Return to flip book view

CT451 Installation Manual

Page 1

This product was tested to comply with the requirements of AAMA 501 (Methods of Test for Exterior Walls) and received product approval from Florida Building Code. DETAILS PRESENTED IN THIS INSTRUCTION ARE ALL CT451 SYSTEM. CT452 & CG451 SHOULD BE SIMILAR IN EXECUTION UNLESS OTHERWISE NOTED.

Page 2

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 2 BEFORE YOU START... The correct installaon of a storefront system is crical to its performance and should only be carried out by a knowledgeable and experienced installaon crew. There are no safe shortcuts. Failure to install the proper quanty and type of perimeter fasteners and sealants as prescribed by approved construcon drawings, engineer’s requirements and all local building codes could lead to catastrophic failure of the in-stallaon with damaging results. These instrucons are to be used as a supplement to the shop drawings and are designed to show general fabricaon sequence and procedure for a typical installaon. If you don't know, or aren't sure; ask a qualied Trulite representave. COMMON STOREFRONT SYSTEM FIELD FAILURE PROBLEMS 1. Failure to follow product installaon instrucons 2. Poor workmanship 3. Frames not installed level and plumb 4. Frames not properly aached to resist dynamic forces of shear, tension and compression 5. Mullion and ller not properly engaged 6. Debris le in glazing pockets 7. Misapplicaon. For example, ulizing a storefront system for a curtain wall applicaon 8. Glass not centered in opening and not using proper seng blocks.

Page 3

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 3 TABLE OF CONTENTS INSTALLATION INSTRUCTION NOTES PART 1 Handling, Storage and Protecon of Aluminum ................................................................................................. 4 PART 2 Frame Fabricaon ............................................................................................................................................... 4 PART 3 General Installaon Instrucons ........................................................................................................................ 4-5 FRAME FABRICATION Typical Elevaon and Details ........................................................................................................................................... 6 Determine Frame Size ..................................................................................................................................................... 7-8 Fabricate Vercals and Snap-In Fillers............................................................................................................................. 9-10 Fabricate Horizontals and Glass stops ............................................................................................................................ 11-12 Fabricate Starter Sills ……………………………….................................................................................................................. ...13 FRAME ASSEMBLY Assemble for Exterior Glazing ......................................................................................................................................... 14 Assemble for Interior Glazing ………………………………………………………………………………………….……………………….....…………....15 FRAME INSTALLATION Install Starter Sill ….......................................................................................................................................................... 16-17 Install Starter Sill at Door Jamb ...................................................................................................................................... 18 Install Starter Sill Splice Sleeve ....................................................................................................................................... 19 Install Starter Sill at Corner Condions .......................................................................................................................... 20 Install/ Fabricate Bulkhead at Starter Sill…………………...…………………………………………………………………………..………..………..20 Install Head Receptor……………………………………………...………………………………………………………………………………………..………..21 Install Expansion Mullions……………………………………………………………………………………………………………………………....………….22 Install Corners at Starter Sill…..…………………………………………………………………………………………………..……...…….…....………….23 Install Oponal Adjustable Column Covers.…………………………………………………………………………………….………………….……...24 Install Frames in Opening ............................................................................................................................................... 25 Frames Installaon Sequence ……………........................................................................................................................... 26 Main anchor Installaon ……………................................................................................................................................... 27 Apply Perimeter Sealant.................................................................................................................................................. 28 GLAZING Glazing Preparaon & Instrucons ................................................................................................................................ 29 Installing Glass ................................................................................................................................................................ 30 Installing Water Diverters & Glass Stops......................................................................................................................... 31 Installing “W” An-Walk Blocks ...................................................................................................................................... 32 Glazing Gaskets Installaon ........................................................................................................................................... 33-34 ACCESSORIES Parts and Accessories...................................................................................................................................................... 35-38

