HOMEOWNER'S ESTIMATE FOR

 

1011 MADISON LANE

 

 

02.14.17

 

 

V.01

 

PROPOSAL
February 15, 2017
Submitted to:
Business: craigthole@gmail.com
Personal: ebradican@aol.com
NEWTOWN SQUARE, PA 19073
1011 MADISON LANE
TRACY THOLE and CRAIG THOLE
Business: 2155824529
Business: foxfireww@gmail.com
OADLTD, LLC
Submitted by:
GENERAL CONDITIONS
The contractor shall provide all necessary labor and materials, and perform all work of every nature on the proposed remodeling
in accordance with this contract, the specifications, and the accompanying drawings. The Contractor shall obtain the building
permit. All subcontractors will take out their own permits and pay for them. The owner, if necessary, will have the lot surveyed
and will apply for all zoning, historic preservation or other related permits as necessary. Work for any of these are not included
under this contract. All work is to be executed in a workman like manner in accordance with the contract, plans, and
specifications.
PROJECT SPECIFICATIONS-
1011.GLOBAL.H02
REVISED: 02.14.17
RE: REPAIRS FOR DAMAGE FROM WATER LINE LEAK ON 12.23.16 W/ADDITIONAL ROOMS
C00: MUDROOM
OAD QBO LIST
PROGRESS CLEANING
$29.12
PROJECT PREPARATION
NIC/BY OTHERS: MOVE OUT THEN RESET ROOM CONTENTS
$0.00
GENERAL DEMOLITION
GENERAL DEMO
$29.12
SYSTEMS DEMOLITION
NA: DISCONNECT&CAP ALL MEP
$0.00
LOAD/HAUL/DISPOSE OF DEBRIS
$18.68
WALL FRAMING
CARPENTRY: ROUGH
$108.16
GENERAL PLUMBING
NA: MEP: PLUMBING
$0.00
HEATING, VENTILATION, AIR CONDITIONING
MEP: HVAC- CLEAN&REINSTALL EXISTING REGISTERS & GRILLS
$13.52
ELECTRICAL
MEP: ELECTRICAL&LIGHTING- REINSTALL EXISTING/NEW FIXTURES; NEW WIRING DEVICES&COVER PLATES
AS REQUIRED
$124.92
INSULATION
INSULATION&WEATHERPROOFING: REPLACE AS REQUIRED
$125.04
WALL COVERINGS
PATCHING&REPAIRS FOR EXISTING WALLS
$0.00
WALL COVER: SEE WALLPAPER
$0.00
DRYWALL: WALLS&CEILINGS- PAINT READY
$708.40
INTERIOR DOORS
DOORS: VERIFY FIT&OPERATION OF EXISTING INTERIOR DOOR(S); REINSTALL HARDWARE AFTER PAINTING
$134.88
INTERIOR TRIM, STAIRS AND ACCESSORIES
CARPENTRY: FINISH- CASING FOR WINDOW&DOORS; BASEBOARDS; MISC.TRIMS
$784.80
DETAILS: MISC.- RE-SET COAT CLOSET
$108.00
CABINETS AND COUNTERTOPS
MILLWORK&BUILT-INS: DETAIL EXISTING BUILT-IN
$65.16
FLOOR COVERING
FLOORING: SEE 'GLOBAL' FIGURES FOR FLOORING- HARDWOOD
$0.00
Sub-Total is
$2,249.80
C01: GLOBAL
OAD QBO LIST
ALLOWANCE FOR PERMITS: $2,800
$3,192.00
GLOBAL: FINAL CLEANING
$2,284.96
TEMPORARY PROTECTION: TRIMS
$207.68
TEMPORARY PROTECTION: WOOD FLOORS
$943.48
TEMPORARY PROTECTION: CARPET FLOORS
$618.12
TEMPORARY PROTECTION: CABINETS&BUILT-INS
$344.48
SPECIAL: DECORATING: HANG PICTURES, PAINTINGS, ACCESSORIES
$1,265.76
FIRE SUPPRESSION- EXISTING SYSTEM- PROTECT DURING WORK; INSTALL TRIMS/COVERS
$1,143.12
HVAC DUCTS: CLEANING
$1,426.24
DETECTION&ALARMS: TEST ALL SYSTEMS; ADDITIONAL FOR ANY REQUIRED REPAIRS
$171.00
PROJECT PREPARATION
PROJECT SET-UP
$684.00
NIC/BY OTHERS: MOVE CONTENTS TO ON-SITE STORAGE; 3-MO.ON-SITE RENTALS FOR (3) CONTAINERS;
W/INSURANCE
$0.00
NIC: SPECIALITY: $2,850 ALLOWANCE FOR AIR QUALITY TESTING/NO REMEDIATION, SEE SEPARATE FIGURE
$0.00
NIC: ALLOWANCE FOR MOLD REMEDIATION: ALLOWANCE OF $3,200
$0.00
JOBSITE PREPARATION
PROTECTION FOR EXISTING SURFACES; ROOMxROOM
$997.20
CLEANUP
DAILY CLEAN-UP&LOADING OF DUMPSTER
$623.04
DUMPSTER
$1,783.36
Sub-Total is
$15,684.44
C02: WOOD FLOORS
OAD QBO LIST
WOOD FLOORS: ADDITIONAL DEMO FOR SELECTED AREAS NOT DEMO'D UNDER REMEDIATION
$349.44
FLOORS: SUBFLOORS- SELECTIVE REPAIR TO EXISTING SUBFLOOR FOR WATER DAMAGE; RE-NAIL ALL AREAS
PRIOR TO INSTALLATION OF NEW FLOORING
$1,246.08
FLOOR: TRIMS&TRANSTIONS
$973.44
FLOOR: QTR.ROUND TRIM- SUPPLY&INSTALL PAINTED OR PREFINISHED SHOE/QTR.RND.TRIM @ ALL NEW
WOOD FLOORS
$2,310.24
WOOD FLOOR: PREP- AQUABAR B UNDERLAYMENT BARRIER PAPER
$754.81
WOOD FLOOR: 3/4"X3 1/4" RED OAK PREFINISHED SELECT GRADE T&G FLOORING
$26,455.74
Sub-Total is
$32,089.75
C03: CARPET FLOORS
OAD QBO LIST
FLOOR: ADDITIONAL DEMO FOR FOR CARPET FLOOR AREAS NOT DEMO'D DURING REMEDIATION
$174.72
FLOOR: SUBFLOOR- LIMITED REPAIRS TO EXISTING SUBFLOOR; RENAIL ALL INCLUDED SUBFLOOR AREAS
$253.28
FLOOR: TRIMS&TRANSITIONS
$379.68
FLOOR: CARPET W/INSTALLATION(PER SQ.FT): CARPET ALLOWANCE @ $8.50/SQ.FT.
