potential plant generation during 2020 would have been 23 9 GWh approximately 91 of the annual average energy estimated at application stage 16 2019 T his run of river hydropower plant is located in the Bundibugyo District in Western Uganda and was developed in parallel with the Sindila SHP located on an adjacent river basin also supported by GET FiT The project commenced construction in June 2017 and achieved Deemed COD on 1 October 2019 Planned Generation 26 5 in GWh year Total Investment 17 1 in million USD GET FiT Commitment 3 2 in million USD Annual Generation in GWh 27 27 27 19 5 2019 2020 2021e 2022e 2023e 4 50 6 00 4 00 5 00 3 00 4 00 Energy GWh Uganda 3 50 2 00 1 50 2 00 1 00 1 00 0 00 0 50 Jan Feb Mar Apr Planned Energy GWh May Jun Jul Aug Actual Energy GWh Sep Oct Nov Dec Deemed Energy GWh Figure 18 Kyambura SHP Planned versus Actual Energy Output 2020 40 Uganda 2 50 3 00 0 00 Planned Energy GWh Actual Energy GWh Deemed Energy GWh Figure 19 Ndugutu SHP Planned versus Actual Energy Output 2020 41 Estimated Generation

Page 43

GET FiT Uganda Annual Report 2020 Ndugutu SHP Kyambura SHP Operational Operational Hydropower Capacity 7 6 in MW Planned Generation 36 7 in GWh year Total Investment 24 0 in million USD GET FiT Commitment 5 4 in million USD T his run of river hydropower plant is located in the Rubirizi District in Western Uganda The Developer initially mobilised to site in February 2017 but only commenced with key construction activities from September 2017 During 2020 the Project delivered 33 7 GWh of electricity to the grid Grid failures and external outages resulted in generation losses approximately equivalent to 12 of the potential plant output for the year energy delivered plus deemed energy which is similar to the level of outages experienced in the first five full months of operation in 2019 The plant availability during 2020 was again above 98 which is in line with the upper end of the expected range for a new SHP whilst grid availability was slightly lower than during the second half of 2019 with an annual average availability in 2020 of 91 Adjusting for the partial availability of the power evacuation line the cumulative energy output of the plant during 2020 would have been 38 4 GWh approximately equivalent to 105 of the annual average energy estimated at application stage Annual Generation in GWh 34 Estimated Generation 37 37 37 2020 2021e 2022e 2023e Hydropower Capacity 5 9 in MW Despite having been operational since 2019 the plant was still unable to complete the full suite of commissioning tests due to a combination of limited available water and grid constraints Nonetheless plant availability during 2020 was 98 which is in line with the upper end of the expected range for a new SHP and 19 0 GWh of electricity was delivered to the grid Reinforcements to the existing grid and construction of a new power evacuation line to the Fort Portal substation were ongoing during 2020 These efforts are expected to substantially reduce outages and allow both Ndugutu and the neighbouring Sindila SHPs to generate at full capacity In the meantime the grid was only capable of evacuating power up to a maximum of 8 MW from both plants during 2020 which is less than their combined total capacity As a result an average grid availability of 83 resulted in missed generation at the Ndugutu SHP approximately equivalent to 21 of the potential plant output for the year energy delivered plus deemed energy Adjusting for the partial availability of the power evacuation line the potential plant generation during 2020 would have been 23 9 GWh approximately 91 of the annual average energy estimated at application stage 16 2019 T his run of river hydropower plant is located in the Bundibugyo District in Western Uganda and was developed in parallel with the Sindila SHP located on an adjacent river basin also supported by GET FiT The project commenced construction in June 2017 and achieved Deemed COD on 1 October 2019 Planned Generation 26 5 in GWh year Total Investment 17 1 in million USD GET FiT Commitment 3 2 in million USD Annual Generation in GWh 27 27 27 19 5 2019 2020 2021e 2022e 2023e 4 50 6 00 4 00 5 00 3 00 4 00 Energy GWh Uganda 3 50 2 00 1 50 2 00 1 00 1 00 0 00 0 50 Jan Feb Mar Apr Planned Energy GWh May Jun Jul Aug Actual Energy GWh Sep Oct Nov Dec Deemed Energy GWh Figure 18 Kyambura SHP Planned versus Actual Energy Output 2020 40 Uganda 2 50 3 00 0 00 Planned Energy GWh Actual Energy GWh Deemed Energy GWh Figure 19 Ndugutu SHP Planned versus Actual Energy Output 2020 41 Estimated Generation

Page 44

GET FiT Uganda Annual Report 2020 Kikagati SHP Nyamagasani 1 SHP Under Construction Hydropower Capacity in MW Planned Generation in GWh year Total Investment in million USD GET FiT Commitment in million USD 16 0 115 0 87 7 12 3 Uganda 42 Under Construction T his run of river hydropower plant is located in Isingiro District in Southern Uganda on the Kagera River on the border with Tanzania T his run of river hydropower plant is located in the Kasese District in Western Uganda The Developer mobilised to site in February 2017 and experienced substantial delays through to the end of 2019 as a result of a combination of issues predominantly comprising poor construction planning performance and contractor cashflow issues At the end of 2019 the Developer implemented a series of changes that appeared to result in substantially improved construction progress during the first quarter of 2020 At that stage construction completion and commencing commercial operations during 2020 appeared feasible Hydropower Total Investment The Developer still planned to commission the three generating units progressively with a final estimated COD in August 2021 delayed from September 2020 as estimated at the end of 2019 Completion of the major project structures however was forecast for October 2021 compared with the previously forecast completion date of March 2021 Subsequently the project experienced a series of major setbacks including worldwide travel restrictions imposed as a result of the coronavirus SARS CoV 2 pandemic which affected the movement of key people involved in project delivery as well as supply chain disruptions as well as a major flood event in May 2020 The flood event resulted in damage to key project structures construction equipment adversely impacted construction access to the most challenging section of the project the first few hundred metres of waterway in steep terrain downstream of the weir and ultimately led to further construction delays Based on observed progress outstanding design issues the scope of remaining construction works and substantial construction risks such as being able to successfully divert the Kagera River for dam construction construction completion will be delayed by several months Harmonisation and continued coordination with respect to requirements in the two countries is likely to be essential to avoid further unexpected delays in particular as construction works expand to the Tanzanian side in 2021 Nonetheless construction of the various project structures continued throughout 2020 with the exception of the critical structures at the intake By the end of 2020 access to the weir had been reinstated and new construction plant mobilised to enable the works to progress The Project is now expected to complete construction and commence commercial operations around the middle of 2021 Refer to Section 4 3 for an update on the related power evacuation infrastructure The project experienced construction delays during 2020 as a result of the global COVID 19 pandemic including adverse impacts to the supply chain and the travel and movements of project key personnel and workforce Whilst a number of important design issues had been resolved by the end of 2020 a few key issues were still outstanding and required urgent attention early during 2021 Construction works were substantially progressed at the powerhouse by the end of the year and plans for construction of other key structures were well underway Construction of the switchyard on the Tanzanian side of the river was also nearing completion Capacity in MW Planned Generation in GWh year in million USD 15 0 64 0 36 1 GET FiT Commitment 9 3 in million USD Uganda 43

Page 45

GET FiT Uganda Annual Report 2020 Kikagati SHP Nyamagasani 1 SHP Under Construction Hydropower Capacity in MW Planned Generation in GWh year Total Investment in million USD GET FiT Commitment in million USD 16 0 115 0 87 7 12 3 Uganda 42 Under Construction T his run of river hydropower plant is located in Isingiro District in Southern Uganda on the Kagera River on the border with Tanzania T his run of river hydropower plant is located in the Kasese District in Western Uganda The Developer mobilised to site in February 2017 and experienced substantial delays through to the end of 2019 as a result of a combination of issues predominantly comprising poor construction planning performance and contractor cashflow issues At the end of 2019 the Developer implemented a series of changes that appeared to result in substantially improved construction progress during the first quarter of 2020 At that stage construction completion and commencing commercial operations during 2020 appeared feasible Hydropower Total Investment The Developer still planned to commission the three generating units progressively with a final estimated COD in August 2021 delayed from September 2020 as estimated at the end of 2019 Completion of the major project structures however was forecast for October 2021 compared with the previously forecast completion date of March 2021 Subsequently the project experienced a series of major setbacks including worldwide travel restrictions imposed as a result of the coronavirus SARS CoV 2 pandemic which affected the movement of key people involved in project delivery as well as supply chain disruptions as well as a major flood event in May 2020 The flood event resulted in damage to key project structures construction equipment adversely impacted construction access to the most challenging section of the project the first few hundred metres of waterway in steep terrain downstream of the weir and ultimately led to further construction delays Based on observed progress outstanding design issues the scope of remaining construction works and substantial construction risks such as being able to successfully divert the Kagera River for dam construction construction completion will be delayed by several months Harmonisation and continued coordination with respect to requirements in the two countries is likely to be essential to avoid further unexpected delays in particular as construction works expand to the Tanzanian side in 2021 Nonetheless construction of the various project structures continued throughout 2020 with the exception of the critical structures at the intake By the end of 2020 access to the weir had been reinstated and new construction plant mobilised to enable the works to progress The Project is now expected to complete construction and commence commercial operations around the middle of 2021 Refer to Section 4 3 for an update on the related power evacuation infrastructure The project experienced construction delays during 2020 as a result of the global COVID 19 pandemic including adverse impacts to the supply chain and the travel and movements of project key personnel and workforce Whilst a number of important design issues had been resolved by the end of 2020 a few key issues were still outstanding and required urgent attention early during 2021 Construction works were substantially progressed at the powerhouse by the end of the year and plans for construction of other key structures were well underway Construction of the switchyard on the Tanzanian side of the river was also nearing completion Capacity in MW Planned Generation in GWh year in million USD 15 0 64 0 36 1 GET FiT Commitment 9 3 in million USD Uganda 43

Page 46

GET FiT Uganda Annual Report 2020 Nyamagasani 2 SHP Under Construction Hydropower Capacity 5 0 in MW Planned Generation in GWh year Total Investment in million USD 25 5 19 4 GET FiT Commitment 3 7 in million USD Uganda T his run of river hydropower plant is located in the Kasese District in Western Uganda and was developed as part of a cascade just downstream of the Nyamagasani 1 SHP also approved for GET FiT support The Developer and EPC Contractor are common to both the Nyamagasani 1 and 2 SHP s and the reported construction progress issues up until the end of 2019 were similar as well as the apparent substantial improvements in construction progress during the first quarter of 2020 At that stage construction completion and commencing commercial operations during 2020 appeared feasible Similar to the upstream Nyamagasani 1 SHP the Project experienced a series of major setbacks in 2020 including worldwide travel restrictions imposed as a result of the coronavirus SARSCoV 2 pandemic and a major flood event in May 2020 The flood event resulted in substantial damage to key project structures the need to modify designs and substantial reconstruction works ultimately resulting in further construction delays The flooding also resulted in modifications to the fish passage at the weir with the fish passage currently planned for completion after commissioning of the plant The construction of other project structures continued throughout the year and by the end of 2020 remedial and reconstruction works to flood damaged project structures were nearing completion The Developer had furthermore invested in upgrades to the existing nearby grid to enable the plant to be connected commissioning tests completed and evacuation of at least a limited plant output prior to completion of the permanent power evacuation solution Commissioning works and commercial operations during the first quarter of 2021 therefore appeared feasible Refer to Section 4 3 for further details with respect to the related power evacuation infrastructure 44 45

Page 47

GET FiT Uganda Annual Report 2020 Nyamagasani 2 SHP Under Construction Hydropower Capacity 5 0 in MW Planned Generation in GWh year Total Investment in million USD 25 5 19 4 GET FiT Commitment 3 7 in million USD Uganda T his run of river hydropower plant is located in the Kasese District in Western Uganda and was developed as part of a cascade just downstream of the Nyamagasani 1 SHP also approved for GET FiT support The Developer and EPC Contractor are common to both the Nyamagasani 1 and 2 SHP s and the reported construction progress issues up until the end of 2019 were similar as well as the apparent substantial improvements in construction progress during the first quarter of 2020 At that stage construction completion and commencing commercial operations during 2020 appeared feasible Similar to the upstream Nyamagasani 1 SHP the Project experienced a series of major setbacks in 2020 including worldwide travel restrictions imposed as a result of the coronavirus SARSCoV 2 pandemic and a major flood event in May 2020 The flood event resulted in substantial damage to key project structures the need to modify designs and substantial reconstruction works ultimately resulting in further construction delays The flooding also resulted in modifications to the fish passage at the weir with the fish passage currently planned for completion after commissioning of the plant The construction of other project structures continued throughout the year and by the end of 2020 remedial and reconstruction works to flood damaged project structures were nearing completion The Developer had furthermore invested in upgrades to the existing nearby grid to enable the plant to be connected commissioning tests completed and evacuation of at least a limited plant output prior to completion of the permanent power evacuation solution Commissioning works and commercial operations during the first quarter of 2021 therefore appeared feasible Refer to Section 4 3 for further details with respect to the related power evacuation infrastructure 44 45

Page 48

GET FiT Uganda Annual Report 2020 03 Environmental Social Performance 3 1 Improved Management of Environmental and Social Risks S ound management of environmental and social E S risks protects the environment and safeguards workers and project affected people Projects supported by GET FiT are required to comply with Ugandan regulations and international standards particularly the environmental and social performance standards PS of the International Finance Corporation IFC The IFC PS act as a global benchmark and are widely applied by international financing institutions and private investors also making these a convenient common reference point in multi donor funded initiatives like GET FiT Over multiple years GET FiT has observed that the capacity of project developers to manage E S risks including health and safety has been considerably lower than expected and not commensurate to the project risks in several of the projects This necessitated increased supervision efforts and follow up by GET FiT Multiple projects have been requested to develop substantial corrective measures Where risks were critical GET FiT requested certain construction works to stop until corrective measures were implemented or notified developers of potential subsidy reductions unless critical gaps were closed Some subsidy reductions were implemented due to delays in implementing appropriate measures Important non compliances during construction included serious health and safety risks to the work force inadequate compensation during land acquisition and displacement and excessive pollution and habitat damage due to construction works During operations GET FiT uncovered serious deviations from the required releases of environmental minimum flow along the diverted river section between the dam and the powerhouse 46 During programme implementation dedicated and joint follow up together with ERA combined with developers strengthened efforts resulted in substantial improvements including Greater in house environmental and social capacity among developers in the home office and in the field during construction and operations Improved environmental and social management plans and procedures Changes in project designs and construction methods to better incorporate E S concerns Closer supervision and monitoring of contractors construction practices by developers Reduced risks to workers health and safety Fair compensation to people losing land houses crops or natural resources including provision of water supply schemes for people with project affected access to water sources at eight projects see upper photos Reduced pollution of rivers and less damage to biodiversity including support to Uganda Wildlife Authority in the form of two new ranger posts to better protect national park areas neighbouring project sites see photo in the middle Improved arrangements to reliably release and monitor environmental minimum flows including retrofitting new arrangements during project operations to replace unreliable solutions see bottom pictures 47