Page 4

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 4 PART 1 - HANDLING, STORING AND PROTECTION OF ALUMINUM PRECAUTIONS: The following precauons are recommended to protect architectural aluminum materials against damage. Following these precauons will help ensure early acceptance of your products and workmanship. A. HANDLE CAREFULLY: All aluminum materials stored at job site must be stored with adequate separaon and not stacked directly onto the concrete oor slab to prevent materials from being damaged when handling. Cardboard wrapped or paper interleaved materials must be kept dry. B. CHECK ARRIVING MATERIALS: Check for quanty and keep records of where various materials are stored. C. KEEP MATERIAL AWAY FROM WATER, MUD AND SPRAY: Prevent cement, plaster or other materials from damaging the nish. D. PROTECT MATERIALS AFTER ERECTION: Wrap aluminum secon proles with polyethylene or protect by erecng a polyethylene splaer screen. Cement, plaster, terrazzo, other alkaline soluons and acid based materials used to clean concrete are very harmful to the nish and should be removed with water and mild soap IMMEDIATELY. Reference AAMA 609 and 610-2 for cleaning architectural aluminum. PART 2 - FRAME FABRICATION A. CHECK SHOP DRAWINGS & INSTALLATION INSTRUCTIONS to become thoroughly familiar with the project. The SHOP DRAWINGS take precedence and include specic details for the project. The INSTALLATION INSTRUCTIONS are of general nature and cover most common condions. B. CUTTING TOLERANCES: Fabricaon cung tolerances are +0”/-1/32” unless otherwise noted. C. PREPPING OF PARTS: Drill and tap holes to correct sizes and notch as required for frame assembly. D. GLAZING: Clean surfaces and use only approved gaskets. E. BUILDING CODES: Glass and glazing codes governing the design and use of products vary widely throughout the USA. Trulite does not control the selecon of product conguraons, or glazing materials, and assumes no responsibility for these design consideraons. It is the responsibility of the owner, specier, architect, general contractor and installer to make these selecons in strict conformance with all applicable codes. PART 3 - GENERAL INSTALLATION INSTRUCTIONS A. BENCH MARKS: All work should start from bench marks and/or column lines established by the ARCHITECTURAL DRAWINGS and the GENERAL CONTRACTOR with guaranteed accuracy. B. SURROUNDING CONDITIONS: Make certain that construcon receiving your materials is in accordance with the con-tract documents. Nofy the general contractor in wring of any discrepancies and resolve dierences before proceeding with work. C. ERECTION: All materials are to be installed plumb, level and true. D. ISOLATION OF ALUMINUM: Aluminum to be placed in direct contact with uncured concrete or incompable materi-als should be isolated with a heavy coat of zinc chromate or bituminous paint. E. FASTENING: Within the body of these instrucons, “fastening” means any method of securing one part to another or to adjacent materials. Only those fasteners used within the system are specied in these instrucons. Due to various sub-strates condions to which the framing may be aached, specic structural perimeter anchor fasteners are not specied in these instrucons. For structural perimeter fasteners, reference the shop drawings or consult with the engineer of rec-ord. F. EXPANSION JOINTS: Expansion joints and perimeter seals shown in these instrucons or in the shop drawings are shown at normal size. Actual dimensions may vary due to perimeter condions and dierences in metal temperature be-tween me of fabricaon and the me of installaon.

Page 5

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 5 G. COORDINATION WITH OTHER TRADES: Coordinate with the GENERAL CONTRACTOR and sequence with other trades any materials which oset the framing installaon. For example, backup walls, parons, ceilings, mechanical ducts, con-vectors, etc. H. FINAL CLEANING (CARE AND MAINTENANCE): Final cleaning of exposed aluminum surfaces should be done in ac-cordance with AAMA publicaons 609 and 610-2 . I. PRODUCT DESIGN CHANGES: Trulite reserves the right to change product designs without prior noce when deemed necessary for product improvement. Please check our website at www.trulite.com for the latest product installaon in-strucons prior to commencing work. TRULITE ABBREVIATIONS USED IN THESE INSTRUCTIONS: D.L.O. or DLO = Day Light Opening Ø = Diameter Typ. = Typical 1TH = Single Thermal Frame Conguraon (CT451 System) 2TH = Double Thermal Frame Conguraon (CT452 System) NT = Non-Thermal Frame Conguraon (CG451)