$17,410.08
CARPET STAIR RUNNERS: MAIN STAIRS, STAIRS TO BASEMENT, BACK STAIRS
$3,209.33
FLOOR: CARPET SUPPLIES
$114.00
FLOOR: CARPET PAD- 10LB.PAD
$1,267.91
Sub-Total is
$22,809.00
C04: MAIN STAIRCASE- REFINISH WOOD STAIRS AND STAIRS&RAILINGS
OAD QBO LIST
WOOD RAILINGS: STAIN&FINISH
$408.48
WOOD RAILINGS: PREP FOR REFINISH
$390.96
WOOD FLOORS: PREP&SANDING
$799.49
STAIRS: STAIN&FINISH
$879.36
STAIRS: SCOTIA TRIMS
$362.88
STAIRS: PREP&PAINT BALUSTERS
$431.28
STAIRS: PREP&PAINT SKIRTS
$575.04
STAIRS: CARPET RUNNER, SEE CARPET FLOORS
$0.00
Sub-Total is
$3,847.49
C05: BACK STAIRCASE- REFINISH WOOD STAIRS AND STAIRS&RAILINGS
OAD QBO LIST
WOOD RAILINGS: STAIN&FINISH
$287.52
WOOD RAILINGS: PREP FOR REFINISH
$149.04
WOOD FLOORS: PREP&SANDING
$734.98
STAIRS: STAIN&FINISH
$879.36
STAIRS: SCOTIA TRIMS
$362.88
STAIRS: PREP&PAINT SKIRTS
$454.08
STAIRS: PREP&PAINT RAILINGS
$229.68
STAIRS: CARPET RUNNER, SEE CARPET FLOORS
$0.00
Sub-Total is
$3,097.54
C06: BASEMENT STAIRCASE- REFINISH WOOD STAIRS AND STAIRS&RAILINGS
OAD QBO LIST
WOOD RAILINGS: STAIN&FINISH
$206.88
WOOD RAILINGS: PREP FOR REFINISH
$229.68
STAIRS: STAIN&FINISH
$879.36
STAIRS: SCOTIA TRIMS
$326.40
WOOD FLOORS: PREP&SANDING
$702.72
STAIRS: PREP&PAINT SKIRTS
$333.12
STAIRS: CARPET RUNNER, SEE CARPET FLOORS
$0.00
Sub-Total is
$2,678.16
C07: MUDROOM POWDER ROOM
OAD QBO LIST
PROGRESS CLEANING
$29.12
PROJECT PREPARATION
NIC/BY OTHERS:MOVE OUT THEN RESET ROOM CONTENTS
$0.00
GENERAL DEMOLITION
GENERAL DEMO
$29.12
SYSTEMS DEMOLITION
DISCONNECT&CAP ALL MEP
$68.16
LOAD/HAUL/DISPOSE OF DEBRIS
$15.04
WALL FRAMING
CARPENTRY: ROUGH
$72.32
GENERAL PLUMBING
MEP: PLUMBING- (RE)INSTALL EXISTING FIXTURES
$454.08
HEATING, VENTILATION, AIR CONDITIONING
MEP: HVAC- CLEAN&REINSTALL EXISTING REGISTERS & GRILLS
$13.52
ELECTRICAL
MEP: ELECTRICAL&LIGHTING- REINSTALL EXISTING/NEW FIXTURES; NEW WIRING DEVICES&COVER PLATES
AS REQUIRED
$83.28
INSULATION
INSULATION&WEATHERPROOFING: REPLACE AS REQUIRED
$44.46
WALL COVERINGS
NA: PATCHING&REPAIRS FOR EXISTING WALLS
$0.00
WALL COVER: SEE WALLPAPER
$0.00
DRYWALL: WALLS&CEILINGS- PAINT READY
$556.60
INTERIOR DOORS
DOORS: VERIFY FIT&OPERATION OF EXISTING INTERIOR DOOR(S); REINSTALL HARDWARE AFTER PAINTING
$33.72
INTERIOR TRIM, STAIRS AND ACCESSORIES
CARPENTRY: FINISH- CASING FOR WINDOW&DOORS; BASEBOARDS; MISC.TRIMS
$392.40
DETAILS: MISC.
$81.12
CABINETS AND COUNTERTOPS
NA: MILLWORK&BUILT-INS: DETAIL EXISTING BUILT-IN
$0.00
FLOOR COVERING
FLOORING: SEE 'GLOBAL' FIGURES FOR FLOORING
$0.00
Sub-Total is
$1,872.94
C08: KITCHEN&BUTLER'S PANTRY: NEW CABINETS, GRANITE, APPLIANCE & FIXTURES
OAD QBO LIST
PROGRESS CLEANING
$162.08
DETAILING: ADJUSTMENTS & DETAILING
$633.68
TILE: TILE BACKSPLASH- SUPPLY & INSTALL NEW TILE BACKSPLASH PER ORIGINAL; $12/SQ.FT.FOR TILE
$1,710.94
ALLOWANCE: APPLIANCES: KITCHEN- ALL NEW APPLIANCES
$18,696.00
WINDOW TREATMENTS: KITCHEN- CLEAN & REINSTALL EXISTING FIXTURES
$117.16
COUNTER TOPS: ALLOWANCE FOR NEW GRANITE/QUARTZ
$12,084.00
ALLOWANCE: DISPOSAL,SINK&FAUCET
$2,211.60
HVAC: KITCHEN VENTING- RECONNECT EXISTING VENT HOOD TO EXISTING DUCTWORK
$140.08
APPLIANCES, LIGHTING & DEVICES: SPECIAL NOTE: EXISTING FIXTURES- ANY ITEMS THAT ARE DAMAGED OR
MISSING PARTS WILL REQUIRE REPLACEMENT @ ADDITIONAL COST(S); CHANGE ORDER(S) WILL BE
REQUIRED
$0.00
TECH: SPEAKERS
$311.84
PROJECT PREPARATION
NIC/BY OTHERS: MOVE OUT THEN RESET ROOM CONTENTS
$0.00
GENERAL DEMOLITION
GENERAL DEMO: REMOVE ANY REMAINING FIXTURE
$262.08
SYSTEMS DEMOLITION
DISCONNECT&CAP ALL MEP
$371.28
LOAD/HAUL/DISPOSE OF DEBRIS
$172.24
WALL FRAMING
CARPENTRY: MINOR ROUGH CARPENTRY AS REQUIRED
$710.24
GENERAL PLUMBING
MEP: PLUMBING- ALL ROUGH&FINISH PLUMBING TO RECONNECT EXISTING KITCHEN
$1,261.44
HEATING, VENTILATION, AIR CONDITIONING
MEP: HVAC- CLEAN&REINSTALL EXISTING REGISTERS & GRILLS
$27.04
ELECTRICAL
MEP: ELECTRICAL&LIGHTING- REINSTALL EXISTING/NEW FIXTURES&APPLIANCES; NEW WIRING
DEVICES&COVER PLATES AS REQUIRED
$1,551.60
INSULATION
INSULATION&WEATHERPROOFING: REPLACE AS REQUIRED
$166.73
WALL COVERINGS
WALL COVER: MIRROR BACKSPLASH @ BUTLER'S PANTRY
$224.76
DRYWALL: WALLS&CEILINGS- PAINT READY
$1,720.40
INTERIOR DOORS
DOORS: VERIFY FIT&OPERATION OF EXISTING INTERIOR DOOR(S); REINSTALL HARDWARE AFTER PAINTING
$134.88
INTERIOR TRIM, STAIRS AND ACCESSORIES
CARPENTRY: FINISH- CASING FOR WINDOW&DOORS; BASEBOARDS; MISC.TRIMS
$2,086.56
ALLOWANCE: DETAILS: MISC.- TROMPE-L'OEIL DETAILS@2 AREAS
$684.00
CABINETS AND COUNTERTOPS
MILLWORK&BUILT-INS- INSTALL ALL CABINETS&TRIMS
$5,784.48
KITCHEN&BUTLER'S PANTRY CABINETRY- ALLOWANCE FOR NEW CABINETRY, PANELS TRIMS & DETAILS:
ALLOWANCE OF $44,500 FOR CABINETS & TRIMS
$52,531.20
FLOOR COVERING
FLOORING: SEE 'GLOBAL' FIGURES FOR FLOORING- HARDWOOD
$0.00
Sub-Total is
$103,756.31
C09: FAMILY ROOM
OAD QBO LIST
PROGRESS CLEANING
$29.12
WINDOW TREATMENTS- CLEAN & RE-SET CURTAINS&WINDOW TREATMENTS
$395.16
PROJECT PREPARATION
NIC/BY OTHERS: MOVE OUT THEN RESET ROOM CONTENTS
$0.00
GENERAL DEMOLITION
GENERAL DEMO
$29.12
SYSTEMS DEMOLITION
NA: DISCONNECT&CAP ALL MEP
$0.00
LOAD/HAUL/DISPOSE OF DEBRIS
$18.68
WALL FRAMING
CARPENTRY: ROUGH
$108.16
GENERAL PLUMBING
NA: MEP: PLUMBING
$0.00
HEATING, VENTILATION, AIR CONDITIONING
MEP: HVAC- CLEAN&REINSTALL EXISTING REGISTERS & GRILLS
$27.04
ELECTRICAL
MEP: ELECTRICAL&LIGHTING- REINSTALL EXISTING/NEW FIXTURES; NEW WIRING DEVICES&COVER PLATES
AS REQUIRED
$230.40
INSULATION
NA: INSULATION&WEATHERPROOFING: REPLACE AS REQUIRED
$0.00
WALL COVERINGS
PATCHING&REPAIRS FOR EXISTING WALLS
$643.44
NA: WALL COVER: APPLICATION OF SPECIAL FINISH/TREATMENTS PER ORIGINAL CONDITIONS
$0.00
NA/SEE PATCHING: DRYWALL: WALLS&CEILINGS- PAINT READY
$0.00
INTERIOR DOORS
NA: DOORS: VERIFY FIT&OPERATION OF EXISTING INTERIOR DOOR(S); REINSTALL HARDWARE AFTER
PAINTING
$0.00
INTERIOR TRIM, STAIRS AND ACCESSORIES
CARPENTRY: FINISH- CASING FOR WINDOW&DOORS; BASEBOARDS; MISC.TRIMS
$563.52
DETAILS: MISC.