Page 49

GET FiT Uganda Annual Report 2020 03 Environmental Social Performance 3 1 Improved Management of Environmental and Social Risks S ound management of environmental and social E S risks protects the environment and safeguards workers and project affected people Projects supported by GET FiT are required to comply with Ugandan regulations and international standards particularly the environmental and social performance standards PS of the International Finance Corporation IFC The IFC PS act as a global benchmark and are widely applied by international financing institutions and private investors also making these a convenient common reference point in multi donor funded initiatives like GET FiT Over multiple years GET FiT has observed that the capacity of project developers to manage E S risks including health and safety has been considerably lower than expected and not commensurate to the project risks in several of the projects This necessitated increased supervision efforts and follow up by GET FiT Multiple projects have been requested to develop substantial corrective measures Where risks were critical GET FiT requested certain construction works to stop until corrective measures were implemented or notified developers of potential subsidy reductions unless critical gaps were closed Some subsidy reductions were implemented due to delays in implementing appropriate measures Important non compliances during construction included serious health and safety risks to the work force inadequate compensation during land acquisition and displacement and excessive pollution and habitat damage due to construction works During operations GET FiT uncovered serious deviations from the required releases of environmental minimum flow along the diverted river section between the dam and the powerhouse 46 During programme implementation dedicated and joint follow up together with ERA combined with developers strengthened efforts resulted in substantial improvements including Greater in house environmental and social capacity among developers in the home office and in the field during construction and operations Improved environmental and social management plans and procedures Changes in project designs and construction methods to better incorporate E S concerns Closer supervision and monitoring of contractors construction practices by developers Reduced risks to workers health and safety Fair compensation to people losing land houses crops or natural resources including provision of water supply schemes for people with project affected access to water sources at eight projects see upper photos Reduced pollution of rivers and less damage to biodiversity including support to Uganda Wildlife Authority in the form of two new ranger posts to better protect national park areas neighbouring project sites see photo in the middle Improved arrangements to reliably release and monitor environmental minimum flows including retrofitting new arrangements during project operations to replace unreliable solutions see bottom pictures 47

Page 50

GET FiT Uganda Annual Report 2020 In 2020 travel restriction limited GET FiT s project supervision There were no on site construction supervision visits or post COD visits only home office follow up plans and management During 2020 an additional five CPs were cleared across four projects Three CPs remained across the three projects still under construction at the end of 2020 The GET FiT Investment Committee defined more than 50 environmental and social Conditions Precedent CPs across the three Requests for Proposals RfPs in 2013 2014 and 2015 related to necessary improvements in environmental and social studies As a result of the GET FiT Programme there is now a considerably higher degree of compliance with Ugandan regulations and international standards than would otherwise have been observed and improved safeguarding of people and nature in project areas 3 2 Environmental Flows B As illustrated in previous GET FiT Annual Reports 10 there is substantial variation in the minimum flow requirements defined in the water abstraction permits measured as a proportion of the estimated mean annual flow As site specific and project specific conditions vary so should the minimum flow requirements as part of balancing water user interests at a specific site However the variation in minimum flow requirements across the GET FiT project portfolio is not clearly justified and not clearly correlated with site conditions The lack of clear national requirements or guidelines including on methods or criteria to estimate the minimum flow contributed to the challenges for developers when suggesting an appropriate level of minimum flow to the authorities Following GET FiT inspections during construction and operations most of the projects had to undertake substantial changes to the design of the minimum flow release arrangements Developers and their designers had limited experience in this area there was a lack of clear national requirements and poor construction or operational practices exacerbated the problems concerning release of the minimum flow Six projects had to retrofit an entirely new arrangement during project operations as a corrective measure to reliably release the required minimum flow This followed substantial non compliances and unacceptable practices noted at some projects concerning the minimum flow release to the detriment of ecosystems local people and the electricity consumers in Uganda paying for surplus energy produced based on water abstracted contrary to their permits Projects are also being required to improve their monitoring and documentation of the minimum flow release to allow for verification for instance by installing automated flow meters In 2021 GET FiT plans to establish a Working Group with ERA and key stakeholders such as DWRM NEMA and UETCL to review the current practices on minimum flows and recommend requirements for hydropower developers in Uganda to safeguard the economic interest of the off taker and consumers as well as ecosystems and local water users As GET FiT is phased out the valuable lessons from the GET FiT Programme will support the relevant Ugandan agencies in their future follow up of existing and new hydropower projects In future GET FiT Programmes the relevant national agencies and GET FiT should develop a set of minimum requirements and guidelines prior to programme implementation where such do not already exist in country Minimum environmental flows are essential to reduce adverse impacts on local water users and river biodiversity While water permits in Uganda prescribe a fixed rather than dynamic minimum flow requirement the lack of reservoirs in the GET FiT supported run of river hydropower projects means that during high flow events there is always spilling of water over the dam that partly mimics the highly variable flows experienced in Ugandan rivers see figure below for illustration River Flow y design the hydropower projects result in a major reduction of the natural river flow between the intake and the powerhouse Typically the diverted river section for a GET FiT supported project is 3 4 km long but can be above 5 km for a single project and up to 10 km for cascade projects The release of a minimum flow is a standard mitigation measure to reduce impacts on people and ecosystems along the affected river section The volume of the minimum flow also directly impacts on the economic viability of a hydropower project as water that could otherwise be used for power generation remains in the natural river channel Defining releasing and monitoring minimum flows have proved problematic to most project developers Similarly national requirements on how to release and monitor the minimum flow were not clear An additional problem was the overall poor quality of the aquatic ecology studies undertaken by project developers as part of the basis for assessing minimum flows Thirteen out of 14 projects were later asked by GET FiT to redo their aquatic studies to meet even the most basic requirements Natural 10 See for instance the Annual Report for 2017 pp 49 50 Section 3 4 Minimum flow an unresolved issue 48 For ecological maintenance Figure 20 A simplified illustration of environmental flows compared with a natural flow regime 49

Page 51

GET FiT Uganda Annual Report 2020 In 2020 travel restriction limited GET FiT s project supervision There were no on site construction supervision visits or post COD visits only home office follow up plans and management During 2020 an additional five CPs were cleared across four projects Three CPs remained across the three projects still under construction at the end of 2020 The GET FiT Investment Committee defined more than 50 environmental and social Conditions Precedent CPs across the three Requests for Proposals RfPs in 2013 2014 and 2015 related to necessary improvements in environmental and social studies As a result of the GET FiT Programme there is now a considerably higher degree of compliance with Ugandan regulations and international standards than would otherwise have been observed and improved safeguarding of people and nature in project areas 3 2 Environmental Flows B As illustrated in previous GET FiT Annual Reports 10 there is substantial variation in the minimum flow requirements defined in the water abstraction permits measured as a proportion of the estimated mean annual flow As site specific and project specific conditions vary so should the minimum flow requirements as part of balancing water user interests at a specific site However the variation in minimum flow requirements across the GET FiT project portfolio is not clearly justified and not clearly correlated with site conditions The lack of clear national requirements or guidelines including on methods or criteria to estimate the minimum flow contributed to the challenges for developers when suggesting an appropriate level of minimum flow to the authorities Following GET FiT inspections during construction and operations most of the projects had to undertake substantial changes to the design of the minimum flow release arrangements Developers and their designers had limited experience in this area there was a lack of clear national requirements and poor construction or operational practices exacerbated the problems concerning release of the minimum flow Six projects had to retrofit an entirely new arrangement during project operations as a corrective measure to reliably release the required minimum flow This followed substantial non compliances and unacceptable practices noted at some projects concerning the minimum flow release to the detriment of ecosystems local people and the electricity consumers in Uganda paying for surplus energy produced based on water abstracted contrary to their permits Projects are also being required to improve their monitoring and documentation of the minimum flow release to allow for verification for instance by installing automated flow meters In 2021 GET FiT plans to establish a Working Group with ERA and key stakeholders such as DWRM NEMA and UETCL to review the current practices on minimum flows and recommend requirements for hydropower developers in Uganda to safeguard the economic interest of the off taker and consumers as well as ecosystems and local water users As GET FiT is phased out the valuable lessons from the GET FiT Programme will support the relevant Ugandan agencies in their future follow up of existing and new hydropower projects In future GET FiT Programmes the relevant national agencies and GET FiT should develop a set of minimum requirements and guidelines prior to programme implementation where such do not already exist in country Minimum environmental flows are essential to reduce adverse impacts on local water users and river biodiversity While water permits in Uganda prescribe a fixed rather than dynamic minimum flow requirement the lack of reservoirs in the GET FiT supported run of river hydropower projects means that during high flow events there is always spilling of water over the dam that partly mimics the highly variable flows experienced in Ugandan rivers see figure below for illustration River Flow y design the hydropower projects result in a major reduction of the natural river flow between the intake and the powerhouse Typically the diverted river section for a GET FiT supported project is 3 4 km long but can be above 5 km for a single project and up to 10 km for cascade projects The release of a minimum flow is a standard mitigation measure to reduce impacts on people and ecosystems along the affected river section The volume of the minimum flow also directly impacts on the economic viability of a hydropower project as water that could otherwise be used for power generation remains in the natural river channel Defining releasing and monitoring minimum flows have proved problematic to most project developers Similarly national requirements on how to release and monitor the minimum flow were not clear An additional problem was the overall poor quality of the aquatic ecology studies undertaken by project developers as part of the basis for assessing minimum flows Thirteen out of 14 projects were later asked by GET FiT to redo their aquatic studies to meet even the most basic requirements Natural 10 See for instance the Annual Report for 2017 pp 49 50 Section 3 4 Minimum flow an unresolved issue 48 For ecological maintenance Figure 20 A simplified illustration of environmental flows compared with a natural flow regime 49

Page 52

GET FiT Uganda Annual Report 2020 3 3 Displacement S ubstantial parts of Uganda are blessed with relatively abundant rainfall This provides the basis for hydropower production as well as rainfed subsistence agriculture supporting a high population density in most project areas where GET FiT supported projects were constructed Therefore displacement of people from project land has been a key issue for project developers to manage A review of levels of planned displacement was included in the 2016 GET FiT Annual Report pp 38 41 An update on some of the experiences from implementation of the hydropower projects is included below Most projects experienced substantial increases in land acquisition and displacement from the time of GET FiT approval to project completion GET FiT warned several developers of this risk and asked for project plans to be revised as to be more realistic in terms of land requirements Across the 14 hydropower projects an overall increase in land acquisition of 104 was observed from the time of GET FiT approval to project completion see Figure 21 Excluding the three outliers in Figure 21 the increase in land take was at approximately 30 with the single most important driver being weaknesses in early project planning due to inadequate engineering and social surveys The increased land take at the three outliers can mainly be attributed to significant layout and design changes and an underestimation of inundation and associated buffer zone in one case Inadequate planning resulted in unrealistic plans for land requirements e g too narrow land corridors along the waterway and subsequent design changes and changes in construction methods that triggered additional need for land In addition poor construction practices resulted in damage to neighbouring land that at times had to be acquired Additional land requirements partly necessitated additional land take from people already affected by a project and partly resulted in land take from people not originally subject to land acquisition by a project On average the number of households losing land economic displacement increased by 53 from GET FiT approval to project completion again with large variation between projects from 24 reduction to 367 increase During the detailed planning most developers were able to adjust project plans to avoid increase in physical displacement loss of shelter which on average increased by 9 from GET FiT approval to project completion Only three projects experienced an increase in physical displacement while seven projects were able to reduce physical displacement 350 327 293 300 250 200 174 150 100 46 50 24 24 47 48 64 65 30 0 0 2 2 50 Figure 21 Increase in Land Acquisition from GET FiT Approval to Project Completion for 14 Hydropower Projects Overall Increase 104 Looking ahead the single most important measure to avoid such substantial increases in land acquisition and associated costs is to undertake improved early planning and surveys for key project components particularly where the terrain or ground conditions are challenging This will also reduce the additional costs associated with design changes during the construction phase Secondly improved monitoring and supervision of contractors practices by the project developers would have reduced the levels of construction related damage to neighbouring land that triggered additional land acquisition and costs In future GET FiT Programmes more specific requirements on engineering and social surveys and key designs should be defined and met by developers prior to construction start to minimise risks of substantial additional land acquisition design changes increased costs and delays 50 51

Page 53

GET FiT Uganda Annual Report 2020 3 3 Displacement S ubstantial parts of Uganda are blessed with relatively abundant rainfall This provides the basis for hydropower production as well as rainfed subsistence agriculture supporting a high population density in most project areas where GET FiT supported projects were constructed Therefore displacement of people from project land has been a key issue for project developers to manage A review of levels of planned displacement was included in the 2016 GET FiT Annual Report pp 38 41 An update on some of the experiences from implementation of the hydropower projects is included below Most projects experienced substantial increases in land acquisition and displacement from the time of GET FiT approval to project completion GET FiT warned several developers of this risk and asked for project plans to be revised as to be more realistic in terms of land requirements Across the 14 hydropower projects an overall increase in land acquisition of 104 was observed from the time of GET FiT approval to project completion see Figure 21 Excluding the three outliers in Figure 21 the increase in land take was at approximately 30 with the single most important driver being weaknesses in early project planning due to inadequate engineering and social surveys The increased land take at the three outliers can mainly be attributed to significant layout and design changes and an underestimation of inundation and associated buffer zone in one case Inadequate planning resulted in unrealistic plans for land requirements e g too narrow land corridors along the waterway and subsequent design changes and changes in construction methods that triggered additional need for land In addition poor construction practices resulted in damage to neighbouring land that at times had to be acquired Additional land requirements partly necessitated additional land take from people already affected by a project and partly resulted in land take from people not originally subject to land acquisition by a project On average the number of households losing land economic displacement increased by 53 from GET FiT approval to project completion again with large variation between projects from 24 reduction to 367 increase During the detailed planning most developers were able to adjust project plans to avoid increase in physical displacement loss of shelter which on average increased by 9 from GET FiT approval to project completion Only three projects experienced an increase in physical displacement while seven projects were able to reduce physical displacement 350 327 293 300 250 200 174 150 100 46 50 24 24 47 48 64 65 30 0 0 2 2 50 Figure 21 Increase in Land Acquisition from GET FiT Approval to Project Completion for 14 Hydropower Projects Overall Increase 104 Looking ahead the single most important measure to avoid such substantial increases in land acquisition and associated costs is to undertake improved early planning and surveys for key project components particularly where the terrain or ground conditions are challenging This will also reduce the additional costs associated with design changes during the construction phase Secondly improved monitoring and supervision of contractors practices by the project developers would have reduced the levels of construction related damage to neighbouring land that triggered additional land acquisition and costs In future GET FiT Programmes more specific requirements on engineering and social surveys and key designs should be defined and met by developers prior to construction start to minimise risks of substantial additional land acquisition design changes increased costs and delays 50 51