Page 6

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 6 TYPICAL ELEVATION AND DETAILS DETAILS PRESENTED IN THIS INSTRUCTION ARE ALL CT451(1TH). CT452(2TH) & CG451 (NT) SHOULD BE SIMILAR IN EXECUTION. SILL HORIZONTAL HEAD HEAD OPTIONS JAMB VERTICAL VERTICAL VERTICAL JAMB FRAME WIDTH

Page 7

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 7 FRAME WIDTH: Measure width of rough opening at the top, middle and boom as shown in FIG. 1.0 and account for the shortest dimension.  Starter sill length = Smallest dimension minus (-) shim gap at each end NOTE: Recommended shim thickness at head, sill & anchored jamb is between 1/4" to 3/8". Refer to approved shop drawing STEP 1.1 FRAME HEIGHT USING CT451-39 STARTER SILL: Example:  Smallest wall opening height (SOH) = 96”  Shim thickness = 1/4” at top & boom = 1/2”  Starter Sill Height = 5/8”  Frame Height Deduct (FHD) = 1/2” + 5/8” = 1 1/8”  Frame Height = SOH - FHD = 96” - 1 1/8” = 94 7/8” Example:  Smallest wall opening width (SOW) = 120”  Shim thickness = 1/4” at le and right jambs  Gap between starter sill & main sill = 1/8” at each end  Starter Sill Deduct (SSD) = 1/4” + 1/4” = 1/2”  Frame Width Deduct (FWD) = (1/4”+1/8”) x 2 = 3/8”x2 = 3/4”  Starter sill length = (SOW - SSD) = 120”- 1/2” = 119 1/2”  Frame width = (SOW- FWD) = 120”-3/4” = 119 1/4”  FRAME HEIGHT: Measure height of rough opening at several places as shown in FIG. 1.1 and account for the shortest di-mension. STEP 1. DETERMINE FRAME WIDTH AND HEIGHT BY MEASURING ROUGH OPENING: FIG. 1.0 FIG. 1.1 NOTE: Perimeter gap/shim thickness varies on a project to project basis. Quarter inch (1/4”) gap is used all throughout this document for consistency.

Page 8

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 8 Connuaon: DETERMINE FRAME HEIGHT USING CG451-12 STARTER SIL FIG. 1.2 NOTE: There’s a 1/2” dierence between using tall sill CT451-39 vs at sill CG451-12. Flat Sill CG451-12 is not intended to be used on CT451 / CT452 Thermal System. SILL STEP 1.2 FRAME HEIGHT USING CG451-12 STARTER SILL Example:  Smallest wall opening height (SOH) = 96”  Shim thickness = 1/4” at top & boom = 1/2”  Starter Sill Height = 1/8”  Frame Height Deduct (FHD) = 1/2” + 1/8” = 5/8”  Frame height = SOH - FHD = 96” - 5/8” = 95 3/8”

Page 9

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 9 STEP 2. FABRICATE VERTICALS AND SNAP-IN FILLERS Cut vercal members to frame height. Drill or punch 0.257 holes (leer “F” drill) in vercal members for spline screw FAS14-2 (¼" x 1” HWH) using drill xture DJ451-36 (FIG. 2.0) or Trulite punch die (CG451-36) and Time Fabsaver™ punch press. Reference FIGS. 2.1& 2.2 for using DJ451-36 symmetrical drill xture. Align DJ451-36 at top, boom and horizontal locaons on vercal members and drill holes as shown. FIG. 2.1 Exterior Glazing CT451-11 CT451-36 CT451-4 CT451-4 CT451-36 CT451-1 FIG. 2.2 Interior Glazing DJ451-36 DJ451-36 DJ451-36 DJ451-36 DJ451-36 DJ451-36 DJ451-36 DRILL FIXTURE USE LETTER ‘F’ (0.257” Ø) DRILL BIT Drill Fixture is non-handed Only two (2) screw holes are required per horizontal Filler Vercal Mullion FIG. 2.0 Note: There should be at least one deep pocket on each frame module.