$87.84
CABINETS AND COUNTERTOPS
MILLWORK&BUILT-INS: DETAIL EXISTING BUILT-IN
$234.96
FLOOR COVERING
FLOORING: SEE 'GLOBAL' FIGURES FOR FLOORING- CARPET
$0.00
Sub-Total is
$2,367.44
C10: BREAKFAST ROOM
OAD QBO LIST
PROGRESS CLEANING
$29.12
WINDOW TREATMENTS- CLEAN&RESET EXISTING CURTAINS
$219.76
PROJECT PREPARATION
NIC/BY OTHERS: MOVE OUT THEN RESET ROOM CONTENTS
$0.00
GENERAL DEMOLITION
GENERAL DEMO
$58.24
SYSTEMS DEMOLITION
NA: DISCONNECT&CAP ALL MEP
$0.00
LOAD/HAUL/DISPOSE OF DEBRIS
$18.68
WALL FRAMING
CARPENTRY: ROUGH
$58.64
GENERAL PLUMBING
NA: MEP: PLUMBING
$0.00
HEATING, VENTILATION, AIR CONDITIONING
MEP: HVAC- CLEAN&REINSTALL EXISTING REGISTERS & GRILLS
$13.52
ELECTRICAL
MEP: ELECTRICAL&LIGHTING- REINSTALL EXISTING/NEW FIXTURES; NEW WIRING DEVICES&COVER PLATES
AS REQUIRED
$197.28
INSULATION
NA: INSULATION&WEATHERPROOFING: REPLACE AS REQUIRED
$0.00
WALL COVERINGS
PATCHING&REPAIRS FOR EXISTING WALLS
$454.08
NA: WALL COVER: APPLICATION OF SPECIAL FINISH/TREATMENTS PER ORIGINAL CONDITIONS
$0.00
NA: DRYWALL: WALLS&CEILINGS- PAINT READY- SEE PATCHING
$708.40
INTERIOR DOORS
DOORS: VERIFY FIT&OPERATION OF EXISTING INTERIOR DOOR(S); REINSTALL HARDWARE AFTER PAINTING
$37.08
INTERIOR TRIM, STAIRS AND ACCESSORIES
CARPENTRY: FINISH- CASING FOR WINDOW&DOORS; BASEBOARDS; MISC.TRIMS
$563.52
DETAILS: MISC.- TROMP-L'OIEL
$3,259.44
CABINETS AND COUNTERTOPS
NA: MILLWORK&BUILT-INS: DETAIL EXISTING BUILT-IN
$0.00
FLOOR COVERING
FLOORING: SEE 'GLOBAL' FIGURES FOR FLOORING- HARDWOOD
$0.00
Sub-Total is
$5,617.76
C11: PROJECT PAINTING
OAD QBO LIST
INTERIOR PAINTING: COAT CLOSET&FORMAL POWDER ROOM- PREP, PRIMER&PAINT
$912.00
INTERIOR PAINTING: FOYER&STAIRWELL- PREP, PRIMER&PAINT
$3,192.00
INTERIOR PAINTING: KITCHEN- PREP, PRIMER&PAINT
$2,280.00
INTERIOR PAINTING: FAMILY ROOM- PREP, PRIMER&PAINT
$2,166.00
INTERIOR PAINTING: BASEMENT BATHROOM PREP, PRIMER&PAINT
$1,083.00
INTERIOR PAINTING: MUDROOM- PREP, PRIMER&PAINT
$1,368.00
INTERIOR PAINTING: MUDROOM POWDER ROOM- PREP, PRIMER&PAINT
$570.00
INTERIOR PAINTING: DINING ROOM- PREP, PRIMER&PAINT
$1,596.00
INTERIOR PAINTING: LIVING ROOM- PREP, PRIMER&PAINT
$2,052.00
INTERIOR PAINTING: STUDY- PREP, PRIMER&PAINT
$2,052.00
INTERIOR PAINTING: BR.01- PREP, PRIMER&PAINT
$1,710.00
INTERIOR PAINTING: HALL BATH- PREP, PRIMER&PAINT
$1,368.00
INTERIOR PAINTING: 2ND.FLOOR BACK HALL&STAIRWELL- PREP, PRIMER&PAINT
$3,078.00
INTERIOR PAINTING: BASEMENT&STAIRWELL- PREP, PRIMER&PAINT
$3,990.00
Sub-Total is
$27,417.00
C12: WALLPAPER
OAD QBO LIST
WALLPAPER: FORMAL POWDER ROOM: ALLOWANCE FOR PAPER @ $500
$1,691.52
WALLPAPER: MUDROOM: ALLOWANCE FOR PAPER @ $800
$2,277.44
WALLPAPER: MUDROOM POWDER ROOM: ALLOWANCE FOR PAPER @ $500
$1,691.52
WALLPAPER: DINING ROOM: ALLOWANCE FOR PAPER @ $1000
$2,505.44
Sub-Total is
$8,165.92
C13: DINING ROOM
OAD QBO LIST
PROGRESS CLEANING
$29.12
PROJECT PREPARATION
NIC/BY OTHERS: MOVE OUT THEN RESET ROOM CONTENTS
$0.00
GENERAL DEMOLITION
GENERAL DEMO
$58.24
SYSTEMS DEMOLITION
NA: DISCONNECT&CAP ALL MEP
$0.00
LOAD/HAUL/DISPOSE OF DEBRIS
$25.96
WALL FRAMING
CARPENTRY: ROUGH
$108.16
GENERAL PLUMBING
NA: MEP: PLUMBING
$0.00
HEATING, VENTILATION, AIR CONDITIONING
MEP: HVAC- CLEAN&REINSTALL EXISTING REGISTERS & GRILLS
$27.04
ELECTRICAL
MEP: ELECTRICAL&LIGHTING- REINSTALL EXISTING/NEW FIXTURES; NEW WIRING DEVICES&COVER PLATES
AS REQUIRED
$257.76
INSULATION
INSULATION&WEATHERPROOFING: REPLACE AS REQUIRED
$13.90
WALL COVERINGS
PATCHING&REPAIRS FOR EXISTING WALLS
$188.96
WALL COVER: SEE WALLPAPER
$0.00
DRYWALL: WALLS&CEILINGS- PAINT READY
$809.60
INTERIOR DOORS
DOORS: VERIFY FIT&OPERATION OF EXISTING INTERIOR DOOR(S); REINSTALL HARDWARE AFTER PAINTING
$0.00
INTERIOR TRIM, STAIRS AND ACCESSORIES
CARPENTRY: FINISH- CASING FOR WINDOW&DOORS; BASEBOARDS; MISC.TRIMS; WAINSCOT; CROWN
$1,382.40
NA: DETAILS: MISC.- RE-SET COAT CLOSET
$0.00
CABINETS AND COUNTERTOPS
NA: MILLWORK&BUILT-INS: DETAIL EXISTING BUILT-IN
$0.00
FLOOR COVERING
FLOORING: SEE 'GLOBAL' FIGURES FOR FLOORING- HARDWOOD
$0.00
Sub-Total is
$2,901.14
C14: ENTRY FOYER
OAD QBO LIST
PROGRESS CLEANING
$29.12
PROJECT PREPARATION
NIC/BY OTHERS: MOVE OUT THEN RESET ROOM CONTENTS
$0.00
GENERAL DEMOLITION
GENERAL DEMO
$29.12
SYSTEMS DEMOLITION
NA: DISCONNECT&CAP ALL MEP
$0.00
LOAD/HAUL/DISPOSE OF DEBRIS
$18.68
WALL FRAMING
NA: CARPENTRY: ROUGH
$0.00
GENERAL PLUMBING
NA: MEP: PLUMBING
$0.00
HEATING, VENTILATION, AIR CONDITIONING
MEP: HVAC- CLEAN&REINSTALL EXISTING REGISTERS & GRILLS
$27.04
ELECTRICAL