Page 54

GET FiT Uganda Annual Report 2020 04 Grid Connection Technical Assistance 4 1 Portfolio Overview T he evacuation of power from the portfolio of GET FiT projects has continued to pose significant challenges during 2020 Several operational projects have claimed deemed energy because of inadequate grid infrastructure while others under construction face high risks of deemed energy Nevertheless there has been progress to overcome these challenges during this reporting period after concerted efforts by GoU project developers and the GET FiT development partners The graph below highlights the actual energy production plotted against the expected or projected energy and the approved deemed energy claims by project 100 90 140 80 120 70 GWh 100 60 50 80 40 60 30 40 20 20 10 Deemed Energy as Percent of Total Generation Potential in 2020 Actual Deemed 160 0 0 Kakira Kyambura Lubilia Muvumbe Ndugutu Deemed Energy percent Nkusi Nyamwamba Rwimi Planned Energy GWh Sindila Siti 1 Actual Energy GWh Siti 2 Soroti Tororo Waki Deemed Energy GWh Figure 22 Planned Annual and Deemed Energy Generation from GET FiT Projects in 2020 4 2 Key Challenges Interventions T he reinforcement of the national grid to overcome power evacuation issues within and beyond GET FiT is an ongoing process Some key reinforcements have been completed whereas others are ongoing We present here some of the specific power evacuation challenges faced by selected projects with high deemed energy claims and any interventions made by various stakeholders to address these in the past year During the flooding event the measuring equipment for deemed energy was damaged and has not been replaced yet Therefore no deemed energy after May 2020 was recorded 52 53

Page 55

GET FiT Uganda Annual Report 2020 04 Grid Connection Technical Assistance 4 1 Portfolio Overview T he evacuation of power from the portfolio of GET FiT projects has continued to pose significant challenges during 2020 Several operational projects have claimed deemed energy because of inadequate grid infrastructure while others under construction face high risks of deemed energy Nevertheless there has been progress to overcome these challenges during this reporting period after concerted efforts by GoU project developers and the GET FiT development partners The graph below highlights the actual energy production plotted against the expected or projected energy and the approved deemed energy claims by project 100 90 140 80 120 70 GWh 100 60 50 80 40 60 30 40 20 20 10 Deemed Energy as Percent of Total Generation Potential in 2020 Actual Deemed 160 0 0 Kakira Kyambura Lubilia Muvumbe Ndugutu Deemed Energy percent Nkusi Nyamwamba Rwimi Planned Energy GWh Sindila Siti 1 Actual Energy GWh Siti 2 Soroti Tororo Waki Deemed Energy GWh Figure 22 Planned Annual and Deemed Energy Generation from GET FiT Projects in 2020 4 2 Key Challenges Interventions T he reinforcement of the national grid to overcome power evacuation issues within and beyond GET FiT is an ongoing process Some key reinforcements have been completed whereas others are ongoing We present here some of the specific power evacuation challenges faced by selected projects with high deemed energy claims and any interventions made by various stakeholders to address these in the past year During the flooding event the measuring equipment for deemed energy was damaged and has not been replaced yet Therefore no deemed energy after May 2020 was recorded 52 53

Page 56

GET FiT Uganda Annual Report 2020 Waki SHP The 4 8 MW Waki SHP commissioned in December 2018 continued to experience technical constraints to achieving full capacity evacuation in 2020 The project is connected to the Hoima Bulindi Waki 33 kV distribution line operated by UEDCL The technical problems previously reported were frequent line tripping earth faults and poor line clearances along sections inadequate line protection including faulty fuse dropouts and load break switches old electricity poles faulty transformers and lack of remote controlled communication with the auto recloser after a trip The developer Hydromax Nkusi Ltd has reported that there was some improvement in the performance of the grid during 2020 see graph below In the first half of the year UEDCL carried out maintenance works that included the replacement of old poles and line clearances in critical sections The interventions reportedly improved the reliability of the grid and stabilised loads on connected networks This in turn increased the plant s power export to the grid in 2020 compared to 2019 However there remained prolonged grid failures due to old poles and poor line clearances especially in the Budongo forest Additionally UEDCL has reportedly not yet replaced faulty protection hard ware i e dropout fuses insulators and Automatic Break Switches on the network The utility has set up a maintenance schedule in 2021 to address these challenges The developer continues to engage and provide support to the local UEDCL team to minimise grid outages Nkusi SHP The power evacuation of the 9 6 MW Nkusi SHP through the UEDCL operated network in the North Western Service Territory has been characterised by high technical losses since the project s commissioning in June 2018 As a result UEDCL imposed a cap of 6 MW on the plant s generation in 2019 to mitigate losses Additionally 31 km of the 235 km network was upgraded from 100 mm2 to 150 mm2 conductors to improve network performance Technical simulations in 2019 by the System Planning and Coordination Committee SPCC further recommended to split the Nkusi SHP plant into two units 2 x 4 8 MW to be evacuated separately The intervention would reduce the network losses by 50 During 2020 the developer PA Technical Services implemented the SPCC s recommended solution by constructing two power lines evacuating two split units towards Fort Portal and Hoima respectively The construction of the 200 mm2 power lines 14 i ncluding the installation of switches to effect the split was completed and handed over to UEDCL on 8th December 2020 The pending works related to the installation and commissioning of the switchgear have been delayed by the COVID 19 pandemic The completion of this solution is expected to significantly reduce deemed energy claims utages The developer of Sindila SHP has reported o over 2 400 hours of outages since commissioning representing approximately 20 of the time The grid availability has reportedly been below 70 in some months e g October 2020 This has resulted in high deemed energy claims by both projects during the past year Sindila Ndugutu SHPs The grid performance is expected to improve after the construction of new lines and reinforcements to the existing grid by REA with support from the GET FiT interconnection component However this intervention has been delayed as explained in Section 4 3 below The 5 3 MW Sindila and 5 9 MW Ndugutu SHPs in Bundibugyo have faced severe power evacuation challenges since they were commissioned in April and October 2019 respectively Both projects connect to the grid through the same link and are evacuated towards Fort Portal via a pre existing 33 kV line that is over 100 km long The project developer of Sindila SHP Butama Hydro Electricity Company Ltd claimed payment for deemed commissioning from GoU in 2019 due to delayed completion of the line upgrades when the project was declared ready to synchronise to the grid The payment had not been made by the end of 2020 The developer continues to engage GoU through MEMD and ERA to conclude this matter The existing evacuation line has limited capacity to evacuate both projects The production of each project is limited to 3 MW by the grid protection settings in place to mitigate network losses Additionally the grid is highly unreliable and prone to frequent Siti 2 SHP The 16 5 MW Siti 2 SHP has since commissioning in July 2019 been marginally evacuated through a 33kV line connected to a UEDCL operated distribution grid that also evacuates Siti 1 SHP The connection provides limited evacuation capacity for Siti 2 resulting in high deemed energy claims in 2020 The evacuation through Siti 1 was an interim measure to enable commissioning while a new 130 km 33 kV line to Mbale substation was being constructed by Umeme Following extended delays due to wayleave issues and travel restrictions the new 33 kV line operated by Umeme was energised and commissioned in December 2020 The connection point of Siti 2 was 12 10 8 6 4 2 Year 2019 Forced Grid failures in hrs Year 2019 Planned Schedule outages by UEDCL Year 2020 Forced Grid failures in hrs Year 2020 Planned Schedule outages by UEDCL December November October September August July June May April March February January 0 Status as of 31 01 2020 Figure 23 Illustration of the Grid Outages in 2019 and 2020 for Waki SHP Source Hydromax 54 55

Page 57

GET FiT Uganda Annual Report 2020 Waki SHP The 4 8 MW Waki SHP commissioned in December 2018 continued to experience technical constraints to achieving full capacity evacuation in 2020 The project is connected to the Hoima Bulindi Waki 33 kV distribution line operated by UEDCL The technical problems previously reported were frequent line tripping earth faults and poor line clearances along sections inadequate line protection including faulty fuse dropouts and load break switches old electricity poles faulty transformers and lack of remote controlled communication with the auto recloser after a trip The developer Hydromax Nkusi Ltd has reported that there was some improvement in the performance of the grid during 2020 see graph below In the first half of the year UEDCL carried out maintenance works that included the replacement of old poles and line clearances in critical sections The interventions reportedly improved the reliability of the grid and stabilised loads on connected networks This in turn increased the plant s power export to the grid in 2020 compared to 2019 However there remained prolonged grid failures due to old poles and poor line clearances especially in the Budongo forest Additionally UEDCL has reportedly not yet replaced faulty protection hard ware i e dropout fuses insulators and Automatic Break Switches on the network The utility has set up a maintenance schedule in 2021 to address these challenges The developer continues to engage and provide support to the local UEDCL team to minimise grid outages Nkusi SHP The power evacuation of the 9 6 MW Nkusi SHP through the UEDCL operated network in the North Western Service Territory has been characterised by high technical losses since the project s commissioning in June 2018 As a result UEDCL imposed a cap of 6 MW on the plant s generation in 2019 to mitigate losses Additionally 31 km of the 235 km network was upgraded from 100 mm2 to 150 mm2 conductors to improve network performance Technical simulations in 2019 by the System Planning and Coordination Committee SPCC further recommended to split the Nkusi SHP plant into two units 2 x 4 8 MW to be evacuated separately The intervention would reduce the network losses by 50 During 2020 the developer PA Technical Services implemented the SPCC s recommended solution by constructing two power lines evacuating two split units towards Fort Portal and Hoima respectively The construction of the 200 mm2 power lines 14 i ncluding the installation of switches to effect the split was completed and handed over to UEDCL on 8th December 2020 The pending works related to the installation and commissioning of the switchgear have been delayed by the COVID 19 pandemic The completion of this solution is expected to significantly reduce deemed energy claims utages The developer of Sindila SHP has reported o over 2 400 hours of outages since commissioning representing approximately 20 of the time The grid availability has reportedly been below 70 in some months e g October 2020 This has resulted in high deemed energy claims by both projects during the past year Sindila Ndugutu SHPs The grid performance is expected to improve after the construction of new lines and reinforcements to the existing grid by REA with support from the GET FiT interconnection component However this intervention has been delayed as explained in Section 4 3 below The 5 3 MW Sindila and 5 9 MW Ndugutu SHPs in Bundibugyo have faced severe power evacuation challenges since they were commissioned in April and October 2019 respectively Both projects connect to the grid through the same link and are evacuated towards Fort Portal via a pre existing 33 kV line that is over 100 km long The project developer of Sindila SHP Butama Hydro Electricity Company Ltd claimed payment for deemed commissioning from GoU in 2019 due to delayed completion of the line upgrades when the project was declared ready to synchronise to the grid The payment had not been made by the end of 2020 The developer continues to engage GoU through MEMD and ERA to conclude this matter The existing evacuation line has limited capacity to evacuate both projects The production of each project is limited to 3 MW by the grid protection settings in place to mitigate network losses Additionally the grid is highly unreliable and prone to frequent Siti 2 SHP The 16 5 MW Siti 2 SHP has since commissioning in July 2019 been marginally evacuated through a 33kV line connected to a UEDCL operated distribution grid that also evacuates Siti 1 SHP The connection provides limited evacuation capacity for Siti 2 resulting in high deemed energy claims in 2020 The evacuation through Siti 1 was an interim measure to enable commissioning while a new 130 km 33 kV line to Mbale substation was being constructed by Umeme Following extended delays due to wayleave issues and travel restrictions the new 33 kV line operated by Umeme was energised and commissioned in December 2020 The connection point of Siti 2 was 12 10 8 6 4 2 Year 2019 Forced Grid failures in hrs Year 2019 Planned Schedule outages by UEDCL Year 2020 Forced Grid failures in hrs Year 2020 Planned Schedule outages by UEDCL December November October September August July June May April March February January 0 Status as of 31 01 2020 Figure 23 Illustration of the Grid Outages in 2019 and 2020 for Waki SHP Source Hydromax 54 55