Page 10

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 10  STEP 2.1: IF JAMB ANCHOR IS REQUIRED (VERIFY SHOP DRAWING). Fabricate wall jamb anchor holes as shown below. It is recommended to place rst hole at 6” from each ends and addional holes along the span as required by the engineer or as reected on the shop drawing. Fig. 2.3 Fastener holes for horizontal aachment Wall Jamb Fastener holes for horizontal aachment NOTE: CG450-18 at ller must be used for aaching CT451-31 to substrate (min. of 6” length) Anchor holes (Drill & countersunk for at head fas-tener). Refer to approved shop drawing or Engi-neer’s recommendaons for quanty and spacing Anchor hole CT451-31 FIG. 2.3

Page 11

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 11 STEP 3: FABRICATE HORIZONTALS AND GLASS STOPS Cut horizontal proles (head, sill & intermediate) to DLO . Cut glass stops to DLO minus (-) 1/32”. Fabricate head and sill anchor holes as shown. FIG. 3.1 ANCHOR AT HEAD Head Clear hole for 1/4” Ø main anchor  STEP 3.1 USING TALL SILL CT451-39 (CT451/452 THERMAL SYSTEM). Place rst hole 2” from each ends and addional holes are spaced at 2” O.C. for the sill as per FIG. 3.0 Head anchor is 3” o ends and space at 3” O.C. as shown on FIG. 3.1. or as required. Refer to shop drawing or engineer’s recommendaon for detailed requirement. See table below for guidance. NOTE: Horizontal sill to starter sill anchor varies in quanty requirement. For every reacon load imposed on the store-front, there’s a corresponding fastener quanty require-ment. Refer to shop drawing, or engineer’s recommenda-on. See table for guidance. Clear hole for FAS10-12 fastener (counter sunk) FIG. 3.0 ANCHOR AT SILL Sill NOTE: For anchors on CT451-11 sill in combinaon with CT451-39 starter sill (recommended on interior glazed opon), drill 1/4" clear hole spaced at 3" o ends and 3" o.c. thereaer on CT451-11 sill as per approved shop drawing or engineer's recommenda-ons. Refer to FIG. 3.4 for a similar procedure.

Page 12

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 12  STEP 3.2 USING FLAT SILL CG451-12 (CG451 NON-THERMAL SYSTEM): Place the rst hole 3” from each ends and addi-onal holes are spaced at 3” O.C., or as required. Refer to approved shop drawing or engineer’s requirements for quanty, size and locaon for each type of substrate. Clear hole for 1/4” Ø main anchor FIG. 3.2 HEAD & SILL Main anchor FIG. 3.3 CT451-39. ANCHOR HOLE FABRICATION REQ’D FIG. 3.4 CG451-12. NO FABRICATION REQUIRED FAS10-12 Main Anchor Transfer Drill at job site NOTE: Consult shop drawing or engineer to determine main anchor size, quanty, embedment & edge distance. Recommended spacing at 3” O.C. This product received pre-engineered product approval from Florida Building Commission. You can request a copy of the product approval drawings from your branch. Refer to STEP 10 on page 27 for further informaon. Recommended for use in combinaon with CT451-4 Horizontal Sill Only Transfer Drill Main Anchor to Starter Sill at job site Seng Screw

Page 13

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 13 STEP 4. FABRICATE STARTER SILL (CT451-39): Cut starter sill CT451-39 or CG451-12 (Reference FIG. 1.0, STEP 1 for cut length).  For CT451-39, drill and countersunk 1/4" Ø anchor holes as shown. Anchor holes should be 3" on each side of vercals. Re-fer to approved shop drawing or engineer’s requirements for addional anchors. For weep hole locaons, mark locaon of vercals on starter sill. Drill 1/4” weep holes approximately at quarter point of D.L.O. Face of jamb Drill 1/4” weep hole NOTE: CG451-12 Starter Sill. Anchor holes are to be transferred drilled from the horizontal sill (FIG. 3.4 on page 12). No fabricaon holes required. Set starter sill as noted on STEP 6.1.2 on page 17. FIG. 4.0 Anchor hole Face of Intermediate vercal