MEP: ELECTRICAL&LIGHTING- REINSTALL EXISTING/NEW FIXTURES; NEW WIRING DEVICES&COVER PLATES
AS REQUIRED
$128.88
INSULATION
NA: INSULATION&WEATHERPROOFING: REPLACE AS REQUIRED
$0.00
WALL COVERINGS
PATCHING&REPAIRS FOR EXISTING WALLS
$85.36
NA: WALL COVER: APPLICATION OF SPECIAL FINISH/TREATMENTS PER ORIGINAL CONDITIONS
$0.00
NA: DRYWALL: WALLS&CEILINGS- PAINT READY
$0.00
INTERIOR DOORS
DOORS: VERIFY FIT&OPERATION OF EXISTING INTERIOR DOOR(S); REINSTALL HARDWARE AFTER PAINTING
$111.24
INTERIOR TRIM, STAIRS AND ACCESSORIES
CARPENTRY: FINISH- CASING FOR WINDOW&DOORS; BASEBOARDS; MISC.TRIMS
$563.52
NA: DETAILS: MISC.- RE-SET COAT CLOSET
$0.00
CABINETS AND COUNTERTOPS
NA: MILLWORK&BUILT-INS: DETAIL EXISTING BUILT-IN
$0.00
FLOOR COVERING
FLOORING: SEE 'GLOBAL' FIGURES FOR FLOORING- HARDWOOD
$0.00
Sub-Total is
$992.96
C15: LIVING ROOM
OAD QBO LIST
PROGRESS CLEANING
$29.12
PROJECT PREPARATION
NIC/BY OTHERS: MOVE OUT THEN RESET ROOM CONTENTS
$0.00
GENERAL DEMOLITION
NA: GENERAL DEMO
$0.00
SYSTEMS DEMOLITION
NA: DISCONNECT&CAP ALL MEP
$0.00
LOAD/HAUL/DISPOSE OF DEBRIS
$14.12
WALL FRAMING
NA: CARPENTRY: ROUGH
$0.00
GENERAL PLUMBING
NA: MEP: PLUMBING
$0.00
HEATING, VENTILATION, AIR CONDITIONING
MEP: HVAC- CLEAN&REINSTALL EXISTING REGISTERS & GRILLS
$27.04
ELECTRICAL
NA: MEP: ELECTRICAL&LIGHTING- REINSTALL EXISTING/NEW FIXTURES; NEW WIRING DEVICES&COVER
PLATES AS REQUIRED
$0.00
INSULATION
INSULATION&WEATHERPROOFING: REPLACE AS REQUIRED
$125.04
WALL COVERINGS
PATCHING&REPAIRS FOR EXISTING WALLS
$49.52
NA: WALL COVER: APPLICATION OF SPECIAL FINISH/TREATMENTS PER ORIGINAL CONDITIONS
$0.00
NA: DRYWALL: WALLS&CEILINGS- PAINT READY
$0.00
INTERIOR DOORS
NA: DOORS: VERIFY FIT&OPERATION OF EXISTING INTERIOR DOOR(S); REINSTALL HARDWARE AFTER
PAINTING
$0.00
INTERIOR TRIM, STAIRS AND ACCESSORIES
CARPENTRY: FINISH- CASING FOR WINDOW&DOORS; BASEBOARDS; MISC.TRIMS
$140.88
NA: DETAILS: MISC.- RE-SET COAT CLOSET
$0.00
CABINETS AND COUNTERTOPS
NA: MILLWORK&BUILT-INS: DETAIL EXISTING BUILT-IN
$0.00
FLOOR COVERING
FLOORING: SEE 'GLOBAL' FIGURES FOR FLOORING- HARDWOOD
$0.00
Sub-Total is
$385.72
C16: COAT CLOSET.FORMAL POWDER ROOM
OAD QBO LIST
PROGRESS CLEANING
$29.12
PROJECT PREPARATION
NIC/BY OTHERS: MOVE OUT THEN RESET ROOM CONTENTS
$0.00
GENERAL DEMOLITION
GENERAL DEMO
$29.12
SYSTEMS DEMOLITION
DISCONNECT&CAP ALL MEP
$83.28
LOAD/HAUL/DISPOSE OF DEBRIS
$18.68
WALL FRAMING
NA: CARPENTRY: ROUGH
$0.00
GENERAL PLUMBING
MEP: PLUMBING- REINSTALL EXISTING FIXTURES
$314.88
HEATING, VENTILATION, AIR CONDITIONING
MEP: HVAC- CLEAN&REINSTALL EXISTING REGISTERS & GRILLS
$13.52
ELECTRICAL
NA: MEP: ELECTRICAL&LIGHTING- REINSTALL EXISTING/NEW FIXTURES; NEW WIRING DEVICES&COVER
PLATES AS REQUIRED
$0.00
INSULATION
NA: INSULATION&WEATHERPROOFING: REPLACE AS REQUIRED
$0.00
WALL COVERINGS
PATCHING&REPAIRS FOR EXISTING WALLS
$49.52
NA: WALL COVER: APPLICATION OF SPECIAL FINISH/TREATMENTS PER ORIGINAL CONDITIONS
$0.00
NA: DRYWALL: WALLS&CEILINGS- PAINT READY
$0.00
INTERIOR DOORS
DOORS: VERIFY FIT&OPERATION OF EXISTING INTERIOR DOOR(S); REINSTALL HARDWARE AFTER PAINTING
$74.16
INTERIOR TRIM, STAIRS AND ACCESSORIES
CARPENTRY: FINISH- CASING FOR WINDOW&DOORS; BASEBOARDS; MISC.TRIMS
$140.88
DETAILS: MISC.- RE-SET COAT CLOSET
$67.68
CABINETS AND COUNTERTOPS
NA: MILLWORK&BUILT-INS: DETAIL EXISTING BUILT-IN
$71.88
FLOOR COVERING
FLOORING: SEE 'GLOBAL' FIGURES FOR FLOORING- HARDWOOD
$0.00
Sub-Total is
$892.72
C17: STUDY
OAD QBO LIST
PROGRESS CLEANING
$29.12
PROJECT PREPARATION
NIC/BY OTHERS: MOVE OUT THEN RESET ROOM CONTENTS
$0.00
GENERAL DEMOLITION
NA: GENERAL DEMO
$0.00
SYSTEMS DEMOLITION
NA: DISCONNECT&CAP ALL MEP
$0.00
LOAD/HAUL/DISPOSE OF DEBRIS
$18.68
WALL FRAMING
NA: CARPENTRY: ROUGH
$0.00
GENERAL PLUMBING
NA: MEP: PLUMBING
$0.00
HEATING, VENTILATION, AIR CONDITIONING
MEP: HVAC- CLEAN&REINSTALL EXISTING REGISTERS & GRILLS
$27.04
ELECTRICAL
NA: MEP: ELECTRICAL&LIGHTING- REINSTALL EXISTING/NEW FIXTURES; NEW WIRING DEVICES&COVER
PLATES AS REQUIRED
$0.00
INSULATION
NA: INSULATION&WEATHERPROOFING: REPLACE AS REQUIRED
$0.00
WALL COVERINGS
PATCHING&REPAIRS FOR EXISTING WALLS
$22.48
NA: WALL COVER: APPLICATION OF SPECIAL FINISH/TREATMENTS PER ORIGINAL CONDITIONS
$0.00
NA: DRYWALL: WALLS&CEILINGS- PAINT READY
$0.00
INTERIOR DOORS
DOORS: VERIFY FIT&OPERATION OF EXISTING INTERIOR DOOR(S); REINSTALL HARDWARE AFTER PAINTING
$74.16
INTERIOR TRIM, STAIRS AND ACCESSORIES
CARPENTRY: FINISH- CASING FOR WINDOW&DOORS; BASEBOARDS; MISC.TRIMS
$140.88
NA: DETAILS: MISC.- RE-SET COAT CLOSET
$0.00
CABINETS AND COUNTERTOPS