Page 58

GET FiT Uganda Annual Report 2020 s hifted accordingly to the new line The line faced initial technical challenges related to loose connections unbalanced loading and high voltages at specific times in the day The unbalanced loading and high voltages have generally been streamlined by adjusting the plant s unit settings upwards in the interim to minimise related outages It was regarded as an interim solution pending the construction of the high voltage HV Mbale Bulambuli transmission line by UETCL The planned 79 km HV line is expected to ultimately evacuate both Siti 1 and 2 SHPs and eliminate transmission bottlenecks in Eastern Uganda for a range of small hydro power plants in the region Tests undertaken at the time indicated that the line could evacuate up to 12 MW with the available water levels Tests for full capacity evacuation are expected to be undertaken in 2021 when higher water levels become available The feasibility study for the line including ESIA scoping was completed in 2019 with funding from the EU ITF through KfW The detailed ESIA was launched in November 2020 and is currently ongoing The RAP study is expected to start in early 2021 The financing of the line is not yet concluded pending loan approvals from GoU The planned completion timeline for commissioning the line according to UETCL is end 2024 Mbale Bulambuli Transmission Line The above 130 km 33 kV line evacuating Siti 2 is still characterised by generally high technical losses due to its long distance and low transmission voltage 4 3 GET FiT Interconnection Support The Programme has solicited for funds to support GoU in the development of critical infrastructure and reinforcements to facilitate grid interconnection of renewable energy projects All funding has been provided by the UK Department for International Development DFID which is now the Foreign Commonwealth Development Office FCDO We present a status update of the different components which are summarised in the table below together with their associated investment needs Required Intervention 1 Reinforcement of 33 kV networks in Western Uganda 2 Opuyo Substation upgrade 3 TA support to ERA Total grid interconnection support Reinforcement of 33 kV networks in Western Uganda This component is aimed at developing and reinforcing 33 kV lines to secure the adequate grid integration and power evacuation of five GET FiT projects i e Nyamagasani 1 Nyamagasani 2 Lubilia Sindila and Ndugutu SHPs in Kasese and Bundibugyo districts The projects have a combined capacity of 37 MW 56 During 2020 the technical designs were reportedly 90 complete for both Lots and the procurement of materials was at 90 and 60 for Lots A and B respectively However the line routes for each lot had to be reviewed by REA in order to optimise the wayleaves costs and social impact of the lines in the national park and densely populated areas The line route was finalised and the contractors are currently redesigning the sections that were re routed This exercise is expected to be completed end of March 2021 REA had previously conducted assessments to establish wayleave compensation costs along the corridor of the original line route The Agency had also made some limited compensation payments to Project Affected Persons PAPs on some sections of the line in Lot B Another study on the rerouted line sections is to be conducted to establish the final compensation costs The Government through MOFPED has committed to prioritise and avail funds for compensation once the final costs are established by REA This followed high level engagements between GoU KfW and the GET FiT development partners In accordance with IFC Performance Standards line construction should only commence after PAPs have been compensated by REA The planned timeline for start of construction is the second quarter of 2021 according to REA The construction period is expected to be one year Opuyo Substation Upgrade The main objective of this interconnection component was to upgrade the transformation capacity of UETCL s Opuyo high voltage transmission substation from a single 10 14 MVA 132 33 kV transformer to two 40 MVA 132 33 kV transformers This was aimed at facilitating improved grid reliability and security for the evacuation of existing and planned solar generation power plants in Eastern Uganda including the Soroti solar PV plant The project commenced in May 2018 The implementation schedule according to the original contracts was 16 months but there have been delays due to slower than expected construction of the civil works All designs procurements and construction have been completed and the upgraded substation is expected to be energised and commissioned by the end of Q1 2021 4 4 Technical Assistance to ERA Table 2 Funding Commitments for Interconnection Support through GET FiT Item elayed from the initial completion timeline of Aud gust 2019 due to several challenges particularly related to much higher than anticipated wayleaves costs Project Owner Estimated Investment Need MUSD REA 13 UETCL 5 8 ERA 3 7 22 5 The implementing agency REA procured two EPC contractors in August 2018 to build the lines in two lots Lot A construction of 104 km of new 33 kV lines from Bundibugyo to Fort Portal and Lot B construction of 120 km of new 33 kV lines in Kasese district The project implementation has been e xtensively Regulatory Information Management System RIMS The RIMS project is the last of a series of components under the GET FiT Technical Assistance Facility to provide capacity building support to ERA and other sector agencies over the years Previous TA components are documented in earlier annual reports available at https www getfit uganda org annual reports The objective of the RIMS at ERA is to enhance the Regulator s information collection and data processing automate regulatory analysis and compliance monitoring and facilitate stronger web based stakeholder engagements for effective service delivery The project commenced in May 2018 During 2020 the initial system design preparation of tender documents and launch of the tender for the final design supply and installation of the RIMS were completed The tender was launched in April 2020 Following a detailed evaluation of bids the contract was awarded to a Kenya based firm in October 2020 The entire process was fully coordinated by ERA with support from KfW and the GET FiT Secretariat The contractor kicked off the project in November 2020 The System is expected to be installed and ready to go online in the third quarter of 2021 57

Page 59

GET FiT Uganda Annual Report 2020 s hifted accordingly to the new line The line faced initial technical challenges related to loose connections unbalanced loading and high voltages at specific times in the day The unbalanced loading and high voltages have generally been streamlined by adjusting the plant s unit settings upwards in the interim to minimise related outages It was regarded as an interim solution pending the construction of the high voltage HV Mbale Bulambuli transmission line by UETCL The planned 79 km HV line is expected to ultimately evacuate both Siti 1 and 2 SHPs and eliminate transmission bottlenecks in Eastern Uganda for a range of small hydro power plants in the region Tests undertaken at the time indicated that the line could evacuate up to 12 MW with the available water levels Tests for full capacity evacuation are expected to be undertaken in 2021 when higher water levels become available The feasibility study for the line including ESIA scoping was completed in 2019 with funding from the EU ITF through KfW The detailed ESIA was launched in November 2020 and is currently ongoing The RAP study is expected to start in early 2021 The financing of the line is not yet concluded pending loan approvals from GoU The planned completion timeline for commissioning the line according to UETCL is end 2024 Mbale Bulambuli Transmission Line The above 130 km 33 kV line evacuating Siti 2 is still characterised by generally high technical losses due to its long distance and low transmission voltage 4 3 GET FiT Interconnection Support The Programme has solicited for funds to support GoU in the development of critical infrastructure and reinforcements to facilitate grid interconnection of renewable energy projects All funding has been provided by the UK Department for International Development DFID which is now the Foreign Commonwealth Development Office FCDO We present a status update of the different components which are summarised in the table below together with their associated investment needs Required Intervention 1 Reinforcement of 33 kV networks in Western Uganda 2 Opuyo Substation upgrade 3 TA support to ERA Total grid interconnection support Reinforcement of 33 kV networks in Western Uganda This component is aimed at developing and reinforcing 33 kV lines to secure the adequate grid integration and power evacuation of five GET FiT projects i e Nyamagasani 1 Nyamagasani 2 Lubilia Sindila and Ndugutu SHPs in Kasese and Bundibugyo districts The projects have a combined capacity of 37 MW 56 During 2020 the technical designs were reportedly 90 complete for both Lots and the procurement of materials was at 90 and 60 for Lots A and B respectively However the line routes for each lot had to be reviewed by REA in order to optimise the wayleaves costs and social impact of the lines in the national park and densely populated areas The line route was finalised and the contractors are currently redesigning the sections that were re routed This exercise is expected to be completed end of March 2021 REA had previously conducted assessments to establish wayleave compensation costs along the corridor of the original line route The Agency had also made some limited compensation payments to Project Affected Persons PAPs on some sections of the line in Lot B Another study on the rerouted line sections is to be conducted to establish the final compensation costs The Government through MOFPED has committed to prioritise and avail funds for compensation once the final costs are established by REA This followed high level engagements between GoU KfW and the GET FiT development partners In accordance with IFC Performance Standards line construction should only commence after PAPs have been compensated by REA The planned timeline for start of construction is the second quarter of 2021 according to REA The construction period is expected to be one year Opuyo Substation Upgrade The main objective of this interconnection component was to upgrade the transformation capacity of UETCL s Opuyo high voltage transmission substation from a single 10 14 MVA 132 33 kV transformer to two 40 MVA 132 33 kV transformers This was aimed at facilitating improved grid reliability and security for the evacuation of existing and planned solar generation power plants in Eastern Uganda including the Soroti solar PV plant The project commenced in May 2018 The implementation schedule according to the original contracts was 16 months but there have been delays due to slower than expected construction of the civil works All designs procurements and construction have been completed and the upgraded substation is expected to be energised and commissioned by the end of Q1 2021 4 4 Technical Assistance to ERA Table 2 Funding Commitments for Interconnection Support through GET FiT Item elayed from the initial completion timeline of Aud gust 2019 due to several challenges particularly related to much higher than anticipated wayleaves costs Project Owner Estimated Investment Need MUSD REA 13 UETCL 5 8 ERA 3 7 22 5 The implementing agency REA procured two EPC contractors in August 2018 to build the lines in two lots Lot A construction of 104 km of new 33 kV lines from Bundibugyo to Fort Portal and Lot B construction of 120 km of new 33 kV lines in Kasese district The project implementation has been e xtensively Regulatory Information Management System RIMS The RIMS project is the last of a series of components under the GET FiT Technical Assistance Facility to provide capacity building support to ERA and other sector agencies over the years Previous TA components are documented in earlier annual reports available at https www getfit uganda org annual reports The objective of the RIMS at ERA is to enhance the Regulator s information collection and data processing automate regulatory analysis and compliance monitoring and facilitate stronger web based stakeholder engagements for effective service delivery The project commenced in May 2018 During 2020 the initial system design preparation of tender documents and launch of the tender for the final design supply and installation of the RIMS were completed The tender was launched in April 2020 Following a detailed evaluation of bids the contract was awarded to a Kenya based firm in October 2020 The entire process was fully coordinated by ERA with support from KfW and the GET FiT Secretariat The contractor kicked off the project in November 2020 The System is expected to be installed and ready to go online in the third quarter of 2021 57

Page 60

GET FiT Uganda Annual Report 2020 05 Financial Status 5 1 Funding Commitments G 58 ET FiT Uganda is dependent on predictable commitments from sponsors in order to be successful since it is a results based Programme meaning that subsidies are being paid following actual delivery of energy Several changes were made to the portfolio structure since the Programme s inception in 2013 demanding an active follow up from all stakeholders This requirement has also been met by the GET FiT funders to date enabling the Programme to deal with any arising uncertainties and risks in a relatively pro active manner Four development partners have taken up the challenge and provided GET FiT with the necessary funding Government of Norway Government of UK through BEIS and FCDO formerly DFID Germany BMZ and the EU through EU ITF About EUR 93 million has been committed to the Programme and an overview of the respective commitments can be found in the table on the right Table 3 Overall Donor Commitments to GET FiT Exchange rate developments had an adverse impact on the overall budget of GET FiT Uganda due to donor commitments in GBP A budget buffer was introduced to cushion future decline in the EUR GBP rate until remaining GBP disbursements were made to KfW and converted in EUR Reference is made to previous GET FiT annual reports Only a limited amount of undisbursed donor contributions remains at this stage Approximately 8 of the total GET FiT budget in form of 6 5 million GBP remains subject to foreign exchange risk GET FiT frequently monitors exchange rate developments to allow for proactive action if needed Donor Net Amount Committed EUR Norway 15 592 885 UK BEIS 28 009 040 UK FCDO formerly UK DFID 14 129 894 GER BMZ 15 000 000 EU ITF 20 000 000 Total 92 731 819 Note Net amounts are based on funding disbursed to the Programme thus far projected exchange rates for undisbursed funds and deduction of management fees 59

Page 61

GET FiT Uganda Annual Report 2020 05 Financial Status 5 1 Funding Commitments G 58 ET FiT Uganda is dependent on predictable commitments from sponsors in order to be successful since it is a results based Programme meaning that subsidies are being paid following actual delivery of energy Several changes were made to the portfolio structure since the Programme s inception in 2013 demanding an active follow up from all stakeholders This requirement has also been met by the GET FiT funders to date enabling the Programme to deal with any arising uncertainties and risks in a relatively pro active manner Four development partners have taken up the challenge and provided GET FiT with the necessary funding Government of Norway Government of UK through BEIS and FCDO formerly DFID Germany BMZ and the EU through EU ITF About EUR 93 million has been committed to the Programme and an overview of the respective commitments can be found in the table on the right Table 3 Overall Donor Commitments to GET FiT Exchange rate developments had an adverse impact on the overall budget of GET FiT Uganda due to donor commitments in GBP A budget buffer was introduced to cushion future decline in the EUR GBP rate until remaining GBP disbursements were made to KfW and converted in EUR Reference is made to previous GET FiT annual reports Only a limited amount of undisbursed donor contributions remains at this stage Approximately 8 of the total GET FiT budget in form of 6 5 million GBP remains subject to foreign exchange risk GET FiT frequently monitors exchange rate developments to allow for proactive action if needed Donor Net Amount Committed EUR Norway 15 592 885 UK BEIS 28 009 040 UK FCDO formerly UK DFID 14 129 894 GER BMZ 15 000 000 EU ITF 20 000 000 Total 92 731 819 Note Net amounts are based on funding disbursed to the Programme thus far projected exchange rates for undisbursed funds and deduction of management fees 59

Page 62

GET FiT Uganda Annual Report 2020 5 2 Disbursement Projections GET FiT funds are disbursed for the following three purposes Project grants where 50 is paid at commercial operation date and 50 paid in the form of results based support over the first five years of operation subject to actual generation Consultants under the Technical Assistance Facility for ERA Consultants for the overall management and monitoring of the Programme Figure 24 illustrates the actual and projected disbursements from the Programme The overview includes net funding available to the Programme only The projections are based on the status of the project portfolio and expected progress During the first five years of operation of each project results based disbursements in the form of annual subsidies are made In the disbursement projections the main uncertainty relates to actual COD for the various projects Project construction delays have influenced the disbursement profile delaying the payment of COD premiums and annual subsidies With the majority of projects commissioned and the three projects remaining under construction expected to achieve COD during 2021 there is limited risk for further shifts or delays in the disbursement However the COD disbursement amount in 2021 is subject to some variation as projects face monthly subsidy penalties for construction delays during 2020 and 2021 Furthermore there is also some uncertainty tied to the annual result based payments for each project Since the developers will only be paid for what they are producing with a cap at their planned average energy generation under production may lead to accumulation of excess funding In addition eligibility for the annual subsidy payments will end in 2023 for all projects except for Kikagati for which the eligibility will end in 2024 as the project has been granted an exception due to trans boundary issues signifying that there will not be any disbursement after 2024 resulting in additional available funds It has been agreed with donors that excess funding may be allocated to the interconnection components that are supported by GET FiT 11 The annual GET FiT Steering Committee SC meeting was held online on September 15 2020 with representatives from the German Embassy UK FCDO UK BEIS the European Union ERA the Embassy of Norway MEMD MOFPED KfW and the GET FiT Secretariat Multiconsult A key topic of the 2020 SC meeting was delays at the projects under construction 16 Total accumulated Consultants 6 7 Premium Payments Bagasse 7 0 Premium Payments Hydro 68 2 Figure 25 Distribution of Budget Reservation of GET FiT Uganda Figure 25 shows the relative shares of the various cost components under the GET FiT Programme based on current budget reservations Overall approximately 8 of the overall funds are tied to management implementation and the Technical Assistance Facility while 92 of the total commitments are allocated to premium payments 90 TA Facility Consultants 60 accumulated 50 10 8 40 6 30 4 20 2 Million EUR accumulated 70 12 Million EUR Premium Payments Solar 17 0 TA Facility 1 1 80 14 0 articularly in relation to the Force Majeure events p caused by the global COVID 19 pandemic and floods in early 2020 As multiple projects have declared Force Majeure events in 2020 it was decided that the COD deadline for affected projects under construction can be extended by up to 6 months noting that the actual Force Majeure duration is subject to legal review and progress assessment The annual subsidy cut offs in 2023 and 2024 remain for the projects under construction Projects in operation that were affected by floods will receive additional follow up by the Programme and an extension of the annual subsidy cut off by up to one year can be granted subject to available funds 10 2013 2014 2015 2016 TA Facility Consultants 2017 2018 2019 2020 COD Premium Payments 2021e 2022e 2023e 2024e 0 Annual Subsidy Payments Figure 24 Projected Annual Payments Premium Payments and Consultants under GET FiT Note Projections are subject to budget uncertainty related to individual project progress Subsidy penalties were considered in the disbursement projection 11 The GET FiT commitments to the interconnection component is not included in the financial status overview and disbursement projections 60 61