Page 14

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 14 STEP 5A. FRAME ASSEMBLY - EXTERIOR GLAZED. APPLY GT-1 TACKY TAPE AT ALL HORIZONTAL TO VERTICAL JOINTS. NOTE: Silicone sealant Dowsil 1199 (or equal) can be used at joint as alternate opon to GT-1 Tacky Tape. CRITICAL SEAL: Clean, prep and completely ll gasket reglet with sealant at boom of vercal and pocket ller as shown. CT451-31 FIG. 5.0 CT451-11 (SHOWN) CT451-31 (OPTIONAL) CT451-4 FIG. 5.1 CT451-35 FAS14-2 Typical frame screw. Seal Heads CT451-36 Sealant

Page 15

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 15 STEP 5B. FRAME ASSEMBLY - INTERIOR GLAZED. APPLY GT-1 TACKY TAPE AT ALL HORIZONTAL TO VERTICAL JOINTS. NOTE: Silicone sealant Dowsil 1199 (or equal) can be used at joint as alternate opon to GT-1 Tacky Tape. CT451-31 CT451-4 CRITICAL SEAL: Clean, prep and completely ll gasket reglet with sealant at boom of vercal and pocket ller as shown. CT451-36 CT451-4 FIG. 5.2 CT451-35 Sealant FAS14-2 Typical frame screw. Seal Heads

Page 16

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 16 STEP 6. PRE-ATTACHED END DAM(s) TO STARTER SILL PRIOR TO INSTALLATION  For CT451-39: Aach ED451-2 end dam(s) using 23005 screw to starter sill as shown in FIG. 6.0  For CG451-12: Aached ED451-2 end dam(s) with double VHB Tape or silicone sealant.  Apply sealants along joint . CG451-12 Flat Threshold (CG451 System Only) ED450-1 ED450-2 CT451-39 Hi-Performance Threshold 23005 FIG. 6.0

Page 17

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 17 STEP 6.1 SETTING OF STARTER SILL. Center starter sill into opening allowing for a 1/4” (minimum) shim space at each side. Shim beneath starter sill and ensure that it is level and plumb. Wedge shims ghtly behind end dams at wall jambs and seal as shown in FIG. 6.1. 1/4” Shim Seal and tool end dam to starter sill Aach with structural fasteners and seal heads. (Structural Fasteners not by Trulite ED451-2 FIG. 6.1 CT451-39 INSTALLATION Recommended for use in combinaon with CT451-4 Horizontal Sill Only STEP 6.1.1 USING CT451-39 STARTER SILL. STEP 6.1.2 USING CG451-12 STARTER SILL. Run connuous bead of sealant on the substrate along the line of structural anchor locaon and return at least 6” (minimum) at jambs prior to seng the starter sill. FIG. 6.2 CG451-12 INSTALLATION Install starter sill using seng fasteners and seal heads. (Seng Fasteners not by Trulite). Main anchor are to be transferred drilled from horizontal sill. Connuous bead of sealant along anchor locaon Seal and tool end dam to starter sill ED451-2 1/4” Shim Not recommended to use on CT451/CT452 Thermal Storefront System