NA: MILLWORK&BUILT-INS: DETAIL EXISTING BUILT-IN
$0.00
FLOOR COVERING
FLOORING: SEE 'GLOBAL' FIGURES FOR FLOORING- HARDWOOD
$0.00
Sub-Total is
$312.36
C18: STAIRWELL&LANDING
OAD QBO LIST
PROGRESS CLEANING
$29.12
PROJECT PREPARATION
NIC/BY OTHERS: MOVE OUT THEN RESET ROOM CONTENTS
$0.00
GENERAL DEMOLITION
GENERAL DEMO
$145.60
SYSTEMS DEMOLITION
NA: DISCONNECT&CAP ALL MEP
$0.00
LOAD/HAUL/DISPOSE OF DEBRIS
$40.52
WALL FRAMING
NA: CARPENTRY: ROUGH
$0.00
GENERAL PLUMBING
NA: MEP: PLUMBING
$0.00
HEATING, VENTILATION, AIR CONDITIONING
MEP: HVAC- CLEAN&REINSTALL EXISTING REGISTERS & GRILLS
$13.52
ELECTRICAL
NA: MEP: ELECTRICAL&LIGHTING- REINSTALL EXISTING/NEW FIXTURES; NEW WIRING DEVICES&COVER
PLATES AS REQUIRED
$0.00
INSULATION
NA: INSULATION&WEATHERPROOFING: REPLACE AS REQUIRED
$0.00
WALL COVERINGS
PATCHING&REPAIRS FOR EXISTING WALLS
$85.36
NA: WALL COVER: APPLICATION OF SPECIAL FINISH/TREATMENTS PER ORIGINAL CONDITIONS
$0.00
NA: DRYWALL: WALLS&CEILINGS- PAINT READY
$0.00
INTERIOR DOORS
NA: DOORS: VERIFY FIT&OPERATION OF EXISTING INTERIOR DOOR(S); REINSTALL HARDWARE AFTER
PAINTING
$0.00
INTERIOR TRIM, STAIRS AND ACCESSORIES
NA: CARPENTRY: FINISH- CASING FOR WINDOW&DOORS; BASEBOARDS; MISC.TRIMS
$0.00
NA: DETAILS: MISC.- RE-SET COAT CLOSET
$0.00
CABINETS AND COUNTERTOPS
NA: MILLWORK&BUILT-INS: DETAIL EXISTING BUILT-IN
$0.00
FLOOR COVERING
FLOORING: SEE 'GLOBAL' FIGURES FOR FLOORING- HARDWOOD
$0.00
Sub-Total is
$314.12
C19: BACK HALL
OAD QBO LIST
PROGRESS CLEANING
$29.12
PROJECT PREPARATION
NIC/BY OTHERS: MOVE OUT THEN RESET ROOM CONTENTS
$0.00
GENERAL DEMOLITION
GENERAL DEMO
$87.36
SYSTEMS DEMOLITION
NA: DISCONNECT&CAP ALL MEP
$0.00
LOAD/HAUL/DISPOSE OF DEBRIS
$18.68
WALL FRAMING
NA: CARPENTRY: ROUGH
$0.00
GENERAL PLUMBING
NA: MEP: PLUMBING
$0.00
HEATING, VENTILATION, AIR CONDITIONING
MEP: HVAC- CLEAN&REINSTALL EXISTING REGISTERS & GRILLS
$27.04
ELECTRICAL
NA: MEP: ELECTRICAL&LIGHTING- REINSTALL EXISTING/NEW FIXTURES; NEW WIRING DEVICES&COVER
PLATES AS REQUIRED
$0.00
INSULATION
NA: INSULATION&WEATHERPROOFING: REPLACE AS REQUIRED
$0.00
WALL COVERINGS
PATCHING&REPAIRS FOR EXISTING WALLS
$0.00
NA: WALL COVER: APPLICATION OF SPECIAL FINISH/TREATMENTS PER ORIGINAL CONDITIONS
$0.00
NA: DRYWALL: WALLS&CEILINGS- PAINT READY
$0.00
INTERIOR DOORS
NA: DOORS: VERIFY FIT&OPERATION OF EXISTING INTERIOR DOOR(S); REINSTALL HARDWARE AFTER
PAINTING
$0.00
INTERIOR TRIM, STAIRS AND ACCESSORIES
NA: CARPENTRY: FINISH- CASING FOR WINDOW&DOORS; BASEBOARDS; MISC.TRIMS
$0.00
NA: DETAILS: MISC.- RE-SET COAT CLOSET
$0.00
CABINETS AND COUNTERTOPS
NA: MILLWORK&BUILT-INS: DETAIL EXISTING BUILT-IN
$0.00
FLOOR COVERING
FLOORING: SEE 'GLOBAL' FIGURES FOR FLOORING- HARDWOOD
$0.00
Sub-Total is
$162.20
C20: BR.01
OAD QBO LIST
PROGRESS CLEANING
$29.12
PROJECT PREPARATION
NIC/BY OTHERS: MOVE OUT THEN RESET ROOM CONTENTS
$0.00
GENERAL DEMOLITION
GENERAL DEMO
$29.12
SYSTEMS DEMOLITION
NA: DISCONNECT&CAP ALL MEP
$0.00
LOAD/HAUL/DISPOSE OF DEBRIS
$18.68
WALL FRAMING
NA: CARPENTRY: ROUGH
$0.00
GENERAL PLUMBING
NA: MEP: PLUMBING
$0.00
HEATING, VENTILATION, AIR CONDITIONING
MEP: HVAC- CLEAN&REINSTALL EXISTING REGISTERS & GRILLS
$27.04
ELECTRICAL
NA: MEP: ELECTRICAL&LIGHTING- REINSTALL EXISTING/NEW FIXTURES; NEW WIRING DEVICES&COVER
PLATES AS REQUIRED
$0.00
INSULATION
NA: NSULATION&WEATHERPROOFING: REPLACE AS REQUIRED
$0.00
WALL COVERINGS
PATCHING&REPAIRS FOR EXISTING WALLS
$44.96
NA: WALL COVER: APPLICATION OF SPECIAL FINISH/TREATMENTS PER ORIGINAL CONDITIONS
$0.00
NA: DRYWALL: WALLS&CEILINGS- PAINT READY
$0.00
INTERIOR DOORS
DOORS: VERIFY FIT&OPERATION OF EXISTING INTERIOR DOOR(S); REINSTALL HARDWARE AFTER PAINTING
$74.16
INTERIOR TRIM, STAIRS AND ACCESSORIES
CARPENTRY: FINISH- CASING FOR WINDOW&DOORS; BASEBOARDS; MISC.TRIMS
$140.88
DETAILS: MISC.- RE-SET COAT CLOSET
$108.00
CABINETS AND COUNTERTOPS
NA: MILLWORK&BUILT-INS: DETAIL EXISTING BUILT-IN
$0.00
FLOOR COVERING
FLOORING: SEE 'GLOBAL' FIGURES FOR FLOORING- HARDWOOD
$0.00
Sub-Total is
$471.96
C21: HALL BATH
OAD QBO LIST
PROGRESS CLEANING
$29.12
TILE: REPLACE WALL TILE / TILE SURROUND INCLUDING NEW BACKER @ TUB: $1,100 ALLOWANCE FOR TILE
$2,687.60
PROJECT PREPARATION
NIC/BY OTHERS: MOVE OUT THEN RESET ROOM CONTENTS
$0.00
GENERAL DEMOLITION
GENERAL DEMO
$87.36
SYSTEMS DEMOLITION
DISCONNECT&CAP ALL MEP
$249.84
LOAD/HAUL/DISPOSE OF DEBRIS
$18.68
WALL FRAMING
CARPENTRY: ROUGH
$108.16
GENERAL PLUMBING
MEP: PLUMBING
$653.76
HEATING, VENTILATION, AIR CONDITIONING
MEP: HVAC- CLEAN&REINSTALL EXISTING REGISTERS & GRILLS
$13.52