Page 63

GET FiT Uganda Annual Report 2020 5 2 Disbursement Projections GET FiT funds are disbursed for the following three purposes Project grants where 50 is paid at commercial operation date and 50 paid in the form of results based support over the first five years of operation subject to actual generation Consultants under the Technical Assistance Facility for ERA Consultants for the overall management and monitoring of the Programme Figure 24 illustrates the actual and projected disbursements from the Programme The overview includes net funding available to the Programme only The projections are based on the status of the project portfolio and expected progress During the first five years of operation of each project results based disbursements in the form of annual subsidies are made In the disbursement projections the main uncertainty relates to actual COD for the various projects Project construction delays have influenced the disbursement profile delaying the payment of COD premiums and annual subsidies With the majority of projects commissioned and the three projects remaining under construction expected to achieve COD during 2021 there is limited risk for further shifts or delays in the disbursement However the COD disbursement amount in 2021 is subject to some variation as projects face monthly subsidy penalties for construction delays during 2020 and 2021 Furthermore there is also some uncertainty tied to the annual result based payments for each project Since the developers will only be paid for what they are producing with a cap at their planned average energy generation under production may lead to accumulation of excess funding In addition eligibility for the annual subsidy payments will end in 2023 for all projects except for Kikagati for which the eligibility will end in 2024 as the project has been granted an exception due to trans boundary issues signifying that there will not be any disbursement after 2024 resulting in additional available funds It has been agreed with donors that excess funding may be allocated to the interconnection components that are supported by GET FiT 11 The annual GET FiT Steering Committee SC meeting was held online on September 15 2020 with representatives from the German Embassy UK FCDO UK BEIS the European Union ERA the Embassy of Norway MEMD MOFPED KfW and the GET FiT Secretariat Multiconsult A key topic of the 2020 SC meeting was delays at the projects under construction 16 Total accumulated Consultants 6 7 Premium Payments Bagasse 7 0 Premium Payments Hydro 68 2 Figure 25 Distribution of Budget Reservation of GET FiT Uganda Figure 25 shows the relative shares of the various cost components under the GET FiT Programme based on current budget reservations Overall approximately 8 of the overall funds are tied to management implementation and the Technical Assistance Facility while 92 of the total commitments are allocated to premium payments 90 TA Facility Consultants 60 accumulated 50 10 8 40 6 30 4 20 2 Million EUR accumulated 70 12 Million EUR Premium Payments Solar 17 0 TA Facility 1 1 80 14 0 articularly in relation to the Force Majeure events p caused by the global COVID 19 pandemic and floods in early 2020 As multiple projects have declared Force Majeure events in 2020 it was decided that the COD deadline for affected projects under construction can be extended by up to 6 months noting that the actual Force Majeure duration is subject to legal review and progress assessment The annual subsidy cut offs in 2023 and 2024 remain for the projects under construction Projects in operation that were affected by floods will receive additional follow up by the Programme and an extension of the annual subsidy cut off by up to one year can be granted subject to available funds 10 2013 2014 2015 2016 TA Facility Consultants 2017 2018 2019 2020 COD Premium Payments 2021e 2022e 2023e 2024e 0 Annual Subsidy Payments Figure 24 Projected Annual Payments Premium Payments and Consultants under GET FiT Note Projections are subject to budget uncertainty related to individual project progress Subsidy penalties were considered in the disbursement projection 11 The GET FiT commitments to the interconnection component is not included in the financial status overview and disbursement projections 60 61

Page 64

GET FiT Uganda Annual Report 2020 06 Programme Monitoring Risk Management 6 1 Programme Monitoring T he GET FiT Monitoring and Evaluation framework monitors the results of the Programme through several quantitative indicators which are collected from project developers and key sector stakeholders on an annual basis The Programme s monitoring and evaluation is structured in a logical framework Logframe outlining the relationship between targeted Outputs Outcomes and Impacts and setting baselines expected milestones and targets Nevertheless the project portfolio delivered a 20 increase in energy generation in 2020 and is already reaching and even exceeding some 2023 targets such as job creation and sector related indicators With expected commissioning of the entire portfolio in 2021 and improved grid connection for some operational projects the Programme also expects continued improvement in delivered results in the coming years The Programme is behind schedule on achieving the original capacity targets which aimed at full commissioning of the RE portfolio by the end of 2018 Despite the delays in project implementation intensive efforts in previous years have resulted in good progress on most reporting dimensions An overview of the targeted Outputs Outcomes and Impacts is provided in the overview below The following section will address these goals in more depth providing details and context on the development of the Programme Notably due to a lower share of biomass projects in the portfolio than anticipated the original capacity targets of 170 MW and 830 GWh year will not be achieved Programme targets have not been revised to this end Other targets that relate to the portfolio size such as finance mobilised or displacement of thermal generation are also be affected by the overall reduced capacity of the portfolio Table 4 Overview of Impact Outcomes and Outputs Outputs 1 Increased small scale RE capacity generation 2 Balanced portfolio of RE technologies 3 Reduced GHG emissions 4 Increased number of Ugandan national jobs Outcomes 1 Improved private sector investment environment for renewable energy in Uganda 2 Improved financial stability of energy sector Impact Uganda pursues a low carbon climate resilient development path resulting in growth poverty reduction and climate change mitigation 3 Improved local grid stability 5 Increased capacity of ERA 6 Finance mobilised for GET FiT portfolio 62 63

Page 65

GET FiT Uganda Annual Report 2020 06 Programme Monitoring Risk Management 6 1 Programme Monitoring T he GET FiT Monitoring and Evaluation framework monitors the results of the Programme through several quantitative indicators which are collected from project developers and key sector stakeholders on an annual basis The Programme s monitoring and evaluation is structured in a logical framework Logframe outlining the relationship between targeted Outputs Outcomes and Impacts and setting baselines expected milestones and targets Nevertheless the project portfolio delivered a 20 increase in energy generation in 2020 and is already reaching and even exceeding some 2023 targets such as job creation and sector related indicators With expected commissioning of the entire portfolio in 2021 and improved grid connection for some operational projects the Programme also expects continued improvement in delivered results in the coming years The Programme is behind schedule on achieving the original capacity targets which aimed at full commissioning of the RE portfolio by the end of 2018 Despite the delays in project implementation intensive efforts in previous years have resulted in good progress on most reporting dimensions An overview of the targeted Outputs Outcomes and Impacts is provided in the overview below The following section will address these goals in more depth providing details and context on the development of the Programme Notably due to a lower share of biomass projects in the portfolio than anticipated the original capacity targets of 170 MW and 830 GWh year will not be achieved Programme targets have not been revised to this end Other targets that relate to the portfolio size such as finance mobilised or displacement of thermal generation are also be affected by the overall reduced capacity of the portfolio Table 4 Overview of Impact Outcomes and Outputs Outputs 1 Increased small scale RE capacity generation 2 Balanced portfolio of RE technologies 3 Reduced GHG emissions 4 Increased number of Ugandan national jobs Outcomes 1 Improved private sector investment environment for renewable energy in Uganda 2 Improved financial stability of energy sector Impact Uganda pursues a low carbon climate resilient development path resulting in growth poverty reduction and climate change mitigation 3 Improved local grid stability 5 Increased capacity of ERA 6 Finance mobilised for GET FiT portfolio 62 63

Page 66

Annual Report 2020 GET FiT Uganda Outputs The Programme made limited progress in terms of commissioning projects and increasing the installed capacity as three projects still remain under constructions with delays experienced due to flooding damage and the coronavirus pandemic Electricity generation picked up considerably with approximately 380 GWh delivered to the grid in 2020 which is a 20 increase since 2019 This represents approximately 70 of planned annual generation of commissioned projects overall This difference is largely due to grid related issues causing high deemed energy levels for certain projects With the three remaining projects expected to commission in 2021 the overall portfolio generation is expected to increase in the coming calendar year The GET FiT portfolio is contributing to the country s geographical and technological diversification being represented in most regions of the country and multiple renewable energy technologies In addition it is diversifying the group of developers contractors and other players that participate in the Ugandan electricity sector almost 50 of the generating power plants in the country 14 out of 33 are supported by GET FiT With an increasing level of energy generation the Programme portfolio is contributing to reducing Uganda s GHG emissions Thermal generation has reduced significantly from 200 GWh in 2018 to 100 GWh in 2019 and to approximately 50 GWh in 2020 Table 5 Output Indicators The GET FiT portfolio has direct effects on the local economy and made a substantial contribution to local job creation This is represented by approximately 11 750 newly created jobs FTE s Full Time Equivalent by far exceeding the initial target In 2020 the portfolio has contributed almost another 1 400 FTE jobs compared to last year s 1 700 This decline is due to more projects reaching commercial operations and fewer construction jobs Notably the share of Ugandan employment remains at about 90 In addition indicators relating to the Technical Assistance activities at the regulator ERA provide positive signals Time efficient issuance of generation licences has slightly improved from last year exceeding the initially targeted processing time of 2 months Due to delays in the implementation of the RIMS component licensee reporting has not been digitalised yet A roll out of the platform is expected for July 2021 Further GET FiT is happy to see ERA being ranked number 1 in the Africa Electricity Regulatory Index for the third time in a row Finally GET FiT projects have raised over USD 455 million in investments for the portfolio approximately USD 165 million in private and USD 290 million in public funding Private financing represents a share of 36 An overview of all Output indicators is presented in Table 5 Indicator Target 2023 Status 2020 Target Achieved Comment Output 1 Increased small scale renewable energy capacity and generation Indicator 1 1 MW installed Indicator 1 2 GWh year delivered to the national grid 170 158 4 122 4 830 760 380 77 The current portfolio has a planned capacity of 158 4 MW The original target of 170 MW will not be achieved due to lower availability of Programme funds and a lower share of biomass projects than originally expected 46 Commissioned projects have an expected annual generation of 557 7 GWh Deemed Energy in 2020 was 130 GWh which is not considered in the reported value The current portfolio has a planned total output of approximately 760 GWh year Output 2 Balanced portfolio of renewable energy technologies Indicator 2 1 Number of technologies supported by GET FiT 4 3 75 Supported technologies include hydropower solar PV and bagasse Indicator 2 2 Number of sub regions with GET FiT projects 5 4 80 The GET FiT portfolio includes 4 regions Western South Western Eastern and Central 22 The cumulative net change in 2019 was at 0 65 and increased by approximately 250 000 tonnes The indicator is behind target due to the delayed portfolio implementation Output 3 Reduced GHG emissions Indicator 3 1 Net change in GHG emissions Cumulative MtCO2e 4 03 0 90 Output 4 Increased number of Ugandan national jobs Indicator 4 1 Number of direct national construction and O M jobs FTE created 4 200 11 732 280 GET FiT is exceeding targets on this indicator Approximately 1 400 full time equivalent FTE jobs were created in 2020 Indicator 5 1 Time taken by ERA to review generation licence for 1 20 MW renewable energy applications months 2 0 8 n a Two generation licences were reviewed in 2020 with an average time taken for the review of 25 days This is slightly less than last year s value and exceeds the 2023 target Indicator 5 2 Number of REFiT tariff reviews taking place by ERA per year 1 0 0 REFiT tariffs are not reviewed on an annual basis The last review REFiT IV concluded in April 2019 and will be effective for two years Indicator 5 3 Timely and complete reporting to ERA by licensees 100 93 93 164 out of 176 reports were submitted complete and on time Indicator 5 4 Online delivery of ERA services 50 0 0 The Regulatory Information Management System RIMS is expected to be rolled out in July 2021 83 All projects have reached financial close Due to the reduced portfolio size following inception the target will not be reached In the reporting period more than EUR 10 million have been injected into the projects under construction due to COVID 19 and flooding incidents This is not considered in the value as finance mobilised is reported at financial close 97 Mobilised finance at financial close All projects have reached financial close Due to the reduced portfolio size following inception the target will not be fully reached The public finance has increased in 2020 for the projects under construction as project cost has increased Output 5 Increased capacity at ERA Output 6 Finance mobilised for GET FiT portfolio Indicator 6 1 Private finance mobilised for GET FiT portfolio in USD million Indicator 6 2 Public finance mobilised for GET FiT portfolio in USD million 64 200 300 165 290 65