Page 18

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 18 STEP 6B. OPTIONAL (STARTER SILL TERMINATION AT DOOR JAMB) IF REQUIRED (NOTE: Same procedure if using CG451-12 starter sill) Install door frame in opening rst. Install starter sill so that it abuts ghtly against door jamb. Shim, level and aach to substrate with anchor fasteners. Cap seal fasteners and apply sealant at inside of door jamb and starter sill as shown in FIG. 6.3. NOTE: Do not apply perimeter sealant at this me. Perimeter sealant is not applied unl all panels have been installed and aached to wall opening. Shim DOOR JAMB AT SIDELITE Thoroughly seal along joint Threshold is anchored to nished oor. Reference door and doorframe instrucons. STARTER SILL AT DOOR JAMB FIG. 6.3 Door jamb rests on nished oor. Thoroughly seal inside perimeter and end of starter sill to prevent water inltraon except front face for water to drain outside. CT451-39 Starter Sill Caulk Ends of starter sill and gap opening at shim

Page 19

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 19 STEP 6C. STARTER SILL SPLICE Provide splice at the starter sill if the wall length exceeds 24. Splices should be located every 12 to 15 feet with a 1/2” expansion joint as shown in FIGS. 6.4 & 6.5. NOTE: Locate splice anywhere between weep holes. Clean and dry surface before applying sealant. Put masking tape before applying sealant to prevent over spilling 2” wide x 0.03” thk Silicone Tape (or equal) FIG. 6.4 Bed of sealant (Dowsil 791 or equal) Provide backer rod as needed FIG. 6.5 Remove masking tape only once sealant is cured Ensure silicone tape hugged along the surface of starter sill

Page 20

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 20 STEP 6D. OPTIONAL (STARTER SILL CORNER CONNECTION) IF REQUIRED Miter cut two 18” secons of starter sill to correct angle as shown in FIG. 6.6. Drill and countersink two anchor holes located in each secon as shown to anchor starter sill. Shim and anchor with 1/4” Ø structural fasteners and cap seal. Completely seal mi-tered corners. Typical bulk head installaon into starter sill. FIG. 6.7 1/4” Ø weep hole NOTE: All dimensions shown for splice are approximate and may be modied based on job condions. FIG. 6.6 18” 18” 10” 3” 1/4” Ø weep hole Seal corner Refer to Step 6C For splice procedure bead of sealant along anchor locaon

Page 21

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 21 STEP 6E. OPTIONAL (HEAD RECEPTOR) IF REQUIRED Refer to approved shop drawing or Engineer’s requirements for type of head receptor for specic project design pressure. HEAD RECEPTOR SPLICE AT HEAD RECEPTOR SPLICE APPLICATION AT HEAD RECEPTOR IS THE SAME AS DEPICTED ON THE ISOMETRIC BELOW. Refer to Step 6C for similar procedure. 2” wide x 0.03” thk Silicone Tape (or equal) 1/2” gap Fill gap with sealant (Dowsil 791 or equal) connuous RG-11 gasket

Page 22

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 22 STEP 6F. *Determined by job condions, project specicaons and temperature at the me of installaon. Expansion mullions allow for 3/8” maximum movement. Reference FIG. 6.8 EXPANSION GAP SIZE FORMULA = L x F x 0.0000129  L= Length in inches between centerline of expansion mullion in elevaon  F= Specied temperature variaon (°F )  0.0000129 = Thermal coecient for aluminum EXAMPLE: Assume 100° temperature variaon specied and temperature at job site on day of installaon is 60°. 1. 100° - 60° = 40° temperature dierence 2. Length of elevaon between expansion mullions equals 20’ - 0” or 240” 3. 240” x 40° x 0.0000129 = 0.124”. Therefore, set expansion gap at 0.124 or 1/8” FIG. 6.8 STEP 6F. OPTIONAL (EXPANSION MULLION) IF REQUIRED

Page 23

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 23 STEP 7A. Aach horizontal members to one side and anchor head and sill as shown in FIG 6.9. Install horizontals to other side and anchor head and sill. CT451-14 Corner Post Sealant at joint CT451-39 Starter Sill FIG. 6.9 CT451-4 Sill CG451-15 Corner Trim FIG. 6.10 Sealant Typical Install corner trim as shown in FIG. 6.10