ELECTRICAL
NA: MEP: ELECTRICAL&LIGHTING- REINSTALL EXISTING/NEW FIXTURES; NEW WIRING DEVICES&COVER
PLATES AS REQUIRED
$0.00
INSULATION
NA: INSULATION&WEATHERPROOFING: REPLACE AS REQUIRED
$0.00
WALL COVERINGS
PATCHING&REPAIRS FOR EXISTING WALLS
$179.84
WALL COVER: TILE
$735.84
NA: DRYWALL: WALLS&CEILINGS- PAINT READY
$0.00
INTERIOR DOORS
DOORS: VERIFY FIT&OPERATION OF EXISTING INTERIOR DOOR(S); REINSTALL HARDWARE AFTER PAINTING
$74.16
INTERIOR TRIM, STAIRS AND ACCESSORIES
CARPENTRY: FINISH- CASING FOR WINDOW&DOORS; BASEBOARDS; MISC.TRIMS
$140.88
DETAILS: MISC.- RE-SET MISC.FIXTURES
$67.68
CABINETS AND COUNTERTOPS
MILLWORK&BUILT-INS: NEW VANITY W/EXISTING TOP
$1,153.92
FLOOR COVERING
FLOORING: NEW TILE FLOOR & TILE BASE; PER EXISTING FLOOR
$1,561.54
Sub-Total is
$7,761.90
C22: BASEMENT.HOME THEATER
OAD QBO LIST
PROGRESS CLEANING
$29.12
PROJECT PREPARATION
NIC/BY OTHERS: MOVE OUT THEN RESET ROOM CONTENTS
$0.00
GENERAL DEMOLITION
NA: GENERAL DEMO
$0.00
SYSTEMS DEMOLITION
NA: DISCONNECT&CAP ALL MEP
$0.00
LOAD/HAUL/DISPOSE OF DEBRIS
$18.68
WALL FRAMING
NA: CARPENTRY: ROUGH
$0.00
GENERAL PLUMBING
NA: MEP: PLUMBING
$0.00
HEATING, VENTILATION, AIR CONDITIONING
MEP: HVAC- CLEAN&REINSTALL EXISTING REGISTERS & GRILLS
$27.04
ELECTRICAL
NA: MEP: ELECTRICAL&LIGHTING- REINSTALL EXISTING/NEW FIXTURES; NEW WIRING DEVICES&COVER
PLATES AS REQUIRED
$0.00
INSULATION
NA: INSULATION&WEATHERPROOFING: REPLACE AS REQUIRED
$0.00
WALL COVERINGS
PATCHING&REPAIRS FOR EXISTING WALLS
$134.88
NA: WALL COVER: APPLICATION OF SPECIAL FINISH/TREATMENTS PER ORIGINAL CONDITIONS
$0.00
NA: DRYWALL: WALLS&CEILINGS- PAINT READY
$0.00
INTERIOR DOORS
NA: DOORS: VERIFY FIT&OPERATION OF EXISTING INTERIOR DOOR(S); REINSTALL HARDWARE AFTER
PAINTING
$0.00
INTERIOR TRIM, STAIRS AND ACCESSORIES
CARPENTRY: FINISH- CASING FOR WINDOW&DOORS; BASEBOARDS; MISC.TRIMS
$140.88
DETAILS: MISC.- RE-SET TV&EQUIPMENT
$222.24
CABINETS AND COUNTERTOPS
MILLWORK&BUILT-INS: DETAIL EXISTING BUILT-IN
$65.16
FLOOR COVERING
FLOORING: SEE 'GLOBAL' FIGURES FOR FLOORING- CARPET
$0.00
Sub-Total is
$638.00
C23: BASEMENT.KITCHEN
OAD QBO LIST
PROGRESS CLEANING
$29.12
PROJECT PREPARATION
NIC/BY OTHERS: MOVE OUT THEN RESET ROOM CONTENTS
$0.00
GENERAL DEMOLITION
GENERAL DEMO
$174.72
SYSTEMS DEMOLITION
DISCONNECT&CAP ALL MEP
$204.48
LOAD/HAUL/DISPOSE OF DEBRIS
$40.52
WALL FRAMING
CARPENTRY: ROUGH
$179.84
GENERAL PLUMBING
MEP: PLUMBING
$278.40
HEATING, VENTILATION, AIR CONDITIONING
MEP: HVAC- CLEAN&REINSTALL EXISTING REGISTERS & GRILLS
$13.52
ELECTRICAL
MEP: ELECTRICAL&LIGHTING- REINSTALL EXISTING/NEW FIXTURES; NEW WIRING DEVICES&COVER PLATES
AS REQUIRED
$378.72
INSULATION
NA: INSULATION&WEATHERPROOFING: REPLACE AS REQUIRED
$0.00
WALL COVERINGS
PATCHING&REPAIRS FOR EXISTING WALLS
$179.84
WALL COVER: TILE BACKSPLASH
$648.00
DRYWALL: WALLS&CEILINGS- PAINT READY
$404.80
INTERIOR DOORS
DOORS: VERIFY FIT&OPERATION OF EXISTING INTERIOR DOOR(S); REINSTALL HARDWARE AFTER PAINTING
$37.08
INTERIOR TRIM, STAIRS AND ACCESSORIES
CARPENTRY: FINISH- CASING FOR WINDOW&DOORS; BASEBOARDS; MISC.TRIMS
$784.80
DETAILS: MISC.- REMOVE&REINSTALL EXISTING GRANITE & APPLIANCES
$999.36
CABINETS AND COUNTERTOPS
MILLWORK&BUILT-INS: NEW CABINETRY PER ORIGINAL
$11,669.76
FLOOR COVERING
FLOORING: ENGINEERED WOOD FLOOR
$1,138.08
Sub-Total is
$17,161.04
C24: BASEMENT.MAIN
OAD QBO LIST
PROGRESS CLEANING
$29.12
PROJECT PREPARATION
NIC/BY OTHERS: MOVE OUT THEN RESET ROOM CONTENTS
$0.00
GENERAL DEMOLITION
GENERAL DEMO
$58.24
SYSTEMS DEMOLITION
NA: DISCONNECT&CAP ALL MEP
$0.00
LOAD/HAUL/DISPOSE OF DEBRIS
$18.68
WALL FRAMING
CARPENTRY: ROUGH
$179.84
GENERAL PLUMBING
NA: MEP: PLUMBING
$0.00
HEATING, VENTILATION, AIR CONDITIONING
MEP: HVAC- CLEAN&REINSTALL EXISTING REGISTERS & GRILLS
$40.56
ELECTRICAL
MEP: ELECTRICAL&LIGHTING- REINSTALL EXISTING/NEW FIXTURES; NEW WIRING DEVICES&COVER PLATES
AS REQUIRED
$1,140.48
INSULATION
NA: INSULATION&WEATHERPROOFING: REPLACE AS REQUIRED
$0.00
WALL COVERINGS
PATCHING&REPAIRS FOR EXISTING WALLS
$377.92
NA: WALL COVER: APPLICATION OF SPECIAL FINISH/TREATMENTS PER ORIGINAL CONDITIONS
$0.00
DRYWALL: WALLS&CEILINGS- PAINT READY
$1,654.80
INTERIOR DOORS
DOORS: VERIFY FIT&OPERATION OF EXISTING INTERIOR DOOR(S); REINSTALL HARDWARE AFTER PAINTING
$148.32
INTERIOR TRIM, STAIRS AND ACCESSORIES
CARPENTRY: FINISH- CASING FOR WINDOW&DOORS; BASEBOARDS; MISC.TRIMS
$1,690.56
DETAILS: MISC.- CEILING SPEAKERS
$888.00
CABINETS AND COUNTERTOPS
NA: MILLWORK&BUILT-INS: DETAIL EXISTING BUILT-IN
$0.00
FLOOR COVERING