Page 67

Annual Report 2020 GET FiT Uganda Outputs The Programme made limited progress in terms of commissioning projects and increasing the installed capacity as three projects still remain under constructions with delays experienced due to flooding damage and the coronavirus pandemic Electricity generation picked up considerably with approximately 380 GWh delivered to the grid in 2020 which is a 20 increase since 2019 This represents approximately 70 of planned annual generation of commissioned projects overall This difference is largely due to grid related issues causing high deemed energy levels for certain projects With the three remaining projects expected to commission in 2021 the overall portfolio generation is expected to increase in the coming calendar year The GET FiT portfolio is contributing to the country s geographical and technological diversification being represented in most regions of the country and multiple renewable energy technologies In addition it is diversifying the group of developers contractors and other players that participate in the Ugandan electricity sector almost 50 of the generating power plants in the country 14 out of 33 are supported by GET FiT With an increasing level of energy generation the Programme portfolio is contributing to reducing Uganda s GHG emissions Thermal generation has reduced significantly from 200 GWh in 2018 to 100 GWh in 2019 and to approximately 50 GWh in 2020 Table 5 Output Indicators The GET FiT portfolio has direct effects on the local economy and made a substantial contribution to local job creation This is represented by approximately 11 750 newly created jobs FTE s Full Time Equivalent by far exceeding the initial target In 2020 the portfolio has contributed almost another 1 400 FTE jobs compared to last year s 1 700 This decline is due to more projects reaching commercial operations and fewer construction jobs Notably the share of Ugandan employment remains at about 90 In addition indicators relating to the Technical Assistance activities at the regulator ERA provide positive signals Time efficient issuance of generation licences has slightly improved from last year exceeding the initially targeted processing time of 2 months Due to delays in the implementation of the RIMS component licensee reporting has not been digitalised yet A roll out of the platform is expected for July 2021 Further GET FiT is happy to see ERA being ranked number 1 in the Africa Electricity Regulatory Index for the third time in a row Finally GET FiT projects have raised over USD 455 million in investments for the portfolio approximately USD 165 million in private and USD 290 million in public funding Private financing represents a share of 36 An overview of all Output indicators is presented in Table 5 Indicator Target 2023 Status 2020 Target Achieved Comment Output 1 Increased small scale renewable energy capacity and generation Indicator 1 1 MW installed Indicator 1 2 GWh year delivered to the national grid 170 158 4 122 4 830 760 380 77 The current portfolio has a planned capacity of 158 4 MW The original target of 170 MW will not be achieved due to lower availability of Programme funds and a lower share of biomass projects than originally expected 46 Commissioned projects have an expected annual generation of 557 7 GWh Deemed Energy in 2020 was 130 GWh which is not considered in the reported value The current portfolio has a planned total output of approximately 760 GWh year Output 2 Balanced portfolio of renewable energy technologies Indicator 2 1 Number of technologies supported by GET FiT 4 3 75 Supported technologies include hydropower solar PV and bagasse Indicator 2 2 Number of sub regions with GET FiT projects 5 4 80 The GET FiT portfolio includes 4 regions Western South Western Eastern and Central 22 The cumulative net change in 2019 was at 0 65 and increased by approximately 250 000 tonnes The indicator is behind target due to the delayed portfolio implementation Output 3 Reduced GHG emissions Indicator 3 1 Net change in GHG emissions Cumulative MtCO2e 4 03 0 90 Output 4 Increased number of Ugandan national jobs Indicator 4 1 Number of direct national construction and O M jobs FTE created 4 200 11 732 280 GET FiT is exceeding targets on this indicator Approximately 1 400 full time equivalent FTE jobs were created in 2020 Indicator 5 1 Time taken by ERA to review generation licence for 1 20 MW renewable energy applications months 2 0 8 n a Two generation licences were reviewed in 2020 with an average time taken for the review of 25 days This is slightly less than last year s value and exceeds the 2023 target Indicator 5 2 Number of REFiT tariff reviews taking place by ERA per year 1 0 0 REFiT tariffs are not reviewed on an annual basis The last review REFiT IV concluded in April 2019 and will be effective for two years Indicator 5 3 Timely and complete reporting to ERA by licensees 100 93 93 164 out of 176 reports were submitted complete and on time Indicator 5 4 Online delivery of ERA services 50 0 0 The Regulatory Information Management System RIMS is expected to be rolled out in July 2021 83 All projects have reached financial close Due to the reduced portfolio size following inception the target will not be reached In the reporting period more than EUR 10 million have been injected into the projects under construction due to COVID 19 and flooding incidents This is not considered in the value as finance mobilised is reported at financial close 97 Mobilised finance at financial close All projects have reached financial close Due to the reduced portfolio size following inception the target will not be fully reached The public finance has increased in 2020 for the projects under construction as project cost has increased Output 5 Increased capacity at ERA Output 6 Finance mobilised for GET FiT portfolio Indicator 6 1 Private finance mobilised for GET FiT portfolio in USD million Indicator 6 2 Public finance mobilised for GET FiT portfolio in USD million 64 200 300 165 290 65

Page 68

GET FiT Uganda Annual Report 2020 Outcomes The outcomes address the influence of GET FiT at a higher sector level namely on the private sector investment environment for renewable energy in Uganda and improved financial stability of the energy sector A third indicator on local grid stability has been excluded from the Logframe in 2018 Currently four commercial banks are financing projects of the GET FiT portfolio and as further projects restructure debt in the future it is expected that more commercial banks will become involved in the Ugandan energy sector In 2020 the regulator has issued six development permits and two generation licences for renewable energy projects with capacities greater than 1 MW but less than 20 MW Furthermore 12 additional licenses were granted for project smaller than 1 MW As highlighted in the Output section the process of issuing generation licences has maintained high efficiency with less than one month taken to review applications While the power utility UETCL has paid all its invoices for delivered energy in 2020 some developers have reported delayed deemed energy payments These delays are not considered for the indicator since deemed energy claims are not approved for payment by UETCL but by ERA through the base consumer tariff which is reviewed to include deemed energy only once a year The electricity purchased from thermal power stations has reduced drastically from circa 100 GWh in 2019 to ca 57 GWh in 2020 which is well below the target of 832 GWh in 2023 Capacity payments remain part of a Government subsidy which signifies that the country has not yet achieved fully cost reflective retail tariffs An overview of the Outcome indicators is provided in Table 6 Table 6 Outcome Indicators Indicator Target 2023 Status 2020 Target Achieved Comment Outcome 1 Improved private sector investment environment for renewable energy in Uganda Indicator 1 1 Number of commercial banks that invest in renewable energy for project finance lending for GET FiT projects Indicator 1 2 Number of development permits and generation licences issued for small scale projects 1 20 MW by ERA per year Indicator 1 3 Occurrence of annual UETCL event of default for energy supplied deemed energy Indicator 1 5 REFiT adjusted to be cost reflective 5 12 4 8 80 No Uganda commercial bank is among lenders due to a lack of technical competence and energy sector experience according to developers 70 Two of the permits were permit renewals In addition to the reported permits and licences 12 additional licences were granted to projects below 1 MW 0 0 n a Five projects have reported delayed deemed energy payments These delays are not considered for the indicator since deemed energy claims are not approved for payment by UETCL but by ERA through the base consumer tariff which is reviewed only once a year 100 100 100 REFiTs were adjusted in 2019 REFiT IV and are now providing ceiling tariffs with a maximum return on equity for respective technologies Outcome 2 Improved financial stability of the energy sector Indicator 2 1 Subsidy paid by the Government for UETCL to cover thermal power use Indicator 2 2 GWh purchased by UETCL from thermal stations Indicator 2 3 Cost reflective retail tariffs 66 0 0 n a All energy purchased beyond stand by capacity was covered by tariffs 832 57 n a The sector is well below target due to i lower demand for thermal power than anticipated and ii thermal energy being offset by renewable energy from the GET FiT portfolio and commissioning of Isimba Last year s purchases were at 103 GWh 100 97 97 Capacity payments remain part of the subsidy paid by the Government 67

Page 69

GET FiT Uganda Annual Report 2020 Outcomes The outcomes address the influence of GET FiT at a higher sector level namely on the private sector investment environment for renewable energy in Uganda and improved financial stability of the energy sector A third indicator on local grid stability has been excluded from the Logframe in 2018 Currently four commercial banks are financing projects of the GET FiT portfolio and as further projects restructure debt in the future it is expected that more commercial banks will become involved in the Ugandan energy sector In 2020 the regulator has issued six development permits and two generation licences for renewable energy projects with capacities greater than 1 MW but less than 20 MW Furthermore 12 additional licenses were granted for project smaller than 1 MW As highlighted in the Output section the process of issuing generation licences has maintained high efficiency with less than one month taken to review applications While the power utility UETCL has paid all its invoices for delivered energy in 2020 some developers have reported delayed deemed energy payments These delays are not considered for the indicator since deemed energy claims are not approved for payment by UETCL but by ERA through the base consumer tariff which is reviewed to include deemed energy only once a year The electricity purchased from thermal power stations has reduced drastically from circa 100 GWh in 2019 to ca 57 GWh in 2020 which is well below the target of 832 GWh in 2023 Capacity payments remain part of a Government subsidy which signifies that the country has not yet achieved fully cost reflective retail tariffs An overview of the Outcome indicators is provided in Table 6 Table 6 Outcome Indicators Indicator Target 2023 Status 2020 Target Achieved Comment Outcome 1 Improved private sector investment environment for renewable energy in Uganda Indicator 1 1 Number of commercial banks that invest in renewable energy for project finance lending for GET FiT projects Indicator 1 2 Number of development permits and generation licences issued for small scale projects 1 20 MW by ERA per year Indicator 1 3 Occurrence of annual UETCL event of default for energy supplied deemed energy Indicator 1 5 REFiT adjusted to be cost reflective 5 12 4 8 80 No Uganda commercial bank is among lenders due to a lack of technical competence and energy sector experience according to developers 70 Two of the permits were permit renewals In addition to the reported permits and licences 12 additional licences were granted to projects below 1 MW 0 0 n a Five projects have reported delayed deemed energy payments These delays are not considered for the indicator since deemed energy claims are not approved for payment by UETCL but by ERA through the base consumer tariff which is reviewed only once a year 100 100 100 REFiTs were adjusted in 2019 REFiT IV and are now providing ceiling tariffs with a maximum return on equity for respective technologies Outcome 2 Improved financial stability of the energy sector Indicator 2 1 Subsidy paid by the Government for UETCL to cover thermal power use Indicator 2 2 GWh purchased by UETCL from thermal stations Indicator 2 3 Cost reflective retail tariffs 66 0 0 n a All energy purchased beyond stand by capacity was covered by tariffs 832 57 n a The sector is well below target due to i lower demand for thermal power than anticipated and ii thermal energy being offset by renewable energy from the GET FiT portfolio and commissioning of Isimba Last year s purchases were at 103 GWh 100 97 97 Capacity payments remain part of the subsidy paid by the Government 67

Page 70

GET FiT Uganda Annual Report 2020 Impact The Programme follows the impact statement Uganda pursues a low carbon climate resilient development path resulting in growth poverty reduction and climate change mitigation Accordingly the impact of the Programme is measured through three indicators highlighted below Due to the heavy reliance on the activities of key sector actors to reach the targets the effects of GET FiT Uganda are limited to a certain extent and subject to a time lag between GET FiT activities and observable results at a higher sector level Table 7 provides an overview of the Impact indicator developments in 2020 Grid related CO2 emissions have further reduced in 2020 with lower production from the thermal power plant and increased demand With an increased energy generation from the GET FiT portfolio as well as the commissioning of the Isimba hydropower plant in 2019 less energy was dispatched from fossil fuelled power plants in 2020 As such the grid related CO2 emissions are already lower than the target set for 2023 Further with an electrification rate of 28 the 2023 target of 26 4 is already exceeded Table 7 Impact Indicators Target 2023 Status 2020 Indicator 1 Grid related CO2 emissions per unit electricity use12 0 09 0 01 Grid related CO2 emissions decreased from 0 037 2018 and 0 016 2019 to 0 01 in 2020 which can be attributed to 40 less thermal generation in 2020 Indicator 2 Percent of population with access to electricity 26 4 28 Following the 2019 joint sector review no new official electrification rate statistics were reported 105 103 Following the 2019 joint sector review no new official electricity consumption statistics were reported Impact Indicators Indicator 3 Electricity consumption kWh per capita Comment 6 2 Risk Management R isk management is a continuous process running through the lifetime of a programme where risks are identified and categorised and measures introduced to reduce or eliminate the risks COVID 19 The pandemic resulted in implementation delays for the GET FiT projects still under construction due to travel restrictions for key staff shipping delays and other direct or indirect effects However the projects have maintained activity on site and generally progressed well throughout the year While progress at the different sites has been monitored remotely by the GET FiT construction supervision team the full resulting implications of COVID 19 with respect to actual COD delays are not yet clear and will be subject to further assessment 12 The increased health risks due to COVID 19 also affected personnel at the GET FiT project construction sites COVID 19 cases were recorded at all three construction sites The respective project developers have reported to GET FiT on their test efforts and results as well as preventive and reactive measures The pandemic and to some extent the general elections have also impacted the energy sector in Uganda as a whole The Government of Uganda has directed its financial resources towards health and the economic condition of the country and as such made no allocations towards the Electricity Connections Policy in 2020 Lower CO2 emissions per unit electricity use indicate a power system with high penetration of renewable energy The indicator target was already achieved in 2017 A lower value corresponds to less emissions per unit of electricity use The indicator is calculated by multiplying the national thermal generation by technology specific emission factors and dividing the resulting emissions by the total electricity consumption in Uganda in 2020 68 From a GET FiT risk management perspective the construction supervision team was prevented from carrying out physical supervision visits in 2020 due to travel restrictions In order to maintain a minimum acceptable level of follow up developer support and progress monitoring remote supervision was undertaken on a quarterly basis through digital meetings photos and documentation review This approach has clear limitations when it comes to assessing both technical and E S features of the projects and physical supervision visits will be undertaken when practical Flooding Major flood events occurred in Western Uganda during the second quarter of 2020 causing varying degrees of damage to two operational GET FiT small hydropower power plants Nyamwamba and Lubilia SHPs as well as causing damage and delays for the Nyamagasani 1 and 2 SHPs which are under construction in the same area The GET FiT supervision team has been monitoring the progress of repair works remotely and remained available to follow up progress and provide support to developers as required Both the Nyamwamba and Lubilia SHPs were operational by the end of the year to varying degrees with further remedial works being required at the Nyamwamba SHP in 2021 in order to return to full operating capacity The Lubilia SHP experienced a landslide in November 2020 not believed to be linked to the May 2020 floods which resulted in substantial additional downtime and repairs which will be ongoing into 2021 Grid connection Inadequate grid infrastructure and or operations within the local and regional distribution and transmission networks continue to present the main risk against achievement of Programme targets As a result in 2020 approximately 25 of the energy generation at GET FiT power plants failed to reach Ugandan electricity customers due to grid availability issues deemed energy The current level of deemed energy generated by GET FiT and other power plants across the country poses a major risk to the sustainability of the Ugandan power sector Importantly the remaining three GET FiT projects under construction are also facing challenges related to securing adequate connection to the grid Unless these issues are resolved prior to commissioning of the plants deemed energy levels from the GET FiT portfolio could still rise significantly On this basis the risk category for grid connection is maintained with a high probability and high impact Operational performance With most of the GET FiT projects now operational a different set of risks are introduced The technical performance operations and maintenance of each plant will affect the targeted level of annual energy production across the portfolio E S performance in the operational phase is also vital to ensure sustainable energy generation from GET FiT plants for the next two decades While GET FiT Uganda was originally established to support projects up to COD which is reflected in the Programme s legal framework and budgets the Programme is also trying to monitor general post COD performance to the extent possible This is maintained through review of annual energy production in relation to subsidy disbursements and one or two post COD visits to each project in order to capture key issues and experiences One issue that has become clear during operational phases to date is that some developers are not documenting compliance with minimum flow in a satisfactory manner While such operational risks are not formally part of the GET FiT risk framework it is highly important that they are monitored and managed by the Ugandan authorities Therefore as a first step KfW and the GET FiT supervision team have addressed the issues with the relevant developers and provided documentation as a basis for GoU to follow up on the issues going forward Health Safety and Environment HSE Despite the remaining projects under construction being pushed on maintaining timelines it is crucial that this does not compromise HSE performance in any way GET FiT is not positioned to supervise or control the quality of developer s HSE work daily and these risks are therefore not formally part of the GET FiT risk control framework Nonetheless GET FiT supervision visits focus on monitoring performance in that respect to the extent possible discussing HSE standards with developers and creating awareness around potential risks An overview of the most relevant remaining risks across the Programme is presented in Table 8 69