Page 24

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 24 Fabricate female half of expansion mullion used for oponal adjustable covers same manner as for standard mullion. STEP 7B. OPTIONAL (ADJUSTABLE COLUMN COVERS) IF REQUIRED 1/8” Aluminum Break Metal Typ. (Not by Trulite) 1/8” Aluminum Break Metal Typ. (Not by Trulite) Sea all voids with sealant Varies

Page 25

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 25 STEP 8. NOTE: Remove all debris from starter sill to prevent trash from blocking weep holes prior to installing panels. Install rst panel on le end, plumb, level and place 1/4” shim ghtly between end dam and wall jamb. See FIG. 6.1. Match drill anchor holes in head prole into substrate. Apply sealant to "C" slot in starter sill See FIG. 8.2. With the rst panel installed and aached to substrate, connue installing panels as illustrated on Step 9. NOTE: Ensure panels are pushed ghtly against starter sill and level before aaching at head, see FIG. 8.3. Anchor jambs to substrate when required. Once all panels have been installed and securely an-chored, cap seal all structural fasteners. Reference shop drawings or engineer’s requirements. Apply perimeter seal on exterior and interior. For weeps at CT451-39 starter sill, see FIG. 4.0. Refer to the following steps for detailed instrucons. INSTALLATIONS NOTE: Just prior to installing the frame secons, apply a connuous bead of sealant lling the “c” slot at the top of the sill ash-ing. See FIG. 8.2 EXTERIOR GLAZED INTERIOR GLAZED FIG. 8.0 FIG. 8.1 FIG. 8.4 FIG. 8.3 Note: Check to ensure the sill sits ush on the starter sill before aaching FIG. 8.2 Apply sealant to "C" slot

Page 26

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 26 STEP 9. Frames can be shop fabricated and assembled into panels for eld installaon. Each panel must have at least one deep pocket for glazing. Two shallow pockets should never be facing each other. Expansion mullions should be used in elevaons exceeding 24 feet in length to allow for thermal movement. See FIG. 6.8. FIG. 9.0 Intermediate Panel Sequence FIG. 9.1 Expansion Mullion Panel Sequence FIG. 9.2 Last Panel Sequence

Page 27

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 27 10A. MAIN ANCHOR REQUIREMENT (NOT SUPPLIED BY TRULITE) Applies to all head CT451-39 Non-thermal Opon CG451-12 Each project is dierent. Consult an engineer to determine main anchor size, quanty, embedment & edge distance. Recom-mended spacing at 3” O.C. This product received pre-engineered product approval from Florida Building Commission. You can request a copy of the product approval drawings from your branch. FIG. 10.0 10B. SILL ANCHOR (FAS10-12) NOTE: Horizontal sill to starter sill anchor varies in quanty re-quirement. For every reacon load imposed on the storefront, there’s a corresponding fastener quanty requirement. Refer to shop drawing, or engineer’s recommendaon. See table below for guidance. Fastener is 2” o the face of mullion and 2”O.C. spacing FAS10-13

Page 28

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 28 11. APPLY PERIMETER SEALANT. Ext. Perimeter Seal Note, it is recommended to seal both exterior and interior perimeter. Jamb Sill Sill Ext. Perimeter Seal Head Pre-applied sealant bead Ext. Perimeter Seal Ext. Perimeter Seal FIG. 11.0 Make sure perimeter sealant is connuous (no gap) to prevent possible air and water inltraon.

Page 29

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 29 STEP 12. GLASS INSTALLATION. REMOVE ALL TRASH FROM GLAZING POCKETS AND REGLETS. Set glass on two (2) idencal seng blocks posioned at 1/4 points or 1/8 points in opening. It is recommended not to place seng blocks closer than 6” from the edge of glass. (Refer to approved shop drawing or Engineer’s requirements for special condi-ons). FIG. 12.0 FIG. 12.1 GLASS SIZE CALCULATION Glass bite is 7/16”. To calculate glass size, add two 7/16” (or 7/8”) to D.L.O size. Example: Vercal D.L.O = 92” Horizontal D.L.O. = 46” Glass sizes: Height of glass = 92” + 7/8” = 92 7/8” Width of glass = 46” + 7/8” = 46 7/8”