FLOORING: SEE 'GLOBAL' FIGURES FOR FLOORING- CARPET
$0.00
Sub-Total is
$6,226.52
C25: BASEMENT.MIDDLE ROOM
OAD QBO LIST
PROGRESS CLEANING
$29.12
PROJECT PREPARATION
NIC/BY OTHERS: MOVE OUT THEN RESET ROOM CONTENTS
$0.00
GENERAL DEMOLITION
GENERAL DEMO
$29.12
SYSTEMS DEMOLITION
NA: DISCONNECT&CAP ALL MEP
$0.00
LOAD/HAUL/DISPOSE OF DEBRIS
$18.68
WALL FRAMING
CARPENTRY: ROUGH
$108.16
GENERAL PLUMBING
NA: MEP: PLUMBING
$0.00
HEATING, VENTILATION, AIR CONDITIONING
MEP: HVAC- CLEAN&REINSTALL EXISTING REGISTERS & GRILLS
$27.04
ELECTRICAL
MEP: ELECTRICAL&LIGHTING- REINSTALL EXISTING/NEW FIXTURES; NEW WIRING DEVICES&COVER PLATES
AS REQUIRED
$786.96
INSULATION
NA: INSULATION&WEATHERPROOFING: REPLACE AS REQUIRED
$0.00
WALL COVERINGS
PATCHING&REPAIRS FOR EXISTING WALLS
$306.24
NA: WALL COVER: APPLICATION OF SPECIAL FINISH/TREATMENTS PER ORIGINAL CONDITIONS
$0.00
DRYWALL: WALLS&CEILINGS- PAINT READY
$551.60
INTERIOR DOORS
DOORS: VERIFY FIT&OPERATION OF EXISTING INTERIOR DOOR(S); REINSTALL HARDWARE AFTER PAINTING
$148.32
INTERIOR TRIM, STAIRS AND ACCESSORIES
CARPENTRY: FINISH- CASING FOR WINDOW&DOORS; BASEBOARDS; MISC.TRIMS
$140.88
DETAILS: MISC.- CEILING SPEAKERS
$444.00
CABINETS AND COUNTERTOPS
NA: MILLWORK&BUILT-INS: DETAIL EXISTING BUILT-IN
$0.00
FLOOR COVERING
FLOORING: SEE 'GLOBAL' FIGURES FOR FLOORING- CARPET
$0.00
Sub-Total is
$2,590.12
C26: BASEMENT.BATHROOM
OAD QBO LIST
PROGRESS CLEANING
$29.12
PROJECT PREPARATION
NA: MOVE OUT THEN RESET ROOM CONTENTS
$0.00
GENERAL DEMOLITION
NA: GENERAL DEMO
$0.00
SYSTEMS DEMOLITION
NA: DISCONNECT&CAP ALL MEP
$0.00
NA: LOAD/HAUL/DISPOSE OF DEBRIS
$0.00
WALL FRAMING
NA: CARPENTRY: ROUGH
$0.00
GENERAL PLUMBING
NA: MEP: PLUMBING
$0.00
HEATING, VENTILATION, AIR CONDITIONING
MEP: HVAC- CLEAN&REINSTALL EXISTING REGISTERS & GRILLS
$13.52
ELECTRICAL
NA: MEP: ELECTRICAL&LIGHTING- REINSTALL EXISTING/NEW FIXTURES; NEW WIRING DEVICES&COVER
PLATES AS REQUIRED
$0.00
INSULATION
NA: INSULATION&WEATHERPROOFING: REPLACE AS REQUIRED
$0.00
WALL COVERINGS
PATCHING&REPAIRS FOR EXISTING WALLS
$13.52
NA: WALL COVER: APPLICATION OF SPECIAL FINISH/TREATMENTS PER ORIGINAL CONDITIONS
$0.00
NA: DRYWALL: WALLS&CEILINGS- PAINT READY
$0.00
INTERIOR DOORS
DOORS: VERIFY FIT&OPERATION OF EXISTING INTERIOR DOOR(S); REINSTALL HARDWARE AFTER PAINTING
$37.08
INTERIOR TRIM, STAIRS AND ACCESSORIES
NA: CARPENTRY: FINISH- CASING FOR WINDOW&DOORS; BASEBOARDS; MISC.TRIMS
$0.00
DETAILS: MISC.- REPLACE MARBLE TILE TRANSITION@ BATHROOM DOOR
$117.12
CABINETS AND COUNTERTOPS
NA: MILLWORK&BUILT-INS: DETAIL EXISTING BUILT-IN
$0.00
FLOOR COVERING
NA: FLOORING: EXISTING TILE FLOOR
$0.00
Sub-Total is
$210.36
C27: BASEMENT.UTILITY&STORAGE
OAD QBO LIST
PROGRESS CLEANING
$29.12
HVAC: (2) UNITS; REMOVE DAMAGED DUCT INSULATION; SUPPLY&INSTALL NEW DUCT INSULATION TO
ORIGINAL CONDITIONS
$1,038.24
PROJECT PREPARATION
NA: MOVE OUT THEN RESET ROOM CONTENTS
$0.00
GENERAL DEMOLITION
NA: GENERAL DEMO
$0.00
SYSTEMS DEMOLITION
NA: DISCONNECT&CAP ALL MEP
$0.00
NA: LOAD/HAUL/DISPOSE OF DEBRIS
$0.00
WALL FRAMING
NA: CARPENTRY: ROUGH
$0.00
GENERAL PLUMBING
NA: MEP: PLUMBING
$0.00
HEATING, VENTILATION, AIR CONDITIONING
MEP: HVAC- SERVICE CALL FOR (1) UNITS TO VERIFY FUNCTION AND TEST FOR WATER DAMAGE; COST FOR
ANY REPAIRS WILL BE ADDITIONAL
$399.00
ELECTRICAL
NA: MEP: ELECTRICAL&LIGHTING- REINSTALL EXISTING/NEW FIXTURES; NEW WIRING DEVICES&COVER
PLATES AS REQUIRED
$0.00
INSULATION
NA: INSULATION&WEATHERPROOFING: REPLACE AS REQUIRED
$0.00
WALL COVERINGS
PATCHING&REPAIRS FOR EXISTING WALLS
$0.00
NA: WALL COVER: APPLICATION OF SPECIAL FINISH/TREATMENTS PER ORIGINAL CONDITIONS
$0.00
NA: DRYWALL: WALLS&CEILINGS- PAINT READY
$0.00
INTERIOR DOORS
NA: DOORS: VERIFY FIT&OPERATION OF EXISTING INTERIOR DOOR(S); REINSTALL HARDWARE AFTER
PAINTING
$0.00
INTERIOR TRIM, STAIRS AND ACCESSORIES
NA: CARPENTRY: FINISH- CASING FOR WINDOW&DOORS; BASEBOARDS; MISC.TRIMS
$0.00
NA: DETAILS: MISC.- RE-SET COAT CLOSET
$0.00
CABINETS AND COUNTERTOPS
NA: MILLWORK&BUILT-INS: DETAIL EXISTING BUILT-IN
$0.00
FLOOR COVERING
NA: FLOORING: EXISTING CONCRETE
$0.00
Sub-Total is
$1,466.36
C28: BONUS ROOM-
* PREP&PAINT
* NEW CARPET
OAD QBO LIST
INTERIOR PAINTING: PREP, PRIMER&PAINT
$1,596.00
PROJECT PREPARATION
MOVE OUT THEN RESET ROOM CONTENTS
$40.52
SYSTEMS DEMOLITION
LOAD/HAUL/DISPOSE OF DEBRIS
$28.24
WALL COVERINGS
MINOR PATCHING&REPAIRS FOR EXISTING WALLS
$13.52
NA: WALL COVER: APPLICATION OF SPECIAL FINISH/TREATMENTS PER ORIGINAL CONDITIONS
$0.00
INTERIOR TRIM, STAIRS AND ACCESSORIES
NA: DETAILS: MISC.