Page 71

GET FiT Uganda Annual Report 2020 Impact The Programme follows the impact statement Uganda pursues a low carbon climate resilient development path resulting in growth poverty reduction and climate change mitigation Accordingly the impact of the Programme is measured through three indicators highlighted below Due to the heavy reliance on the activities of key sector actors to reach the targets the effects of GET FiT Uganda are limited to a certain extent and subject to a time lag between GET FiT activities and observable results at a higher sector level Table 7 provides an overview of the Impact indicator developments in 2020 Grid related CO2 emissions have further reduced in 2020 with lower production from the thermal power plant and increased demand With an increased energy generation from the GET FiT portfolio as well as the commissioning of the Isimba hydropower plant in 2019 less energy was dispatched from fossil fuelled power plants in 2020 As such the grid related CO2 emissions are already lower than the target set for 2023 Further with an electrification rate of 28 the 2023 target of 26 4 is already exceeded Table 7 Impact Indicators Target 2023 Status 2020 Indicator 1 Grid related CO2 emissions per unit electricity use12 0 09 0 01 Grid related CO2 emissions decreased from 0 037 2018 and 0 016 2019 to 0 01 in 2020 which can be attributed to 40 less thermal generation in 2020 Indicator 2 Percent of population with access to electricity 26 4 28 Following the 2019 joint sector review no new official electrification rate statistics were reported 105 103 Following the 2019 joint sector review no new official electricity consumption statistics were reported Impact Indicators Indicator 3 Electricity consumption kWh per capita Comment 6 2 Risk Management R isk management is a continuous process running through the lifetime of a programme where risks are identified and categorised and measures introduced to reduce or eliminate the risks COVID 19 The pandemic resulted in implementation delays for the GET FiT projects still under construction due to travel restrictions for key staff shipping delays and other direct or indirect effects However the projects have maintained activity on site and generally progressed well throughout the year While progress at the different sites has been monitored remotely by the GET FiT construction supervision team the full resulting implications of COVID 19 with respect to actual COD delays are not yet clear and will be subject to further assessment 12 The increased health risks due to COVID 19 also affected personnel at the GET FiT project construction sites COVID 19 cases were recorded at all three construction sites The respective project developers have reported to GET FiT on their test efforts and results as well as preventive and reactive measures The pandemic and to some extent the general elections have also impacted the energy sector in Uganda as a whole The Government of Uganda has directed its financial resources towards health and the economic condition of the country and as such made no allocations towards the Electricity Connections Policy in 2020 Lower CO2 emissions per unit electricity use indicate a power system with high penetration of renewable energy The indicator target was already achieved in 2017 A lower value corresponds to less emissions per unit of electricity use The indicator is calculated by multiplying the national thermal generation by technology specific emission factors and dividing the resulting emissions by the total electricity consumption in Uganda in 2020 68 From a GET FiT risk management perspective the construction supervision team was prevented from carrying out physical supervision visits in 2020 due to travel restrictions In order to maintain a minimum acceptable level of follow up developer support and progress monitoring remote supervision was undertaken on a quarterly basis through digital meetings photos and documentation review This approach has clear limitations when it comes to assessing both technical and E S features of the projects and physical supervision visits will be undertaken when practical Flooding Major flood events occurred in Western Uganda during the second quarter of 2020 causing varying degrees of damage to two operational GET FiT small hydropower power plants Nyamwamba and Lubilia SHPs as well as causing damage and delays for the Nyamagasani 1 and 2 SHPs which are under construction in the same area The GET FiT supervision team has been monitoring the progress of repair works remotely and remained available to follow up progress and provide support to developers as required Both the Nyamwamba and Lubilia SHPs were operational by the end of the year to varying degrees with further remedial works being required at the Nyamwamba SHP in 2021 in order to return to full operating capacity The Lubilia SHP experienced a landslide in November 2020 not believed to be linked to the May 2020 floods which resulted in substantial additional downtime and repairs which will be ongoing into 2021 Grid connection Inadequate grid infrastructure and or operations within the local and regional distribution and transmission networks continue to present the main risk against achievement of Programme targets As a result in 2020 approximately 25 of the energy generation at GET FiT power plants failed to reach Ugandan electricity customers due to grid availability issues deemed energy The current level of deemed energy generated by GET FiT and other power plants across the country poses a major risk to the sustainability of the Ugandan power sector Importantly the remaining three GET FiT projects under construction are also facing challenges related to securing adequate connection to the grid Unless these issues are resolved prior to commissioning of the plants deemed energy levels from the GET FiT portfolio could still rise significantly On this basis the risk category for grid connection is maintained with a high probability and high impact Operational performance With most of the GET FiT projects now operational a different set of risks are introduced The technical performance operations and maintenance of each plant will affect the targeted level of annual energy production across the portfolio E S performance in the operational phase is also vital to ensure sustainable energy generation from GET FiT plants for the next two decades While GET FiT Uganda was originally established to support projects up to COD which is reflected in the Programme s legal framework and budgets the Programme is also trying to monitor general post COD performance to the extent possible This is maintained through review of annual energy production in relation to subsidy disbursements and one or two post COD visits to each project in order to capture key issues and experiences One issue that has become clear during operational phases to date is that some developers are not documenting compliance with minimum flow in a satisfactory manner While such operational risks are not formally part of the GET FiT risk framework it is highly important that they are monitored and managed by the Ugandan authorities Therefore as a first step KfW and the GET FiT supervision team have addressed the issues with the relevant developers and provided documentation as a basis for GoU to follow up on the issues going forward Health Safety and Environment HSE Despite the remaining projects under construction being pushed on maintaining timelines it is crucial that this does not compromise HSE performance in any way GET FiT is not positioned to supervise or control the quality of developer s HSE work daily and these risks are therefore not formally part of the GET FiT risk control framework Nonetheless GET FiT supervision visits focus on monitoring performance in that respect to the extent possible discussing HSE standards with developers and creating awareness around potential risks An overview of the most relevant remaining risks across the Programme is presented in Table 8 69

Page 72

GET FiT Uganda Annual Report 2020 Table 8 Risk Matrix Description of Risk Mitigation Actions Progress Additional construction delays and increased health risks on site due to COVID 19 restrictions for Nyamagasani 1 Nyamagasani 2 and Kikagati Monitoring of progress on site through remote supervision Reporting by developers on COVID 19 testing as well as preventive and reactive measures Projects have maintained a substantial level of activity on site progress is being monitored and the full resulting delays attributed to COVID 19 restrictions are yet to be determined Deemed commissioning of GET FiT projects due to poor planning at key institutions as well as lack of funds to ensure timely infrastructure for grid connection Additional funding provided by GET FiT donors to support selected critical grid infrastructure investments required for connection of GET FiT projects Unsatisfactory progress on GET FiT funded grid infrastructure projects due to various implementation challenges including major E S issues related to compensation High risk of continued increase in deemed energy generation from the GET FiT portfolio Operational GET FiT plants generating power at reduced capacity due to continuing unresolved constraints of the high and medium voltage national grid Comprehensive efforts by GET FiT to fasttrack implementation of grid infrastructure projects managed by GoU agencies which are relevant to the GET FiT portfolio Availability of wayleave compensation funds and timely compensation GET FiT evacuation lines in Western Uganda GET FiT SC has stressed that timely provision of compensation funds is a critical pre requisite to completing the ongoing GET FiT grid connection projects and safeguard the Programme targets GoU has committed to providing the necessary compensation funds on time to avoid losing Programme funds but due to slow progress and a stressed national budget a high risk Corruption misuse of funds and bribes paid by developers or contractors Subsidies are performance based and disbursed for energy delivered General risk remains until the commissioning of all projects Compliance with Environmental and Social standards of developers Workshops on E S standards were provided to developers Penalties for non compliance are incorporated in subsidy agreement DFA Additional supervision visits are carried out for underperforming projects Zero tolerance in developer s contracts and termination of contracts as well as repayment of fees in case of paid bribes A water and energy sector working group will be established to address the issue of minimum environmental flow compliance for hydropower projects medium high high medium Some projects still perform unsatisfactorily GET FiT has carried out multiple additional supervision visits and imposed penalties on some developers Compliance is continuously followed up including post commissioning The risk of non compliance and associated reputational risks remain medium A scope has been developed for the minimum flow working group The work will be financed and coordinated by GET FiT in close cooperation with the relevant GoU authorities Lower generation than estimated due to insufficient hydrological data and or climate change Risks were included and diligently assessed in hydrological estimates and sensitivity testing at project evaluation stage Generation data for all projects is continuously followed up by GET FiT The realisation of hydrological risks can only truly be assessed in the fullness of time following a sustained period of generation multiple years Insufficient Programme funds due to foreign exchange rate developments Continuous budget monitoring allows for pro active financial management and early identification of risks and Steering Committee action if needed Low risk level on original Programme budget premium payments due to most funds already disbursed there Medium risk level remaining on grid connection component where a funding shortfall is likely Insufficient understanding of ground conditions results in substantial changes in the design and layout of projects and or adverse environmental and social impacts as a result of landslides or similar during construction Developers required to provide updates on geotechnical conditions in the location of key project structures and in high risk areas during the implementation phase based on further investigations and assessments by geotechnical engineering specialists Developers requested to address key geotechnical risks through changes in project designs and construction methodologies Several projects implemented changes in designs and construction methodologies in 2018 19 to improve the robustness of project designs and to reduce the likelihood of landslides Further changes may be necessary for remaining projects during 2020 to manage residual risks 70 Risk Assessment medium medium medium 71

Page 73

GET FiT Uganda Annual Report 2020 Table 8 Risk Matrix Description of Risk Mitigation Actions Progress Additional construction delays and increased health risks on site due to COVID 19 restrictions for Nyamagasani 1 Nyamagasani 2 and Kikagati Monitoring of progress on site through remote supervision Reporting by developers on COVID 19 testing as well as preventive and reactive measures Projects have maintained a substantial level of activity on site progress is being monitored and the full resulting delays attributed to COVID 19 restrictions are yet to be determined Deemed commissioning of GET FiT projects due to poor planning at key institutions as well as lack of funds to ensure timely infrastructure for grid connection Additional funding provided by GET FiT donors to support selected critical grid infrastructure investments required for connection of GET FiT projects Unsatisfactory progress on GET FiT funded grid infrastructure projects due to various implementation challenges including major E S issues related to compensation High risk of continued increase in deemed energy generation from the GET FiT portfolio Operational GET FiT plants generating power at reduced capacity due to continuing unresolved constraints of the high and medium voltage national grid Comprehensive efforts by GET FiT to fasttrack implementation of grid infrastructure projects managed by GoU agencies which are relevant to the GET FiT portfolio Availability of wayleave compensation funds and timely compensation GET FiT evacuation lines in Western Uganda GET FiT SC has stressed that timely provision of compensation funds is a critical pre requisite to completing the ongoing GET FiT grid connection projects and safeguard the Programme targets GoU has committed to providing the necessary compensation funds on time to avoid losing Programme funds but due to slow progress and a stressed national budget a high risk Corruption misuse of funds and bribes paid by developers or contractors Subsidies are performance based and disbursed for energy delivered General risk remains until the commissioning of all projects Compliance with Environmental and Social standards of developers Workshops on E S standards were provided to developers Penalties for non compliance are incorporated in subsidy agreement DFA Additional supervision visits are carried out for underperforming projects Zero tolerance in developer s contracts and termination of contracts as well as repayment of fees in case of paid bribes A water and energy sector working group will be established to address the issue of minimum environmental flow compliance for hydropower projects medium high high medium Some projects still perform unsatisfactorily GET FiT has carried out multiple additional supervision visits and imposed penalties on some developers Compliance is continuously followed up including post commissioning The risk of non compliance and associated reputational risks remain medium A scope has been developed for the minimum flow working group The work will be financed and coordinated by GET FiT in close cooperation with the relevant GoU authorities Lower generation than estimated due to insufficient hydrological data and or climate change Risks were included and diligently assessed in hydrological estimates and sensitivity testing at project evaluation stage Generation data for all projects is continuously followed up by GET FiT The realisation of hydrological risks can only truly be assessed in the fullness of time following a sustained period of generation multiple years Insufficient Programme funds due to foreign exchange rate developments Continuous budget monitoring allows for pro active financial management and early identification of risks and Steering Committee action if needed Low risk level on original Programme budget premium payments due to most funds already disbursed there Medium risk level remaining on grid connection component where a funding shortfall is likely Insufficient understanding of ground conditions results in substantial changes in the design and layout of projects and or adverse environmental and social impacts as a result of landslides or similar during construction Developers required to provide updates on geotechnical conditions in the location of key project structures and in high risk areas during the implementation phase based on further investigations and assessments by geotechnical engineering specialists Developers requested to address key geotechnical risks through changes in project designs and construction methodologies Several projects implemented changes in designs and construction methodologies in 2018 19 to improve the robustness of project designs and to reduce the likelihood of landslides Further changes may be necessary for remaining projects during 2020 to manage residual risks 70 Risk Assessment medium medium medium 71