Page 30

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 30 STEP 13. EXTERIOR or INTERIOR GLAZING: Place seng blocks at 1/4 points or 1/8 points (refer to shop drawing or engineer’s recommendaons). Note, interior glazing gas-kets can be installed before glass installaon (refer to STEP 16) but for beer glass maneuvering, interior and exterior gaskets can be installed aer the glass is set. INSTALL GLASS: Use glazing methods below. For exterior FIG. 13.0 or interior FIG. 13.1 glazing begins with boom lites and works toward the top. FIG. 13.0 FIG. 13.1 EXTERIOR GLAZING 3 1 2 INTERIOR GLAZING 1 2 3 5 4 5 4

Page 31

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 31 STEP 14. Install WD451-1 water deectors at each end of intermediate horizontals during sequenal glazing process aer the boom lite of glass has been installed. Repeat process for each subsequent intermediate horizontal. Embed water deectors in bed of sealant. See FIG. 14.0. WD451-1 Install snap-in glass stops. Apply sealant to ends of glass stops for interior glazing only. CG451-3 CG451-3 FIG. 14.1 CG451-3 CG451-3 CG451-3 Sealant Sealant EXTERIOR GLAZED INTERIOR GLAZED Embed WD451-1 in sealant as shown FIG. 14.0 WD451-1

Page 32

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 32 STEP 15. Regions prone to seismic movement and/or buildings near highways oen require an-walk blocks (“W” blocks) to prevent the glass from “walking” or shiing from the shallow pocket into the deep pocket. Install one RW451-1 “W” an-walk block into the deep glass pocket at the approximate center of the glass opening as shown in FIG. 15.0. RW451-1 An-walk “W” block FIG. 15.0 Flaen “W” block. Slide between reglet and glass into pocket behind glass.

Page 33

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 33 STEP 16. Four gaskets are cut 3⁄16” longer per foot than D.L.O. (width and height; Ref. FIG. 12.1) to allow for shrinkage. It is important that gaskets are cut and installed as shown in FIG. 16.0. Start head and jamb gaskets at center and corners FIG. 16.0 Start sill gasket at seng block

Page 34

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 34 GLAZING GASKETS FOR STOREFRONT SYSTEMS CORNER TREATMENTS Glazing gaskets are prone to shrink and pull away at the corners over a period of me. This allows for excessive air and/or water inltraon at the corners. Standard glazing pracce is to provide corner treatment to ensure weather ghtness on the exterior and interior corner intersecons. NOT RECOMMENDED Notch Cung Corners - The corners of the rubber gasket are notched on the underside without cung the nearside. The gasket is installed in one length and is bu joined in the center at the horizontal or header. While this method of glazing is widely used for marine glazing residenal sliding glass doors or shower doors, it is not recommended for commercial storefront glazing. RECOMMENDED (SEALED CORNERS) Pull gaskets back 2” in both direcons from interior and exterior corners as shown in FIG. 16.2 and seal with sealant. This should be done on exterior and interior for best performance. While long-term adhesion to the rubber gaskets with sealant is not assured, historical eld experience has proven this type corner treatment to be the next best method short of vulcanized corner gaskets. Apply sealant 2” back from each corner SEAL CORNERS NOTE: Schemac art is not representave of exact details shown within these instrucons. FIG. 16.2 NOT RECOMMENDED FIG. 16.1

Page 35

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 35 CT451 PARTS INDEX FRAMING MEMBERS

Page 36

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 36 CT452 PARTS INDEX FRAMING MEMBERS

Page 37

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 37 CG451 PARTS INDEX FRAMING MEMBERS

Page 38

SERIES CT451 / CT452 / CG451 STOREFRONT SYSTEM INSTALLATION INSTRUCTION 403 West Park Court, Suite 201, Peachtree City, GA 30269. Tel (800) 432-8132. www.trulite.com page 38 ACCESSORIES