$0.00
FLOOR COVERING
FLOORING: CARPET
$1,336.54
CLEANUP
ROOM CLEAN-UP DURING RENOVATIONS
$20.96
Sub-Total is
$3,035.78
C29: BR.02 ROOM-
* PREP&PAINT
* NEW CARPET
OAD QBO LIST
INTERIOR PAINTING: PREP, PRIMER&PAINT
$2,166.00
PROJECT PREPARATION
MOVE OUT THEN RESET ROOM CONTENTS
$40.52
SYSTEMS DEMOLITION
LOAD/HAUL/DISPOSE OF DEBRIS
$28.24
WALL COVERINGS
MINOR PATCHING&REPAIRS FOR EXISTING WALLS
$13.52
NA: WALL COVER: APPLICATION OF SPECIAL FINISH/TREATMENTS PER ORIGINAL CONDITIONS
$0.00
INTERIOR TRIM, STAIRS AND ACCESSORIES
NA: DETAILS: MISC.
$0.00
FLOOR COVERING
FLOORING: CARPET
$2,450.32
CLEANUP
ROOM CLEAN-UP DURING RENOVATIONS
$20.96
Sub-Total is
$4,719.56
C30: LAUNDRY ROOM-
* PREP&PAINT
* NEW FLOOR COVER
OAD QBO LIST
INTERIOR PAINTING: PREP, PRIMER&PAINT
$912.00
PROJECT PREPARATION
MOVE OUT THEN RESET ROOM CONTENTS
$85.60
SYSTEMS DEMOLITION
LOAD/HAUL/DISPOSE OF DEBRIS
$28.24
WALL COVERINGS
MINOR PATCHING&REPAIRS FOR EXISTING WALLS
$13.52
NA: WALL COVER: APPLICATION OF SPECIAL FINISH/TREATMENTS PER ORIGINAL CONDITIONS
$0.00
INTERIOR TRIM, STAIRS AND ACCESSORIES
NA: DETAILS: MISC.
$0.00
FLOOR COVERING
FLOORING: CARPET
$566.40
CLEANUP
ROOM CLEAN-UP DURING RENOVATIONS
$20.96
Sub-Total is
$1,626.72
C31: GUEST BEDROOM-
* PREP&PAINT
* NEW CARPET
OAD QBO LIST
INTERIOR PAINTING: PREP, PRIMER&PAINT
$2,052.00
PROJECT PREPARATION
MOVE OUT THEN RESET ROOM CONTENTS
$40.52
SYSTEMS DEMOLITION
LOAD/HAUL/DISPOSE OF DEBRIS
$28.24
WALL COVERINGS
MINOR PATCHING&REPAIRS FOR EXISTING WALLS
$13.52
NA: WALL COVER: APPLICATION OF SPECIAL FINISH/TREATMENTS PER ORIGINAL CONDITIONS
$0.00
INTERIOR TRIM, STAIRS AND ACCESSORIES
NA: DETAILS: MISC.
$0.00
FLOOR COVERING
FLOORING: CARPET
$2,561.69
CLEANUP
ROOM CLEAN-UP DURING RENOVATIONS
$20.96
Sub-Total is
$4,716.93
C32: GUEST BATH ROOM-
* PREP&PAINT
OAD QBO LIST
INTERIOR PAINTING: PREP, PRIMER&PAINT
$1,026.00
PROJECT PREPARATION
MOVE OUT THEN RESET ROOM CONTENTS
$85.60
SYSTEMS DEMOLITION
LOAD/HAUL/DISPOSE OF DEBRIS
$28.24
WALL COVERINGS
MINOR PATCHING&REPAIRS FOR EXISTING WALLS
$13.52
NA: WALL COVER: APPLICATION OF SPECIAL FINISH/TREATMENTS PER ORIGINAL CONDITIONS
$0.00
INTERIOR TRIM, STAIRS AND ACCESSORIES
NA: DETAILS: MISC.
$0.00
FLOOR COVERING
NA: FLOORING: CARPET
$0.00
CLEANUP
ROOM CLEAN-UP DURING RENOVATIONS
$20.96
Sub-Total is
$1,174.32
C33: MASTER BEDROOM-
* PREP&PAINT
* NEW CARPET
OAD QBO LIST
INTERIOR PAINTING: PREP, PRIMER&PAINT
$3,192.00
PROJECT PREPARATION
MOVE OUT THEN RESET ROOM CONTENTS
$85.60
SYSTEMS DEMOLITION
LOAD/HAUL/DISPOSE OF DEBRIS
$28.24
Alternates
A01 - UPGRADE ALLOWANCE FOR TILE FLOOR FOR MUDROOM & MUD ROOM POWDER ROOM
Total Cost is $903.19
WALL COVERINGS
MINOR PATCHING&REPAIRS FOR EXISTING WALLS
$99.04
NA: WALL COVER: APPLICATION OF SPECIAL FINISH/TREATMENTS PER ORIGINAL CONDITIONS
$0.00
INTERIOR TRIM, STAIRS AND ACCESSORIES
NA: DETAILS: MISC.
$0.00
FLOOR COVERING
FLOORING: CARPET
$6,014.41
CLEANUP
ROOM CLEAN-UP DURING RENOVATIONS
$28.24
Sub-Total is
$9,447.53
C34: MASTER BATHROOM-
* PREP&PAINT
OAD QBO LIST
INTERIOR PAINTING: PREP, PRIMER&PAINT
$1,938.00
PROJECT PREPARATION
MOVE OUT THEN RESET ROOM CONTENTS
$85.60
SYSTEMS DEMOLITION
LOAD/HAUL/DISPOSE OF DEBRIS
$28.24
WALL COVERINGS
MINOR PATCHING&REPAIRS FOR EXISTING WALLS
$13.52
NA: WALL COVER: APPLICATION OF SPECIAL FINISH/TREATMENTS PER ORIGINAL CONDITIONS
$0.00
INTERIOR TRIM, STAIRS AND ACCESSORIES
NA: DETAILS: MISC.
$0.00
FLOOR COVERING
NA: FLOORING: CARPET
$0.00
CLEANUP
ROOM CLEAN-UP DURING RENOVATIONS
$20.96
Sub-Total is
$2,086.32
Project Cost is $300,948.18
PAYMENT SCHEDULE
OAD.01
45,142.23 UPON SIGNING CONTRACT
45,142.23 ON FIRST DAY OF CONSTRUCTION
45,142.23 ON FIRST DAY OF ROUGH-INS
45,142.23 ON FIRST DAY OF DRYWALL
45,142.23 ON FIRST DAY OF FLOORING INSTALL
75,237.05 ON FIRST DAY OF INTERIOR TRIM INSTALLATION
BALANCE DUE UPON COMPLETION OF PROJECT
THE FOLLOWING PROPOSAL IS SUBMITTED BY:
Signature__________________________________________________ Date:_______________
ACCEPTANCE OF PROPOSAL
The prices, specifications, and conditions are satisfactory and are hereby accepted. You are authorized to do the work as
specified. Payment will be made as outlined in this contract.
Signature__________________________________________________ Date:_______________
Signature__________________________________________________ Date:_______________
Signature__________________________________________________ Date:_______________