Page 74

GET FiT Uganda Annual Report 2020 07 Other GET FiT Initiatives 7 1 GET FiT Zambia T he second roll out of the GET FiT concept GET FiT Zambia was launched in 2018 in Lusaka and is now in its third year of implementation Similarly to Uganda the objective of the Programme is to improve the framework conditions for private investments in small scale renewable energy in the country The principal component of GET FiT Zambia is the procurement of up to 200 MW in renewable energy projects of up to 20 MW from IPPs The Programme is a partnership between the Zambian Ministry of Energy and KfW and is implemented by the GET FiT Secretariat managed by Multiconsult Other key stakeholders are the Energy Regulation Board ERB and the state owned power utility Z ESCO Ltd In addition to the procurement of up to 200 MW of renewable energy capacity at the core of the Programme GET FiT Zambia comprises a set of tools that addresses barriers and gaps in the Zambian energy sector see illustration below GET FiT TOOLBOX Procurement Transactions Competitive procurement of 100 MW of Solar Capacity Competitive procurement of up to 100 MW of Hydro Lack of credibility amongst investors that procurement efforts will result in execution Debt Risk Mitigation Facility Mitigating short medium term liquidity risk Regional Liquidity Support Facility RLSF Individual small projects unable to attract appropriate financing and associated DD Figure 26 GET FiT Zambia Toolbox 72 Viability Gap Funding Grid Facility Technical Assistance Production based top up for Hydro Projects Competitive bidding top up based on Usc kWh for the entire PPA Shallow and deep integration support funding and TA Grid related technical assistance Skill Gap identification at key sector stakeholders related to IPPs 5 Procurement of tailored capacity building and TA programmes High cost of capital for renewable transition and new REFiTs yet untested Capacity constraints for integration and operation of decentralized intermittent RE and rural electrification opportunities being overlooked Skills gaps and capacity constraints in becoming credible counterpart to investors BARRIERS GAPS 73

Page 75

GET FiT Uganda Annual Report 2020 07 Other GET FiT Initiatives 7 1 GET FiT Zambia T he second roll out of the GET FiT concept GET FiT Zambia was launched in 2018 in Lusaka and is now in its third year of implementation Similarly to Uganda the objective of the Programme is to improve the framework conditions for private investments in small scale renewable energy in the country The principal component of GET FiT Zambia is the procurement of up to 200 MW in renewable energy projects of up to 20 MW from IPPs The Programme is a partnership between the Zambian Ministry of Energy and KfW and is implemented by the GET FiT Secretariat managed by Multiconsult Other key stakeholders are the Energy Regulation Board ERB and the state owned power utility Z ESCO Ltd In addition to the procurement of up to 200 MW of renewable energy capacity at the core of the Programme GET FiT Zambia comprises a set of tools that addresses barriers and gaps in the Zambian energy sector see illustration below GET FiT TOOLBOX Procurement Transactions Competitive procurement of 100 MW of Solar Capacity Competitive procurement of up to 100 MW of Hydro Lack of credibility amongst investors that procurement efforts will result in execution Debt Risk Mitigation Facility Mitigating short medium term liquidity risk Regional Liquidity Support Facility RLSF Individual small projects unable to attract appropriate financing and associated DD Figure 26 GET FiT Zambia Toolbox 72 Viability Gap Funding Grid Facility Technical Assistance Production based top up for Hydro Projects Competitive bidding top up based on Usc kWh for the entire PPA Shallow and deep integration support funding and TA Grid related technical assistance Skill Gap identification at key sector stakeholders related to IPPs 5 Procurement of tailored capacity building and TA programmes High cost of capital for renewable transition and new REFiTs yet untested Capacity constraints for integration and operation of decentralized intermittent RE and rural electrification opportunities being overlooked Skills gaps and capacity constraints in becoming credible counterpart to investors BARRIERS GAPS 73

Page 76

GET FiT Uganda Annual Report 2020 7 2 GET FiT Mozambique M ozambique is generously endowed with renewable energy resources with about 18 GW in hydropower potential and favourable conditions for electricity production from solar wind and biomass However the country is still suffering from low electricity access rates of 34 The utility EDM operates about 0 5 GW of generation capacity falling short of meeting current demand Several market barriers hamper the development of the energy sector particularly relating to private sector investments The third roll out of the GET FiT concept in Mozambique aims at improving these framework conditions for private investments in renewable energy to support a climate friendly development lower greenhouse gas emissions and reduce poverty The Programme is implemented over a ten year period and is expected to launch in 2021 At the core of the Programme are three procurement rounds of both generation capacity partly with energy storage The first round will include a reverse auction of up to 32 MW of solar PV with storage Furthermore the Programme consists of several instruments to support the development of the energy sector in Mozambique A demanding year for the Programme The procurement through a reverse auction of 120 MWac in the form of six solar PV projects in early 2019 was considered as successful It achieved record breaking bids for Sub Saharan Africa down to 3 999 USc kWh and a weighted average of the successful projects at 4 41 USc kWh However the year 2020 presented some challenges for the Programme The macroeconomic situation in Zambia has been challenging and energy sector reforms are progressing slowly This had noticeable consequences for the Programme particularly affecting the ability to secure financing for the six projects At an average of 4 41 USc kWh these projects are below the average electricity selling price in Zambia and present an excellent value proposition for a country needing to diversity its energy mix Changing weather patterns have caused drought in parts of the hydropower dominated country which led to high levels of load shedding 74 Viability Gap Funding Supplementation of the feed in tariffs to a cost covering level Grid Integration Facility Financing of grid connection costs for subsidised power generation plants from private developers Independent Power Producers IPPs Risk Mitigation Facility Risk Coverage Guarantee Facility for IPPs Technical Assistance Facility Capacity building at the partner institutions through technical support and supervision of the IPPs The Government of Mozambique and KfW signed the Financial Agreement for the Programme in 2019 The German Government has provided a EUR 25 million grant for its implementation The Minist rio dos Recursos Minerais e Energia MIREME is the Programme Executing Agency For further information about the Programme please visit the website www getfit moz org In the face of these challenges financiers have temporarily suspended their financing activities for ongrid projects and as a result the development of the Solar PV projects and the RfP for the small hydropower has been temporarily halted until the situation in the energy sector stabilises The GET FiT Zambia Secretariat continues to have a close dialogue with both the solar PV project developers and prospective lenders to ensure a smooth continuation of the project development once the situation allows for it While the development of the projects is halted GET FiT is continuing the work by concentrating efforts on the Technical Assistance Facility providing support to key institutions during the energy reform process Further information updates Stay informed about development in the GET FiT Zambia Programme please visit the website www getfit zambia org sign up for the GET FiT Zambia newsletter or follow the Programme on LinkedIn and Twitter 75

Page 77

GET FiT Uganda Annual Report 2020 7 2 GET FiT Mozambique M ozambique is generously endowed with renewable energy resources with about 18 GW in hydropower potential and favourable conditions for electricity production from solar wind and biomass However the country is still suffering from low electricity access rates of 34 The utility EDM operates about 0 5 GW of generation capacity falling short of meeting current demand Several market barriers hamper the development of the energy sector particularly relating to private sector investments The third roll out of the GET FiT concept in Mozambique aims at improving these framework conditions for private investments in renewable energy to support a climate friendly development lower greenhouse gas emissions and reduce poverty The Programme is implemented over a ten year period and is expected to launch in 2021 At the core of the Programme are three procurement rounds of both generation capacity partly with energy storage The first round will include a reverse auction of up to 32 MW of solar PV with storage Furthermore the Programme consists of several instruments to support the development of the energy sector in Mozambique A demanding year for the Programme The procurement through a reverse auction of 120 MWac in the form of six solar PV projects in early 2019 was considered as successful It achieved record breaking bids for Sub Saharan Africa down to 3 999 USc kWh and a weighted average of the successful projects at 4 41 USc kWh However the year 2020 presented some challenges for the Programme The macroeconomic situation in Zambia has been challenging and energy sector reforms are progressing slowly This had noticeable consequences for the Programme particularly affecting the ability to secure financing for the six projects At an average of 4 41 USc kWh these projects are below the average electricity selling price in Zambia and present an excellent value proposition for a country needing to diversity its energy mix Changing weather patterns have caused drought in parts of the hydropower dominated country which led to high levels of load shedding 74 Viability Gap Funding Supplementation of the feed in tariffs to a cost covering level Grid Integration Facility Financing of grid connection costs for subsidised power generation plants from private developers Independent Power Producers IPPs Risk Mitigation Facility Risk Coverage Guarantee Facility for IPPs Technical Assistance Facility Capacity building at the partner institutions through technical support and supervision of the IPPs The Government of Mozambique and KfW signed the Financial Agreement for the Programme in 2019 The German Government has provided a EUR 25 million grant for its implementation The Minist rio dos Recursos Minerais e Energia MIREME is the Programme Executing Agency For further information about the Programme please visit the website www getfit moz org In the face of these challenges financiers have temporarily suspended their financing activities for ongrid projects and as a result the development of the Solar PV projects and the RfP for the small hydropower has been temporarily halted until the situation in the energy sector stabilises The GET FiT Zambia Secretariat continues to have a close dialogue with both the solar PV project developers and prospective lenders to ensure a smooth continuation of the project development once the situation allows for it While the development of the projects is halted GET FiT is continuing the work by concentrating efforts on the Technical Assistance Facility providing support to key institutions during the energy reform process Further information updates Stay informed about development in the GET FiT Zambia Programme please visit the website www getfit zambia org sign up for the GET FiT Zambia newsletter or follow the Programme on LinkedIn and Twitter 75

Page 78

GET FiT Uganda Annual Report 2020 08 Outlook for 2021 A s outlined in this report 2020 was a challenging year for the Programme due to unforeseen external events Despite this a good level of progress was achieved on the ground as a result of persistent efforts by project developers and stakeholders The GET FiT Steering Committee and Implementation Consultant have maintained a flexible and pragmatic approach to managing the portfolio ensuring continued support to projects affected by COVID 19 restrictions and flooding Going into 2021 the situation in Uganda with respect to the pandemic remains difficult to predict It is anticipated that remote and digital construction supervision may still be needed for at least parts of the year but physical site visits will hopefully be resumed KfW and the Implementation Consultant are continuously monitoring the overall situation and assessing needs on the ground Physical site visits will also be beneficial with respect to the Working Group on environmental minimum flow compliance for hydropower projects which will be established by GET FiT in cooperation with ERA and other key government agencies The work of this group will address minimum flow guidance and compliance issues across the Ugandan hydropower sector based on challenges and lessons identified during GET FiT implementation This is vital in order to ensure sound management of Ugandan rivers and the findings of this group will form an integral part of the GET FiT legacy 76 Grid connection for GET FiT projects continues to represent a major challenge for the Programme Provision of wayleave compensation funds for the construction of new power lines is critical both in order to safeguard GET FiT energy generation targets and to reduce the financial and reputational burden on GoU of deemed energy payments At least one additional project is reportedly on the verge of achieving commercial operations as we enter 2021 Depending on efforts on the ground commissioning of all three remaining projects under construction is considered possible within the upcoming year Based on current status all projects are expected to be commissioned within 2022 at the latest finally bringing the operational portfolio up to full target capacity after nearly ten years of implementation Although 2020 did not turn out the way anyone expected GET FiT Uganda is on track to achieving the overarching Programme targets GET FiT has built a large and diverse renewable energy portfolio at record speed in the given context This is only as a result of the dedicated efforts and loyal commitment to Programme goals by Project Developers Ugandan Government Agencies GET FiT donors and all other valuable members of the GET FiT Uganda community 77

Page 79

GET FiT Uganda Annual Report 2020 08 Outlook for 2021 A s outlined in this report 2020 was a challenging year for the Programme due to unforeseen external events Despite this a good level of progress was achieved on the ground as a result of persistent efforts by project developers and stakeholders The GET FiT Steering Committee and Implementation Consultant have maintained a flexible and pragmatic approach to managing the portfolio ensuring continued support to projects affected by COVID 19 restrictions and flooding Going into 2021 the situation in Uganda with respect to the pandemic remains difficult to predict It is anticipated that remote and digital construction supervision may still be needed for at least parts of the year but physical site visits will hopefully be resumed KfW and the Implementation Consultant are continuously monitoring the overall situation and assessing needs on the ground Physical site visits will also be beneficial with respect to the Working Group on environmental minimum flow compliance for hydropower projects which will be established by GET FiT in cooperation with ERA and other key government agencies The work of this group will address minimum flow guidance and compliance issues across the Ugandan hydropower sector based on challenges and lessons identified during GET FiT implementation This is vital in order to ensure sound management of Ugandan rivers and the findings of this group will form an integral part of the GET FiT legacy 76 Grid connection for GET FiT projects continues to represent a major challenge for the Programme Provision of wayleave compensation funds for the construction of new power lines is critical both in order to safeguard GET FiT energy generation targets and to reduce the financial and reputational burden on GoU of deemed energy payments At least one additional project is reportedly on the verge of achieving commercial operations as we enter 2021 Depending on efforts on the ground commissioning of all three remaining projects under construction is considered possible within the upcoming year Based on current status all projects are expected to be commissioned within 2022 at the latest finally bringing the operational portfolio up to full target capacity after nearly ten years of implementation Although 2020 did not turn out the way anyone expected GET FiT Uganda is on track to achieving the overarching Programme targets GET FiT has built a large and diverse renewable energy portfolio at record speed in the given context This is only as a result of the dedicated efforts and loyal commitment to Programme goals by Project Developers Ugandan Government Agencies GET FiT donors and all other valuable members of the GET FiT Uganda community 77

Page 80

KfW Development Bank Georg Gr ner Principal Project Manager georg gruener kfw de www kfw de Multiconsult Norge AS Picture credits Cover Page 6 58 66 PA Technical Services Limited Page 72 Douwdejager Getty Images Page 74 Alex Frood Getty Images Jan Ohlenbusch Project Manager jan ohlenbusch multiconsult no www multiconsult no

Page 81

KfW Development Bank Georg Gr ner Principal Project Manager georg gruener kfw de www kfw de Multiconsult Norge AS Picture credits Cover Page 6 58 66 PA Technical Services Limited Page 72 Douwdejager Getty Images Page 74 Alex Frood Getty Images Jan Ohlenbusch Project Manager jan ohlenbusch multiconsult no www multiconsult no